How to Build a Retaining Wall with Concrete Blocks
Build a durable concrete block retaining wall in Australia with our expert guide. Learn council approvals, drainage, foundation prep, and block laying for lasting results.
- Skill level
- Intermediate
- Time
- 2–4 days for a typical wall up to 5 m long and 600–1000 mm high
- Trade
- Building & Construction
- Updated
- 28 November 2026
Tools you will need
- Stanley FatMax 8m Tape Measure - Measuring Tape
- Sutton Tools 1200mm Spirit Level - Level
- Cyclone Square Mouth Shovel - Shovel
- Fiskars Xact Mattock - Mattock
- Wacker Neuson VP1340A - Plate Compactor
- Trojan Hand Tamper - Hand Tamper
- Estwing E3-40BL 1.8kg Club Hammer - Hammer
- Makita DHP485Z 18V Cordless Hammer Driver Drill - Drill
- Sika Sikaflex 11FC - Construction Adhesive (with caulking gun)
- Bunnings String Line and Pegs - Set-out Kit
- Dulux Trade Marking Paint - Marking Paint (Aerosol)
- Trojan Rubber Mallet - Mallet
What is a concrete block retaining wall and when is it used?
A concrete block retaining wall is a durable, low-maintenance way to hold back soil, create level garden areas, and improve drainage on sloping sites. This guide covers a typical DIY-friendly segmental concrete block retaining wall used in Australian landscaping; if you are building a reinforced besser block wall, or a wall over 1000 mm high, you should obtain engineering design and check council requirements before starting.
What skill level is required to build a concrete block retaining wall?
Intermediate — Estimated time: 2–4 days for a typical wall up to 5 m long and 600–1000 mm high
What tools are essential for building a concrete block retaining wall?
What materials are needed for a concrete block retaining wall?
Safety Requirements
Step-by-Step Guide
Step 1: Check approvals, wall height and block system
Confirm the retained height, wall length and whether the site has extra loads behind the wall, such as a driveway, shed, fence, pool or steep slope. For most Australian councils, walls over 1000 mm high, or walls close to boundaries or structures, may need approval and engineering.
Choose a proper retaining wall block system rather than ordinary garden edging blocks. Follow the manufacturer’s installation guide for setback, buried course depth, maximum height and geogrid requirements. If you are using standard hollow concrete blocks or besser blocks, that becomes structural masonry and should be engineer designed to AS 3700 and AS 3600.
Step 2: Set out the wall line and levels
Mark the front face of the wall with string line and pegs. Use a laser level to establish the finished wall height, the retained soil level and the excavation depth.
Allow for:
If the wall runs across a slope, plan to step the base in block-height increments rather than trying to follow the ground with a sloping first course.
Step 3: Excavate the trench
Excavate a trench along the wall line. A practical trench width for many DIY retaining block systems is the block depth plus 200–300 mm behind for drainage stone, with some extra working room.
For a typical wall block 200 mm high:
Remove all soft spots, roots and loose soil. If the ground is very wet, reactive or soft, stop and reassess the design because poor founding material is a common cause of movement.
Step 4: Prepare and compact the base
Spread road base or crushed rock in the trench in layers no thicker than 75 mm, then compact each layer thoroughly with a plate compactor. Build up to a total compacted base thickness of about 100–150 mm, or as specified by the wall system.
Check the base with a laser level and spirit level. This is the most important stage of the build. The first course will only be as straight and level as the base underneath it.
For larger or engineered walls, the manufacturer or engineer may require a concrete footing instead of compacted granular base. If so, use 25 MPa concrete and follow the engineered dimensions and reinforcement details.
Step 5: Lay and level the first course
Place the first row of blocks directly onto the compacted base, starting at the lowest point of the site. Check every block for:
Tap blocks into position with a rubber mallet. Do not use loose bedding sand under retaining wall blocks, as it can settle over time. Take your time here; the first course controls the entire wall.
