Skip to main content

How to build a concrete patio

Building a concrete patio is a solid DIY project for creating an outdoor entertaining area that will handle Australian conditions well when it is set out, reinforced and cured properly. For a typical ground-level patio slab, the key jobs are planning drainage fall, preparing a compacted base, placin

Skill level
Intermediate
Time
2–3 days active work, plus 7 days curing before regular use and 28 days for full cure
Trade
Building & Construction
Updated
28 November 2026

Tools you will need

  • Tape measure
  • String line and line level or rotary laser level
  • Marking paint
  • Shovel and trenching shovel
  • Mattock or pick
  • Plate compactor
  • Wheelbarrow
  • Concrete mixer
  • Formwork tools
  • Straightedge/screed

What is involved in building a concrete patio in Australia?

Building a concrete patio is a solid DIY project for creating an outdoor entertaining area that will handle Australian conditions well when it is set out, reinforced and cured properly. For a typical ground-level patio slab, the key jobs are planning drainage fall, preparing a compacted base, placing reinforcement correctly, and finishing the concrete before it starts to set.

What skill level is required to build a concrete patio?

Intermediate — Estimated time: 2–3 days active work, plus 7 days curing before regular use and 28 days for full cure

What tools are essential for building a concrete patio?

Tape measure — 8 m or longer for set-out
String line and line level or rotary laser level — for setting finished height and fall
Marking paint — for outlining excavation
Shovel and trenching shovel — for excavation and trimming edges
Mattock or pick — useful for hard ground
Plate compactor — 60–90 kg class, ideal for compacting road base; better hired for one-off jobs
Wheelbarrow — heavy-duty steel tray preferred
Concrete mixer — 120–160 L if mixing small quantities; for slabs over about 1.0 m³, ordering premixed concrete is usually more economical and consistent
Formwork tools — circular saw, drill/driver, hammer, nail puller
Straightedge/screed — aluminium screed or straightedge 2400–3000 mm long
Bull float or magnesium float — for initial finishing of the slab surface
Steel trowel — optional for a smoother finish; not recommended for a patio that needs slip resistance
Concrete edging tool — 10–15 mm radius
Jointing groover — optional if hand-tooling control joints
Bolt cutters or angle grinder — for cutting reinforcement mesh
Reinforcement chairs — for supporting mesh during the pour
Garden hose with fine spray nozzle — for dampening base and cleaning tools
Concrete saw with diamond blade — hired for saw-cut control joints after the pour
Spirit level — 1200 mm minimum
Knee boards or kneeling pad — for finishing work
Broom — soft to medium bristle for a non-slip broom finish

Materials Required

Concrete — typically 25 MPa premixed concrete for domestic patio slabs; allow 0.1 m³ per m² for a 100 mm thick slab
Example: a 4.0 m x 5.0 m patio at 100 mm thick = 2.0 m³
Compacted road base — 75–100 mm thick, allow 0.075–0.1 m³ per m²
Reinforcement mesh — commonly SL72 trench mesh/sheet mesh or engineer/supplier-recommended equivalent for a residential patio; do not place mesh directly on the ground
Bar chairs — 40–50 mm plastic or concrete chairs, spaced to support mesh properly
Formwork timber — commonly 90 x 45 mm structural pine or similar straight boards
Timber pegs/stakes — approx. 450–600 mm long for bracing formwork
Screws or nails — galvanised preferred for formwork
10 mm compressible foam expansion joint — where patio abuts the house, walls, columns or existing concrete
Plastic membrane (200 µm) — optional for covered patios or moisture-sensitive sites; check local practice and soil conditions
Curing compound — suitable for exterior concrete, or curing plastic/poly sheet
Sealant — optional concrete sealer for stain resistance after full cure
Water — clean water for mixing, dampening base and curing
If hand mixing small jobs only:
General purpose mix: 1 part cement : 2 parts sand : 3 parts aggregate
For more demanding structural mixes: 1 : 1.5 : 2.5
For most patios over small patch size, premixed concrete is strongly recommended for consistency

