How to Build a Retaining Wall with Concrete Blocks

Build a durable concrete block retaining wall in Australia with our expert guide. Learn council approvals, drainage, foundation prep, and block laying for lasting results.

Skill level
Intermediate
Time
2–4 days for a typical wall up to 5 m long and 600–1000 mm high
Trade
Building & Construction
Updated
28 November 2026

Tools you will need

  • Stanley FatMax 8m Tape Measure - Measuring Tape
  • Sutton Tools 1200mm Spirit Level - Level
  • Cyclone Square Mouth Shovel - Shovel
  • Fiskars Xact Mattock - Mattock
  • Wacker Neuson VP1340A - Plate Compactor
  • Trojan Hand Tamper - Hand Tamper
  • Estwing E3-40BL 1.8kg Club Hammer - Hammer
  • Makita DHP485Z 18V Cordless Hammer Driver Drill - Drill
  • Sika Sikaflex 11FC - Construction Adhesive (with caulking gun)
  • Bunnings String Line and Pegs - Set-out Kit
  • Dulux Trade Marking Paint - Marking Paint (Aerosol)
  • Trojan Rubber Mallet - Mallet

What is a concrete block retaining wall and when is it used?

A concrete block retaining wall is a durable, low-maintenance way to hold back soil, create level garden areas, and improve drainage on sloping sites. This guide covers a typical DIY-friendly segmental concrete block retaining wall used in Australian landscaping; if you are building a reinforced besser block wall, or a wall over 1000 mm high, you should obtain engineering design and check council requirements before starting.

What skill level is required to build a concrete block retaining wall?

Intermediate — Estimated time: 2–4 days for a typical wall up to 5 m long and 600–1000 mm high

What tools are essential for building a concrete block retaining wall?

String line, timber pegs and marking paint for set-out
Tape measure, minimum 8 m
Laser level or dumpy level for accurate heights and stepped footing set-out
1200 mm spirit level and torpedo level
Shovel, trenching shovel, mattock and garden rake
Wheelbarrow, minimum 80 L
Plate compactor, 60–90 kg class, for base and backfill compaction
Hand tamper for compacting close to the wall
Rubber mallet for seating blocks without chipping
Brick bolster and 1.8 kg club hammer, or block splitter
230 mm angle grinder or masonry saw with diamond blade for cutting blocks
Caulking gun for cap adhesive
Broom and stiff brush to keep block beds clean
Utility knife and scissors for geotextile fabric
Optional concrete mixer if a concrete footing is specified by the manufacturer or engineer
PPE: steel-cap boots, gloves, safety glasses, hearing protection, P2 respirator, hi-vis clothing and sunscreen

What materials are needed for a concrete block retaining wall?

Concrete retaining wall blocks, sized to the selected system, quantity based on wall area plus 5–10% waste
Matching corner blocks, end blocks and capping units if required by the wall layout
Compactable road base or crushed rock, typically 100–150 mm deep under the wall and about 300–400 mm wide under the first course
Drainage aggregate, clean 10–20 mm stone, for a 200–300 mm wide drainage zone behind the wall
100 mm slotted ag pipe with filter sock, plus fittings and legal discharge point
Non-woven geotextile fabric to separate drainage stone from soil
Suitable backfill soil, free of roots, clay lumps and organic matter
Landscape block adhesive/polyurethane construction adhesive for capping units
Geogrid reinforcement if required by the wall system, manufacturer or engineer
Topsoil and mulch for final landscaping
If a concrete footing is required: 25 MPa premixed concrete or site mix at approximately 1:1.5:2.5 (cement:sand:aggregate) for structural work

Safety Requirements

Check underground services before digging through Before You Dig Australia (BYDA).
Wear PPE at all times: boots, gloves, eye protection, hearing protection and a P2 respirator when cutting concrete blocks.
Use wet cutting or dust extraction when cutting blocks to reduce silica dust exposure.
Concrete blocks are heavy; use correct manual handling techniques and get help lifting larger units.
Keep trenches tidy and do not leave unsupported excavations unattended, especially after rain.
Use a stable work platform on sloping ground; if access equipment or scaffolding is needed, it must comply with state WHS requirements.
Do not discharge drainage water onto neighbouring property unless approved; connect to a lawful outlet.
Retaining walls in Australia should be designed and built in accordance with manufacturer requirements and relevant standards, including AS 4678 for earth-retaining structures, AS 3700 for masonry structures where applicable, and AS 3600 for concrete work where applicable.
Walls over 1000 mm high, walls carrying surcharge loads from driveways, pools, structures or fences, and walls near boundaries typically require engineering certification and may require council approval.

