How to build a concrete patio
Building a concrete patio is a solid DIY project for creating an outdoor entertaining area that will handle Australian conditions well when it is set out, reinforced and cured properly. For a typical ground-level patio slab, the key jobs are planning drainage fall, preparing a compacted base, placin
- Skill level
- Intermediate
- Time
- 2–3 days active work, plus 7 days curing before regular use and 28 days for full cure
- Trade
- Building & Construction
- Updated
- 28 November 2026
Tools you will need
- Tape measure
- String line and line level or rotary laser level
- Marking paint
- Shovel and trenching shovel
- Mattock or pick
- Plate compactor
- Wheelbarrow
- Concrete mixer
- Formwork tools
- Straightedge/screed
What is involved in building a concrete patio in Australia?
Building a concrete patio is a solid DIY project for creating an outdoor entertaining area that will handle Australian conditions well when it is set out, reinforced and cured properly. For a typical ground-level patio slab, the key jobs are planning drainage fall, preparing a compacted base, placing reinforcement correctly, and finishing the concrete before it starts to set.
What skill level is required to build a concrete patio?
Intermediate — Estimated time: 2–3 days active work, plus 7 days curing before regular use and 28 days for full cure
What tools are essential for building a concrete patio?
Materials Required
Safety Requirements
Step-by-Step Guide
Step 1: Plan the patio size, levels and approvals
Decide the finished patio dimensions and use. For a simple entertaining area, common sizes are 3.0 m x 4.0 m, 4.0 m x 5.0 m or larger.
Check:
Set the finished height so the slab drains away from the house. Aim for a fall of 10–15 mm per metre away from the dwelling. A practical target is 1:100 to 1:80 fall.
Step 2: Set out the patio accurately
Mark the patio perimeter with string lines and pegs. Measure diagonals to ensure the slab is square.
Set your finished surface levels using:
Allow for:
If the patio meets the house, confirm the finished concrete level will remain below weepholes and damp-proof course requirements.
Step 3: Excavate the area
Excavate the site to the required depth:
Trim the subgrade level and keep it reasonably even. If you hit soft clay, wet fill or loose material, dig it out and replace it with compactable road base.
For most patios, keep the excavation slightly wider than the slab so you have room for formwork and pegs.
Step 4: Prepare and compact the base
Spread road base in layers and compact it thoroughly with a plate compactor. Do not try to compact the full thickness in one go.
A good DIY method is:
Check levels as you go. The compacted base should already reflect the final drainage fall. Lightly dampen the base if it is too dry for effective compaction, but do not make it muddy.
A well-compacted base is one of the biggest factors in avoiding cracking and settlement.
Step 5: Install formwork
Fix straight form boards around the patio perimeter using timber pegs at about 1000–1200 mm centres, closer if the ground is uneven.
Check that formwork is:
Use the top edge of the formwork as your screed guide. If the slab abuts the house, install 10 mm compressible foam expansion joint between the slab and the wall or existing concrete.
For curved patios, use flexible form boards or purpose-made edging.
Step 6: Install membrane and reinforcement
For a typical outdoor patio, a membrane is optional, but it can be beneficial for covered areas or certain ground conditions. If used, lay 200 µm plastic membrane neatly over the compacted base with taped overlaps.
Place reinforcement mesh on 40–50 mm bar chairs so it stays embedded in the slab. Never leave mesh lying on the ground and assume it will be pulled up later.
Key points:
For unusual site conditions or heavier loads, reinforcement should match an engineer’s design.
Step 7: Organise the pour
Work out whether to hand mix or order ready-mix.
As a rule:
If ordering premix, ask for:
If hand mixing a very small slab, use a 1:2:3 cement:sand:aggregate mix for general-purpose work, adding water gradually. Avoid overwatering, as this weakens the slab and increases shrinkage cracking.
Step 8: Pour and place the concrete
Start at the far end and work back toward your access point. Place concrete evenly and avoid dumping all the load in one spot.
Use a shovel or rake to spread the concrete into corners and around reinforcement. Do not overwork the mix. If using premix, keep the pour moving steadily so cold joints do not form.
During placement:
For larger pours, a concrete vibrator can help with consolidation, but for a basic patio slab, careful rodding and placement are usually enough.
Step 9: Screed the slab
Using a straightedge or screed resting on the formwork, strike off excess concrete with a sawing motion.
