How to build a concrete block retaining wall

A concrete block retaining wall is a durable way to hold back soil, level a sloping yard, and create more usable outdoor space. For Australian DIY homeowners, the key to a long-lasting wall is proper planning, a compacted base, good drainage, and staying within council, manufacturer, and engineering

Skill level
Intermediate
Time
2–4 days for a small wall of around 5–10 m long and up to 1000 mm high
Trade
Building & Construction
Updated
28 November 2026

Tools you will need

  • String line, line level, pegs and marking paint
  • Tape measure at least 5 m
  • Shovel, trenching shovel and mattock
  • Plate compactor, ideally 60
  • Wheelbarrow
  • Spirit level, preferably 1200 mm
  • Rubber mallet
  • Brick bolster or block splitter if trimming blocks
  • Angle grinder with masonry diamond blade for cuts
  • Screed board or straightedge

🧱 How to Build a Concrete Block Retaining Wall in Australia

What is a concrete block retaining wall and why is it used in Australia?

A concrete block retaining wall is a durable way to hold back soil, level a sloping yard, and create more usable outdoor space. For Australian DIY homeowners, the key to a long-lasting wall is proper planning, a compacted base, good drainage, and staying within council, manufacturer, and engineering requirements.

This guide covers a typical small residential concrete block retaining wall using interlocking retaining wall blocks. For walls carrying heavy loads, supporting driveways, built on steep sites, or generally over 1000 mm high, get engineering certification and check local council rules before starting.

What skill level is required to build a concrete block retaining wall in Australia?

Intermediate — Estimated time: 2–4 days for a small wall of around 5–10 m long and up to 1000 mm high

What essential tools are needed for building a concrete block retaining wall?

String line, line level, pegs and marking paint
Tape measure at least 5 m
Builder’s level, laser level, or dumpy level for accurate set-out
Shovel, trenching shovel and mattock
Plate compactor, ideally 60–90 kg class
Wheelbarrow
Spirit level, preferably 1200 mm
Rubber mallet
Brick bolster or block splitter if trimming blocks
Angle grinder with masonry diamond blade for cuts
Concrete mixer if mixing on site, or order premixed concrete
Screed board or straightedge
Hand tamper for tight areas
Drainage shovel or trenching tool
Broom and hose for clean-up
PPE: gloves, safety glasses, steel-cap boots, hearing protection, dust mask or P2 respirator

What materials are necessary for constructing a concrete block retaining wall?

Concrete retaining wall blocks, quantity based on wall length, height and block size
Matching corner blocks or capping units if required
Base material: compactable crushed rock or road base, typically 100–150 mm deep
Concrete for footing or levelling pad if specified by manufacturer or engineer
Structural concrete mix if hand mixing: 1:1.5:2.5
General-purpose concrete for minor non-structural work: 1:2:3
Drainage aggregate, clean crushed rock 10–20 mm
Agricultural drain pipe or slotted drainage pipe, usually 100 mm diameter
Geotextile filter fabric
Backfill soil suitable for compaction
String line pegs and marking paint
Construction adhesive if required for caps
Reinforcement, geogrid, core fill or concrete grout if required by the wall system or engineer
Starter bar or footing reinforcement if specified by engineering
Topsoil and mulch for final landscaping

Safety Requirements

Wear gloves, safety glasses, steel-cap boots, hearing protection, and a dust mask or P2 respirator when cutting blocks.
Concrete blocks are heavy. Use correct manual handling techniques, lift with your legs, and get help for awkward or repetitive lifting.
Keep hands clear when placing blocks and compacting base material.
Use all power tools with guards fitted and follow the manufacturer’s instructions.
Wet saw cutting is preferred where possible to reduce silica dust exposure.
Never undermine nearby structures, fences, or footings without advice.
For walls near boundaries, pools, services, steep embankments, or with a drop that creates fall risk, additional controls may be required.
If excavation is deep or the site is unstable, stop and seek professional advice.
Structural retaining walls must comply with engineering design and relevant Australian Standards, including AS 4678 for earth-retaining structures and AS 3600 where reinforced concrete elements are used. Masonry work should align with AS 3700 where applicable.
Council approval and engineering requirements vary by state and local authority. Always confirm before building.

Step-by-Step Guide

Step 1: 1️⃣ Plan the Wall and Check Approvals

Start by confirming what the wall needs to do: hold back a garden bed, create a level lawn area, or retain a significant soil bank. Measure the total wall length, the retained height, and whether the soil behind the wall will also carry extra load such as a fence, vehicle area, shed, spa, or sloping ground above. This extra load is called a surcharge and can significantly change the design.

For many Australian councils, walls over about 1000 mm high, or any wall near a boundary, structure, or driveway, may require approval and engineering certification. Retaining walls on sloping sites, in reactive clay, or with poor drainage should also be checked by an engineer.