Safety Requirements

Wear PPE at all times: safety boots, gloves, safety glasses, long sleeves, long pants and hearing protection
Use a P2 respirator when cutting concrete, cement products or handling dry materials due to silica dust risk
Wet concrete is caustic and can cause serious skin burns; wash off immediately if it contacts skin
Use safe manual handling techniques when lifting mesh, formwork and cement bags; get help for sheets, long screeds and heavy loads
Ensure all 240 V tools are connected through an RCD/safety switch
Keep the site clear of trip hazards, especially around string lines, formwork pegs and hoses
Do not pour concrete in heavy rain, extreme heat, or strong drying winds if avoidable
Call Dial Before You Dig before excavation and confirm locations of services
If the patio is attached to the dwelling, supports a roof/pergola, is near retaining walls, on reactive soil, or requires thickened edges/footings, obtain engineering advice and approval as required
Concrete work should align with AS 3600 Concrete Structures and slab/footing design for residential sites should be checked against AS 2870 and local council requirements
Maintain finished patio levels below house damp-proofing and weepholes; as a practical rule, keep paving/slab surfaces at least 75 mm below weepholes, subject to site conditions and NCC/local requirements

Step-by-Step Guide

Step 1: Plan the patio size, levels and approvals

Decide the finished patio dimensions and use. For a simple entertaining area, common sizes are 3.0 m x 4.0 m, 4.0 m x 5.0 m or larger.

Check:

Whether the patio is standalone or tied into the house
Whether it will carry only pedestrian loads or heavier items like an outdoor kitchen, spa base or masonry BBQ
Whether council approval is needed in your area
Whether you need engineering because of reactive soil, nearby retaining walls, posts, or structural loads

Set the finished height so the slab drains away from the house. Aim for a fall of 10–15 mm per metre away from the dwelling. A practical target is 1:100 to 1:80 fall.

Step 2: Set out the patio accurately

Mark the patio perimeter with string lines and pegs. Measure diagonals to ensure the slab is square.

Set your finished surface levels using:

A string line and line level, or
A rotary laser level for better accuracy

Allow for:

100 mm slab thickness
75–100 mm compacted road base
Additional excavation if topsoil is soft or unstable

If the patio meets the house, confirm the finished concrete level will remain below weepholes and damp-proof course requirements.

Step 3: Excavate the area

Excavate the site to the required depth:

175–200 mm total below finished surface for a typical patio slab with base
Remove all topsoil, roots, organic material and soft spots

Trim the subgrade level and keep it reasonably even. If you hit soft clay, wet fill or loose material, dig it out and replace it with compactable road base.

For most patios, keep the excavation slightly wider than the slab so you have room for formwork and pegs.

Step 4: Prepare and compact the base

Spread road base in layers and compact it thoroughly with a plate compactor. Do not try to compact the full thickness in one go.

A good DIY method is:

Lay base in 50 mm layers
Compact each layer separately
Build up to a total of 75–100 mm compacted thickness

Check levels as you go. The compacted base should already reflect the final drainage fall. Lightly dampen the base if it is too dry for effective compaction, but do not make it muddy.

A well-compacted base is one of the biggest factors in avoiding cracking and settlement.

Step 5: Install formwork

Fix straight form boards around the patio perimeter using timber pegs at about 1000–1200 mm centres, closer if the ground is uneven.

Check that formwork is:

Straight
Braced firmly
At the correct finished height
Following the required fall

Use the top edge of the formwork as your screed guide. If the slab abuts the house, install 10 mm compressible foam expansion joint between the slab and the wall or existing concrete.

For curved patios, use flexible form boards or purpose-made edging.

Step 6: Install membrane and reinforcement

For a typical outdoor patio, a membrane is optional, but it can be beneficial for covered areas or certain ground conditions. If used, lay 200 µm plastic membrane neatly over the compacted base with taped overlaps.

