Guide to After Before Brick Bricklayer Come Does Installation Roof Sheeting Viner
Roof sheeting is installed before brick veneer in Australian builds to allow structural frame deflection and avoid cracked joints under AS 3700 and AS 1684.
Quick answer
In standard Australian residential construction, roof sheeting is installed before laying brick veneer. Applying the roof dead load first allows timber or steel roof trusses to undergo immediate structural deflection of up to 12mm. This critical sequencing prevents settling loads from crushing non-loadbearing cavity ties and cracking masonry bed joints.
- Skill level
- Advanced
- Time
- 7–10 days (depending on dwelling size and site access)
- Trade
- Building & Construction
- Updated
- 29 November 2026
Tools you will need
- Marshalltown 19/11 Durasoft - 280mm London Pattern Brick Trowel
- Stabila R-Beam Type 300 - 1200mm Heavy Duty Spirit Level
- Belle Minimix 150 - 240V Portable Cement Mixer
- OX Tools Pro Series - 100mm Masonry Line Blocks and Braided Nylon Line
- DeWalt DWE4206-XE - 125mm Mortar Raking Angle Grinder
- Husqvarna KV760 - Concrete and Masonry Wet Demolition Saw
🧱 Sequencing Brick Veneer Masonry and Roof Sheeting Installation
Does roof sheeting get installed before or after bricklaying on a brick veneer house?
In standard Australian residential construction, roof sheeting (or roof tiles) is almost always installed before the bricklayer lays the brick veneer skin. Loading the timber or light-gauge steel frame with the roof structure allows initial structural deflection and settlement to take place before non-loadbearing masonry is tied to the studs. Following this exact sequence prevents frame movement from cracking mortar joints, complies with AS 3700 (Masonry Structures) and AS 1684 (Residential Timber-Framed Construction), and provides a safer, semi-dry work environment on-site.
Skill Level
Advanced — ~7–10 days (depending on dwelling size and site access)What tools are required for brick veneer construction under Australian standards?
What materials and mortar mixes comply with AS 3700 for brick veneer skins?
What work health and safety regulations apply when laying brick veneer under roof trusses?
⚠️ Safety & Compliance Notes:
Step-by-Step Guide
1️⃣ Complete Frame, Truss Tie-Downs, and Roof Sheeting
Before a bricklayer touches the slab edge rebate, ensure the frame carpenter and roof plumber have completed the roof load. Install rafters/trusses, roof battens, sarking, gutters, and metal roof sheeting (or concrete tiles). Applying this dead load compresses the structural timber framing down to its working resting point. If bricks are laid beforehand, the subsequent roof weight compresses the top plate, causing wall ties to buckle and cracking green mortar joints.
2️⃣ Inspect Slab Rebate, Cavities, and Wall Wrap
Verify the concrete edge rebate depth complies with AS 2870 (typically minimum 50mm rebate step-down, maintaining a 40mm–60mm clear cavity between studs and the brick skin). Ensure the builder has installed pliable building membrane (vapour barrier/wrap) over the studs with minimum 150mm laps, taped securely behind where the brick skin will stand.
3️⃣ Install Damp-Proof Course (DPC) and Base Weep Holes
Fasten the continuous 0.5mm embossed DPC to the timber bottom plate or concrete slab face, projecting down the rebate and extending outward under the first course of bricks. Lay your base mortar bed (10mm–20mm nominal) using a standard 1:1:6 mix. Form open perpendicular weep holes every 1200mm (or every 3rd or 4th brick) directly on the flashing line to drain cavity moisture outward.
4️⃣ Run Out Base Courses and Establish Corner Profiles
Set up your timber story poles or gauge rods marked at 86mm gauge intervals (76mm brick + 10mm bed joint). Lay out your dry bond along the slab perimeter to avoid narrow cut bricks (under 50mm) at window openings or external corners. Run the stretcher bond true and plumb, utilizing a string line pulled taut between corner profiles.
5️⃣ Secure Face Brickwork to Frame with Articulated Wall Ties
As brickwork rises, mechanically screw wall ties into the timber or light-gauge steel studs at maximum 600mm horizontal centres and 400mm vertical centres, adhering strictly to AS 3700. Ties must fall slightly toward the brick skin (preventing water migrating inside to framing) and be embedded a minimum of 50mm into the mortar bed joint. Keep the 50mm cavity clear of mortar snots using a cavity iron or clean timber batten pulled upward.
6️⃣ Finish to Soffits and Underside of Eaves
Build the final courses up beneath the pre-installed eaves lining or fascia. Leave a clean 10mm–15mm expansion clearance between the top course of bricks and the underside of the timber/sheet eaves lining. Never wedge mortar tight between the top brick and the roof frame—this prevents roof live loads (such as wind down-drafts or foot traffic) from transferring structural loads directly onto the veneer skin.
Common Mistakes to Avoid
Pro Tips
Recommended Tools
Frequently asked questions
- Does roof sheeting get installed before or after bricklaying?
- Roof sheeting is installed before bricklaying in Australian brick veneer construction. Loading the roof allows the timber or steel frame to deflect naturally under dead loads before the external masonry skin is tied off. This sequence prevents downward structural pressure from shearing wall ties and cracking mortar joints under AS 3700.
- Why does the roof need to be loaded before brick veneer is laid?
- The roof must be loaded before bricklaying to account for the 5mm to 12mm downward deflection of timber roof trusses under dead weight. If brick veneer is built first, rigid wall ties transfer roof loads into non-loadbearing masonry, breaking the mortar bond and breaching National Construction Code structural settlement requirements.
- What happens if a bricklayer lays bricks before the roof goes on?
- Laying brick veneer before the roof is installed causes frame settlement to crush the cavity wall ties downwards. This crushes horizontal bed joints, causes stepped cracking in upper courses, distorts damp-proof courses, and can dislodge perimeter sarking, allowing storm water into the timber framing system.
- What is the Australian Standard cavity width for brick veneer?
- The standard cavity width for brick veneer construction in Australia is between 40mm and 60mm in accordance with AS 3700 and NCC Volume Two. Cavities must be kept completely clear of mortar droppings to ensure proper cavity drainage, with corrosion-resistant wall ties spaced every 600mm horizontally and 400mm vertically.
- What mortar mix ratio should be used for external brick veneer?
- External brick veneer requires an M3 durability class mortar under AS 3700, mixed at 1 part cement, 1 part hydrated lime, and 6 parts brickies sand by volume. In aggressive coastal zones within 1 kilometre of breaking surf, an M4 mix ratio of 1:0.5:4.5 is strictly required.
- Can bricklaying and roof plumbing happen at the same time?
- Bricklaying and roof plumbing can overlap only if structural work health and safety protocols prevent trades working directly beneath each other. Plumbers typically install metal fascia, gutters, and roof sheets first, enabling bricklayers to work safely below under a watertight cover without the risk of falling materials.
Written by Bricko, the Building & Construction specialist at VIC.Tools.