Choose a retaining block system designed for retaining walls, not standard hollow concrete blocks unless you have a proper engineered design. Read the manufacturer’s installation guide carefully, as setback, base depth, drainage, and geogrid requirements vary by system.

Step 2: 2️⃣ Set Out the Wall

Mark the front face of the wall with string lines and pegs. Check the line is straight, or if building a curve, set the radius accurately from the centre point. Mark the excavation width so you have room for the base, the block depth, and drainage behind the wall.

As a general guide for a small garden retaining wall, excavate wide enough for:

the block width
at least 150 mm of base material beyond the front
at least 200–300 mm drainage zone behind the wall

Use a laser level or builder’s level to establish finished wall height and the required excavation depth. Getting this right now saves a lot of fixing later.

Step 3: 3️⃣ Excavate the Trench

Excavate the trench to the required depth and width. For many low retaining block systems, the trench needs to allow for:

100–150 mm compacted road base
embedment of the first course below finished ground, often around 100 mm or about one-tenth of wall height, depending on the system
a levelling pad if specified

The trench bottom should be firm, even, and free of soft spots, organic matter, roots, or loose fill. If the ground is soft or wet, dig deeper until you reach stable material and replace unsuitable soil with compacted road base.

💡 A wall is only as good as what sits underneath it. Most DIY retaining wall failures start with a poor foundation, not bad blocks.

Step 4: 4️⃣ Install and Compact the Base

Place compactable crushed rock or road base in layers. Build up to a compacted thickness of around 100–150 mm for small walls, or as required by the manufacturer or engineer. Compact each layer thoroughly with a plate compactor.

Check the finished base is:

level side to side
straight along the wall line
at the correct height for the first course

Some retaining wall systems use a compacted granular base only, while others may call for a concrete levelling pad. If using concrete, keep the pad consistent in thickness and level, and allow it to firm up before laying blocks.

For hand-mixed structural footing concrete, use 1:1.5:2.5. For minor general-purpose concrete, use 1:2:3.

Step 5: 5️⃣ Lay the First Course Perfectly

Lay the first row of retaining blocks onto the prepared base. This is the most important step of the whole build. Each block must be level front to back, level side to side, and aligned to the string line.

Use a rubber mallet to tap each block into place. Check every block with a spirit level and check the whole run regularly with a straightedge or string line. If one block is high or low, fix it immediately by lifting it and adjusting the base below.

Where needed, bury the first course so the wall has proper embedment and looks neat at finished ground level.

💡 Spend extra time here. A first course that is even 5–10 mm out will compound as the wall rises.

Step 6: 6️⃣ Install Drainage Behind the Wall

Good drainage is essential. Water pressure behind a retaining wall is one of the main causes of failure. Place a slotted agricultural drain pipe, usually 100 mm diameter, at the back of the wall near the base. Grade the pipe so it drains to daylight, a legal stormwater point, or another approved outlet.

Surround the pipe with clean drainage aggregate such as 10–20 mm crushed rock. Wrap or separate the drainage zone from surrounding soil with geotextile filter fabric to stop fines washing in and clogging the system.

A typical drainage zone for a small wall is at least 200–300 mm behind the blocks, but always follow the block manufacturer’s requirements.

Do not use clayey soil, topsoil, or builder’s rubble as drainage backfill.

Step 7: 7️⃣ Lay Additional Courses

Continue laying the next courses according to the block system. Most concrete retaining blocks either:

interlock with pins or lips, or
naturally step back to create batter

Stagger vertical joints between courses so the wall bonds properly. Keep all block faces clean so each course sits flat. Check level, setback, and alignment every few blocks and at the end of every course.

If the system requires pins, clips, adhesive, or locking bars, install them exactly as specified. If the wall needs cores filled with concrete, steel reinforcement, or grout, follow the engineered details.

For walls of significant height, geogrid reinforcement may be required between courses and extended back into the retained soil. This is not optional if shown on the engineering or manufacturer’s design tables.

Step 8: 8️⃣ Backfill and Compact in Layers

As the wall rises, place drainage aggregate directly behind the blocks and compact suitable backfill further behind that in thin layers. A good rule is to compact backfill in layers of about 150 mm at a time.

Use a hand tamper close to the back of the wall so you do not knock the blocks out of line. Keep heavy compactors back from the wall unless the system specifically allows closer compaction after the wall has gained mass and support.

Do not backfill the entire wall height at once. Build and backfill progressively so the pressure is managed and the wall remains stable during construction.

💡 Never trap water behind the wall. If the site is very wet or receives runoff from above, install spoon drains or surface drainage to divert water away before it reaches the wall.

Step 9: 9️⃣ Cut Blocks and Finish Ends

Where the wall length does not suit full block sizes, cut blocks neatly using an angle grinder with a masonry blade or a block splitter. Dry-fit cut pieces before installing them permanently.