Place reinforcement mesh on 40–50 mm bar chairs so it stays embedded in the slab. Never leave mesh lying on the ground and assume it will be pulled up later.

Key points:

Lap mesh sheets to supplier recommendations
Keep mesh back from slab edges by around 40–50 mm
Support mesh well enough so it does not sag during the pour

For unusual site conditions or heavier loads, reinforcement should match an engineer’s design.

Step 7: Organise the pour

Work out whether to hand mix or order ready-mix.

As a rule:

Up to about 0.5–0.75 m³ can sometimes be managed with a mixer and helper
Over about 1.0 m³, ready-mix is usually the better option
For a 4 m x 5 m x 100 mm patio, you need about 2.0 m³, so ready-mix is the practical choice

If ordering premix, ask for:

25 MPa concrete
Suitable slump for hand placement and screeding, commonly around 80–100 mm
Delivery access confirmed beforehand

If hand mixing a very small slab, use a 1:2:3 cement:sand:aggregate mix for general-purpose work, adding water gradually. Avoid overwatering, as this weakens the slab and increases shrinkage cracking.

Step 8: Pour and place the concrete

Start at the far end and work back toward your access point. Place concrete evenly and avoid dumping all the load in one spot.

Use a shovel or rake to spread the concrete into corners and around reinforcement. Do not overwork the mix. If using premix, keep the pour moving steadily so cold joints do not form.

During placement:

Ensure reinforcement remains supported
Fill to the top of formwork
Consolidate around edges and corners
Avoid adding extra water to the surface

For larger pours, a concrete vibrator can help with consolidation, but for a basic patio slab, careful rodding and placement are usually enough.

Step 9: Screed the slab

Using a straightedge or screed resting on the formwork, strike off excess concrete with a sawing motion.

The goal is to bring the slab to final level while maintaining the planned fall away from the house. Fill low spots immediately and rescreed.

This stage sets the quality of the finished slab, so take your time.

Step 10: Float, edge and finish the surface

After screeding, allow bleed water to rise and disappear before finishing. Do not start steel trowelling or brooming while water is still sitting on the surface.

Finish in this order:

1.Bull float or magnesium float to flatten ridges and close the surface
2.Edging tool around slab perimeter
3.Groover if hand-forming joints
4.Final finish

For most Australian patios, a broom finish is the best DIY option because it gives slip resistance. Drag the broom evenly across the slab once the surface has firmed up enough to hold texture without tearing.

Avoid a polished or very smooth steel-trowel finish on exterior patios, as it can become slippery when wet.

Step 11: Cut control joints

Control joints help manage shrinkage cracking. For a 100 mm slab, saw-cut joints to a depth of about 25 mm as soon as the concrete is hard enough to cut cleanly without edge ravelling, often within 6–18 hours depending on weather.

As a guide:

Space joints at about 2400–3000 mm
Try to keep panel shapes close to square
Include joints where the slab changes direction or narrows

Any slab will crack somewhere; joints encourage it to crack in controlled lines instead of randomly.

Step 12: Cure the concrete properly

Curing is critical for strength and durability. Once finishing is complete and the surface is firm enough, apply curing compound or cover the slab with plastic sheeting.

Good curing practice:

Protect the slab from rapid drying, sun and wind
Keep curing for at least 7 days where possible
Do not allow foot traffic for at least 24–48 hours
Avoid heavy loads for at least 7 days
Full design strength develops over about 28 days

In hot Australian weather, curing is especially important. Poor curing causes dusting, weak surfaces and extra cracking.

Step 13: Strip forms and complete the edges

After the concrete has gained enough strength, usually 24–48 hours, remove formwork carefully. Backfill the slab edges if needed and tidy the perimeter.

If you want extra stain resistance for outdoor furniture, food spills or leaf tannins, apply a suitable concrete sealer after the slab has properly cured, following the manufacturer’s timing and coverage instructions.