Step-by-Step Guide

Step 1: Check approvals, wall height and block system

Confirm the retained height, wall length and whether the site has extra loads behind the wall, such as a driveway, shed, fence, pool or steep slope. For most Australian councils, walls over 1000 mm high, or walls close to boundaries or structures, may need approval and engineering.

Choose a proper retaining wall block system rather than ordinary garden edging blocks. Follow the manufacturer’s installation guide for setback, buried course depth, maximum height and geogrid requirements. If you are using standard hollow concrete blocks or besser blocks, that becomes structural masonry and should be engineer designed to AS 3700 and AS 3600.

Step 2: Set out the wall line and levels

Mark the front face of the wall with string line and pegs. Use a laser level to establish the finished wall height, the retained soil level and the excavation depth.

Allow for:

A buried first course, usually at least 100 mm, or as specified by the block manufacturer
A compacted base under the wall, generally 100–150 mm deep
A drainage zone behind the wall, generally 200–300 mm wide

If the wall runs across a slope, plan to step the base in block-height increments rather than trying to follow the ground with a sloping first course.

Step 3: Excavate the trench

Excavate a trench along the wall line. A practical trench width for many DIY retaining block systems is the block depth plus 200–300 mm behind for drainage stone, with some extra working room.

For a typical wall block 200 mm high:

Excavate deep enough for 100–150 mm compacted base
Include the required buried amount of the first course
Keep the trench bottom as level as possible

Remove all soft spots, roots and loose soil. If the ground is very wet, reactive or soft, stop and reassess the design because poor founding material is a common cause of movement.

Step 4: Prepare and compact the base

Spread road base or crushed rock in the trench in layers no thicker than 75 mm, then compact each layer thoroughly with a plate compactor. Build up to a total compacted base thickness of about 100–150 mm, or as specified by the wall system.

Check the base with a laser level and spirit level. This is the most important stage of the build. The first course will only be as straight and level as the base underneath it.

For larger or engineered walls, the manufacturer or engineer may require a concrete footing instead of compacted granular base. If so, use 25 MPa concrete and follow the engineered dimensions and reinforcement details.

Step 5: Lay and level the first course

Place the first row of blocks directly onto the compacted base, starting at the lowest point of the site. Check every block for:

Level side to side
Level front to back
Straight alignment to the string line
Correct setback or lip orientation according to the system

Tap blocks into position with a rubber mallet. Do not use loose bedding sand under retaining wall blocks, as it can settle over time. Take your time here; the first course controls the entire wall.

Step 6: Install drainage behind the wall

Lay non-woven geotextile fabric behind the wall excavation so it will wrap over the drainage stone later. Place a 100 mm slotted ag pipe at the back of the first course, with a minimum fall of about 1:100 toward a legal discharge point.

Surround the pipe and the rear of the wall with clean 10–20 mm drainage aggregate. Keep a drainage zone of about 200–300 mm behind the wall. This reduces hydrostatic pressure, which is one of the main reasons retaining walls fail.

Never backfill directly against the wall with heavy clay.

Step 7: Build additional courses

Brush the top of each block clean before placing the next course. Even a small stone or bit of dirt can throw the wall out of level.

Stack the next courses with staggered joints as required by the block system. Maintain the built-in setback or locking mechanism. Check level and line every 2–3 blocks and correct errors immediately rather than trying to fix them at the top.

If the selected system requires pins, clips or interlocking lugs, install them exactly as specified by the manufacturer.

Step 8: Install geogrid if required

For taller walls or walls with surcharge loads, geogrid reinforcement may be required at nominated block courses. Roll the geogrid out perpendicular to the wall, pull it taut and place the next course of blocks on top to lock it in.

Typical geogrid lengths vary widely depending on retained height and soil conditions, so always follow the manufacturer’s table or the engineer’s design. As a rule, do not guess reinforcement details on a retaining wall.

Step 9: Backfill and compact in layers

Place backfill behind the drainage stone in layers of about 150 mm and compact each layer before adding the next. Use a hand tamper within about 300 mm of the wall to avoid knocking blocks out of line, and use the plate compactor farther back where safe.

Keep checking the wall for movement or bowing as you go. Do not dump a large amount of fill behind the wall and compact it all at once; staged compaction is essential.

Step 10: Cut blocks, install caps and finish surface drainage

Cut blocks as needed with a masonry saw or angle grinder fitted with a diamond blade. Dry fit capping units first, then fix them with landscape block adhesive once you are happy with the layout.