Finish exposed ends using matching corner units, return sections, or manufacturer-approved end treatments. If the wall turns a corner, check whether the block system has dedicated left and right corner blocks.

Take your time on visible cuts and corners. These are the details that make the job look professional.

Step 10: 🔟 Install Caps and Complete Final Grading

Once the wall is fully laid, backfilled, and stable, install capping blocks if the system includes them. Use the recommended construction adhesive where required, and keep adhesive beads back from visible edges.

Grade the soil at the top of the wall so surface water drains away from the retained area rather than toward the back of the wall. Add topsoil, turf, mulch, or garden edging as needed.

Clean the wall face, remove excess rubble, and make sure the drain outlet remains clear and accessible.

Common Mistakes to Avoid

1.Building without checking council rules, underground services, or engineering requirements for taller or loaded walls.
2.Skipping drainage pipe and drainage aggregate, which can cause hydrostatic pressure and wall failure.
3.Rushing the first course and trying to fix alignment problems in the upper courses.
4.Using soft soil, loose fill, or uncompacted material under the base.
5.Backfilling with clay or topsoil instead of free-draining aggregate behind the wall.
6.Compacting too aggressively right behind the blocks and pushing the wall out of line.
7.Using standard concrete blocks for a retaining wall without an engineered design.

Pro Tips

Use a laser level if possible. It is much faster and more accurate than checking every point with a short spirit level alone.
Buy an extra 5–10% of blocks for cuts, breakages, and future repairs, especially if the product line changes later.
On long walls, work from the lowest point and step the wall up in increments rather than trying to keep the base trench level across sloping ground.
Hire a plate compactor and block splitter for the weekend instead of buying them. For most DIY builds, hire is far more economical than purchase.
Keep the drainage outlet visible and protected. A perfect wall can still fail if the outlet blocks up with mulch, roots, or sediment.

Recommended Tools

Crommelins Plate Compactor 75 kg — good for compacting road base properly on small residential jobs; better to hire than buy for one-off use.
Bosch or DeWalt Rotary Laser Level Kit — makes setting heights and keeping the first course level much easier.
Makita 230 mm Angle Grinder with diamond masonry blade — useful for clean block cuts and trimming end pieces.
OX Pro 1200 mm Spirit Level — reliable for laying the first course accurately.
Husqvarna Block Splitter or Masonry Saw hire — worth hiring for larger jobs where you have many cuts and want a cleaner finish.

Frequently asked questions

What is involved in build a concrete block retaining wall?
A concrete block retaining wall is a durable way to hold back soil, level a sloping yard, and create more usable outdoor space. For Australian DIY homeowners, the key to a long-lasting wall is proper planning, a compacted base, good drainage, and staying within council, manufacturer, and engineering
What skill level do I need for build a concrete block retaining wall?
Intermediate — Estimated time: 2–4 days for a small wall of around 5–10 m long and up to 1000 mm high
What are common mistakes when build a concrete block retaining wall?
1. Building without checking council rules, underground services, or engineering requirements for taller or loaded walls. 2. Skipping drainage pipe and drainage aggregate, which can cause hydrostatic pressure and wall failure. 3. Rushing the first course and trying to fix alignment problems in the upper courses. 4. Using soft soil, loose fill, or uncompacted material under the base. 5. Backfilling
What tools do I need for build a concrete block retaining wall?
This guide includes a comprehensive tools list. Key building & construction tools are detailed in the Tools Required section.
What is the Australian standard for retaining wall design and construction?
The primary Australian standard for earth-retaining structures is AS/NZS 4678:2002. This standard outlines requirements for design, construction, and performance, particularly for walls over 1000 mm in height or those subject to significant loads. Always consult local council regulations as they may have specific overlays.
How high can a concrete block retaining wall be built without engineering approval in Australia?
Generally, a concrete block retaining wall can be built up to 1000 mm (1 metre) in height without requiring specific engineering certification in most Australian councils, provided it's not surcharged or supporting structures. However, this can vary by local government area, so always check with your local council's planning department.
What type of concrete mix is recommended for a retaining wall footing in Australia?
For structural footings or levelling pads for retaining walls, a structural concrete mix of 1:1.5:2.5 (cement:sand:aggregate) is typically recommended. This ensures adequate strength and durability to support the wall's weight and resist lateral earth pressure, as specified by block manufacturers and AS 3700:2018.
Why is proper drainage crucial for a concrete block retaining wall?
Proper drainage is crucial to prevent hydrostatic pressure build-up behind the wall, which can lead to cracking, bulging, or even failure. According to AS/NZS 4678:2002, a drainage aggregate layer and a perforated agricultural pipe are essential to direct water away from the wall's base, ensuring its long-term stability.

Written by Bricko, the Building & Construction specialist at VIC.Tools.