The goal is to bring the slab to final level while maintaining the planned fall away from the house. Fill low spots immediately and rescreed.
This stage sets the quality of the finished slab, so take your time.
Step 10: Float, edge and finish the surface
After screeding, allow bleed water to rise and disappear before finishing. Do not start steel trowelling or brooming while water is still sitting on the surface.
Finish in this order:
For most Australian patios, a broom finish is the best DIY option because it gives slip resistance. Drag the broom evenly across the slab once the surface has firmed up enough to hold texture without tearing.
Avoid a polished or very smooth steel-trowel finish on exterior patios, as it can become slippery when wet.
Step 11: Cut control joints
Control joints help manage shrinkage cracking. For a 100 mm slab, saw-cut joints to a depth of about 25 mm as soon as the concrete is hard enough to cut cleanly without edge ravelling, often within 6–18 hours depending on weather.
As a guide:
Any slab will crack somewhere; joints encourage it to crack in controlled lines instead of randomly.
Step 12: Cure the concrete properly
Curing is critical for strength and durability. Once finishing is complete and the surface is firm enough, apply curing compound or cover the slab with plastic sheeting.
Good curing practice:
In hot Australian weather, curing is especially important. Poor curing causes dusting, weak surfaces and extra cracking.
Step 13: Strip forms and complete the edges
After the concrete has gained enough strength, usually 24–48 hours, remove formwork carefully. Backfill the slab edges if needed and tidy the perimeter.
If you want extra stain resistance for outdoor furniture, food spills or leaf tannins, apply a suitable concrete sealer after the slab has properly cured, following the manufacturer’s timing and coverage instructions.
Common Mistakes to Avoid
Pro Tips
Recommended Tools
Frequently asked questions
- What is involved in build a concrete patio?
- Building a concrete patio is a solid DIY project for creating an outdoor entertaining area that will handle Australian conditions well when it is set out, reinforced and cured properly. For a typical ground-level patio slab, the key jobs are planning drainage fall, preparing a compacted base, placin
- What skill level do I need for build a concrete patio?
- Intermediate — Estimated time: 2–3 days active work, plus 7 days curing before regular use and 28 days for full cure
- What are common mistakes when build a concrete patio?
- 1. Skipping proper base compaction — this leads to settlement, rocking furniture and slab cracking. 2. Pouring the slab flat with no fall — water will pond and may run back toward the house. 3. Letting reinforcement sit on the ground — mesh only works when it is embedded in the concrete. 4. Adding too much water to the mix or surface — this weakens the slab and causes dusting and s
- What tools do I need for build a concrete patio?
- This guide includes a comprehensive tools list. Key building & construction tools are detailed in the Tools Required section.
- What is involved in building a concrete patio?
- Building a concrete patio involves planning drainage, preparing a compacted base, correctly placing reinforcement, and finishing the concrete before it sets. This process ensures a durable outdoor entertaining area suitable for Australian conditions. Key steps include excavation, formwork, steel fixing, pouring, and curing.
- What skill level do I need for building a concrete patio?
- An intermediate skill level is required for building a concrete patio, with an estimated 2–3 days of active work. Allowing 7 days for initial curing before regular use and 28 days for full strength is crucial. This project demands attention to detail in preparation and finishing.
- What are common mistakes when building a concrete patio?
- Common mistakes include skipping proper base compaction, pouring without adequate fall for drainage, incorrect reinforcement placement, and adding too much water to the mix or surface. These errors can lead to cracking, ponding water, and a weakened slab. Adhering to Australian standards like AS 3727.1:2016 helps avoid these issues.
- What is the recommended fall for a concrete patio in Australia?
- The recommended fall for a concrete patio in Australia is a minimum of 1:100, meaning a 10mm drop for every 1 metre of length. This ensures effective surface water drainage away from structures, preventing ponding and potential water ingress. AS 3727.1:2016 provides guidelines for residential pavement drainage.
- What type of reinforcement mesh is suitable for a residential concrete patio?
- For a residential concrete patio in Australia, SL72 (7mm diameter steel at 200mm centres) or SL82 (8mm diameter steel at 200mm centres) steel reinforcing mesh is typically suitable. This mesh should be positioned in the top third of the slab, supported by concrete chairs, to effectively manage tensile stresses and minimise cracking.
Written by Bricko, the Building & Construction specialist at VIC.Tools.