Finish the top surface so water falls away from the wall at about 1:50 where possible. Fold the geotextile over the top of the drainage stone before placing topsoil or decorative gravel. This helps stop fines washing into the drainage zone and blocking the ag pipe.

Step 11: Final inspection and maintenance check

Stand back and inspect the wall for:

Straightness along the face
Consistent setback
Level capping
Proper drainage outlet
No loose or rocking blocks

After heavy rain, check that water is draining freely and not ponding behind the wall. A well-built retaining wall should remain dry, straight and stable.

Common Mistakes to Avoid

1.Skipping council and engineering checks for walls over 1000 mm or walls supporting extra loads.
2.Building on an uncompact base or trying to level the wall with sand instead of proper base preparation.
3.Neglecting drainage behind the wall, especially omitting the ag pipe and drainage aggregate.
4.Using clay or organic soil as backfill, which traps water and expands when wet.
5.Compacting too aggressively right against the rear of the wall, causing the blocks to move out of line.

Pro Tips

Spend extra time on the first course; if the first row is perfect, the rest of the wall goes together much faster.
Start laying from the lowest point of the site and step the wall up as needed rather than trying to force a sloping base.
Keep the tops of blocks spotless before laying the next course; one pebble can create a visible lean over several courses.
Hire a plate compactor and masonry saw for a weekend instead of buying them if this is a one-off project; for most DIY jobs, hire is far more economical.
Buy 5–10% extra blocks and caps to allow for cuts, breakages and future repairs, especially if the product line changes later.

Recommended Tools

Plate compactor 60–90 kg class — essential for proper base and backfill compaction; best hired for DIY jobs.
Bosch or Leica laser level kit — makes setting base heights and stepped courses much more accurate than a spirit level alone.
Stabila 1200 mm spirit level — reliable for keeping the first course dead level.
Husqvarna or Makita 230 mm angle grinder with diamond masonry blade — ideal for trimming blocks and caps neatly.
OX Trade rubber mallet and brick bolster set — useful for seating blocks and making minor adjustments without damaging faces.

Frequently asked questions

What is a concrete block retaining wall and when is it used in Australian landscaping?
A concrete block retaining wall is a robust, low-maintenance structure designed to hold back soil, create level garden areas, and improve drainage on sloping sites. In Australian landscaping, these segmental walls are commonly used for garden beds, terracing, and erosion control, offering a DIY-friendly solution for residential properties up to 1 metre in height.
What Australian standards and regulations apply to building a concrete block retaining wall?
The primary Australian standard for masonry retaining wall construction is AS 3700:2018 Masonry structures, which outlines material, design, and construction requirements. Additionally, local council regulations and the National Construction Code (NCC) impose specific requirements, particularly for walls exceeding 1 metre in height or those supporting additional loads, necessitating engineering certification.
When is council approval required for a concrete block retaining wall in Australia?
Council approval is generally required for retaining walls over 1 metre in height, or any wall supporting a surcharge (like a driveway) or located near property boundaries. Requirements vary significantly by local government area across states like NSW, VIC, and QLD, so always consult your local council before commencing construction to ensure compliance with local planning schemes.
What are the critical steps for preparing the foundation for a concrete block retaining wall?
The critical steps involve excavating a level trench, typically twice the width of the block and 150-200mm deep, followed by laying and compacting a road base or concrete footing. This compacted base, such as Boral DGB20 or similar, ensures a stable, non-subsiding foundation, preventing future wall movement or failure, and must be level within 5mm over 3 metres.
What is the purpose of drainage aggregate and an ag pipe behind a retaining wall?
Drainage aggregate and an ag pipe are crucial for preventing hydrostatic pressure build-up behind the wall, which can lead to structural failure. The 10-20mm drainage aggregate (e.g., 'blue metal' or 'scoria') allows water to percolate freely, while the slotted ag pipe (e.g., Vinidex Draincoil) collects this water and directs it away, safeguarding the wall's integrity and longevity.
What are common mistakes to avoid when building a concrete block retaining wall?
Common mistakes include skipping council and engineering checks for walls over 1000 mm, building on an uncompacted base, or neglecting drainage behind the wall. Using clay or organic soil as backfill, or failing to compact each course of blocks properly, can also compromise the wall's stability and lifespan, leading to costly repairs and potential safety hazards.
How do you properly lay and secure the concrete blocks for a durable retaining wall?
Properly laying and securing concrete blocks involves ensuring each course is level and plumb, with blocks offset in a running bond pattern for structural integrity. The first course must be perfectly embedded and level, followed by applying a high-strength construction adhesive like Sika Sikaflex 11FC between subsequent courses to bond them firmly together, enhancing stability.