Common Mistakes to Avoid

1.Skipping proper base compaction — this leads to settlement, rocking furniture and slab cracking.
2.Pouring the slab flat with no fall — water will pond and may run back toward the house.
3.Letting reinforcement sit on the ground — mesh only works when it is embedded in the concrete.
4.Adding too much water to the mix or surface — this weakens the slab and causes dusting and shrinkage cracks.
5.Not cutting control joints in time — the slab will often form random cracks instead.

Pro Tips

For patios larger than about 10–12 m², order premixed concrete instead of hand mixing. The finish quality is better and timing is easier to manage.
In summer, pour early in the morning to avoid rapid set and finishing stress.
Use a broom finish perpendicular to the main walking direction for better slip resistance.
If the patio touches the house, always install an expansion/isolation joint rather than hard-pouring directly against brickwork.
Before the truck arrives, do a full dry run: access path, wheelbarrow route, hose location, tools laid out, helpers assigned, and formwork checked one last time.

Recommended Tools

Belle Minimix 150 cement mixer — a popular hire and purchase option for small concrete jobs and patch work
Wacker Neuson VP/plate compactor 60–90 kg class — reliable for compacting patio base material properly
Ox Tools or Spear & Jackson aluminium screed 2400 mm — lightweight and straight for accurate strike-off
Marshalltown magnesium float/bull float — gives a clean initial finish without overworking the surface
Husqvarna or Makita concrete saw with diamond blade — ideal hire item for clean control joints after the slab sets

Frequently asked questions

What is involved in build a concrete patio?
Building a concrete patio is a solid DIY project for creating an outdoor entertaining area that will handle Australian conditions well when it is set out, reinforced and cured properly. For a typical ground-level patio slab, the key jobs are planning drainage fall, preparing a compacted base, placin
What skill level do I need for build a concrete patio?
Intermediate — Estimated time: 2–3 days active work, plus 7 days curing before regular use and 28 days for full cure
What are common mistakes when build a concrete patio?
1. Skipping proper base compaction — this leads to settlement, rocking furniture and slab cracking. 2. Pouring the slab flat with no fall — water will pond and may run back toward the house. 3. Letting reinforcement sit on the ground — mesh only works when it is embedded in the concrete. 4. Adding too much water to the mix or surface — this weakens the slab and causes dusting and s
What tools do I need for build a concrete patio?
This guide includes a comprehensive tools list. Key building & construction tools are detailed in the Tools Required section.
What is involved in building a concrete patio?
Building a concrete patio involves planning drainage, preparing a compacted base, correctly placing reinforcement, and finishing the concrete before it sets. This process ensures a durable outdoor entertaining area suitable for Australian conditions. Key steps include excavation, formwork, steel fixing, pouring, and curing.
What skill level do I need for building a concrete patio?
An intermediate skill level is required for building a concrete patio, with an estimated 2–3 days of active work. Allowing 7 days for initial curing before regular use and 28 days for full strength is crucial. This project demands attention to detail in preparation and finishing.
What are common mistakes when building a concrete patio?
Common mistakes include skipping proper base compaction, pouring without adequate fall for drainage, incorrect reinforcement placement, and adding too much water to the mix or surface. These errors can lead to cracking, ponding water, and a weakened slab. Adhering to Australian standards like AS 3727.1:2016 helps avoid these issues.
What is the recommended fall for a concrete patio in Australia?
The recommended fall for a concrete patio in Australia is a minimum of 1:100, meaning a 10mm drop for every 1 metre of length. This ensures effective surface water drainage away from structures, preventing ponding and potential water ingress. AS 3727.1:2016 provides guidelines for residential pavement drainage.
What type of reinforcement mesh is suitable for a residential concrete patio?
For a residential concrete patio in Australia, SL72 (7mm diameter steel at 200mm centres) or SL82 (8mm diameter steel at 200mm centres) steel reinforcing mesh is typically suitable. This mesh should be positioned in the top third of the slab, supported by concrete chairs, to effectively manage tensile stresses and minimise cracking.

Written by Bricko, the Building & Construction specialist at VIC.Tools.