Step 6: Install drainage behind the wall
Lay non-woven geotextile fabric behind the wall excavation so it will wrap over the drainage stone later. Place a 100 mm slotted ag pipe at the back of the first course, with a minimum fall of about 1:100 toward a legal discharge point.
Surround the pipe and the rear of the wall with clean 10–20 mm drainage aggregate. Keep a drainage zone of about 200–300 mm behind the wall. This reduces hydrostatic pressure, which is one of the main reasons retaining walls fail.
Never backfill directly against the wall with heavy clay.
Step 7: Build additional courses
Brush the top of each block clean before placing the next course. Even a small stone or bit of dirt can throw the wall out of level.
Stack the next courses with staggered joints as required by the block system. Maintain the built-in setback or locking mechanism. Check level and line every 2–3 blocks and correct errors immediately rather than trying to fix them at the top.
If the selected system requires pins, clips or interlocking lugs, install them exactly as specified by the manufacturer.
Step 8: Install geogrid if required
For taller walls or walls with surcharge loads, geogrid reinforcement may be required at nominated block courses. Roll the geogrid out perpendicular to the wall, pull it taut and place the next course of blocks on top to lock it in.
Typical geogrid lengths vary widely depending on retained height and soil conditions, so always follow the manufacturer’s table or the engineer’s design. As a rule, do not guess reinforcement details on a retaining wall.
Step 9: Backfill and compact in layers
Place backfill behind the drainage stone in layers of about 150 mm and compact each layer before adding the next. Use a hand tamper within about 300 mm of the wall to avoid knocking blocks out of line, and use the plate compactor farther back where safe.
Keep checking the wall for movement or bowing as you go. Do not dump a large amount of fill behind the wall and compact it all at once; staged compaction is essential.
Step 10: Cut blocks, install caps and finish surface drainage
Cut blocks as needed with a masonry saw or angle grinder fitted with a diamond blade. Dry fit capping units first, then fix them with landscape block adhesive once you are happy with the layout.
Finish the top surface so water falls away from the wall at about 1:50 where possible. Fold the geotextile over the top of the drainage stone before placing topsoil or decorative gravel. This helps stop fines washing into the drainage zone and blocking the ag pipe.
Step 11: Final inspection and maintenance check
Stand back and inspect the wall for:
After heavy rain, check that water is draining freely and not ponding behind the wall. A well-built retaining wall should remain dry, straight and stable.
Common Mistakes to Avoid
Pro Tips
Recommended Tools
Frequently asked questions
- What is a concrete block retaining wall and when is it used in Australian landscaping?
- A concrete block retaining wall is a robust, low-maintenance structure designed to hold back soil, create level garden areas, and improve drainage on sloping sites. In Australian landscaping, these segmental walls are commonly used for garden beds, terracing, and erosion control, offering a DIY-friendly solution for residential properties up to 1 metre in height.
- What Australian standards and regulations apply to building a concrete block retaining wall?
- The primary Australian standard for masonry retaining wall construction is AS 3700:2018 Masonry structures, which outlines material, design, and construction requirements. Additionally, local council regulations and the National Construction Code (NCC) impose specific requirements, particularly for walls exceeding 1 metre in height or those supporting additional loads, necessitating engineering certification.
- When is council approval required for a concrete block retaining wall in Australia?
- Council approval is generally required for retaining walls over 1 metre in height, or any wall supporting a surcharge (like a driveway) or located near property boundaries. Requirements vary significantly by local government area across states like NSW, VIC, and QLD, so always consult your local council before commencing construction to ensure compliance with local planning schemes.
- What are the critical steps for preparing the foundation for a concrete block retaining wall?
- The critical steps involve excavating a level trench, typically twice the width of the block and 150-200mm deep, followed by laying and compacting a road base or concrete footing. This compacted base, such as Boral DGB20 or similar, ensures a stable, non-subsiding foundation, preventing future wall movement or failure, and must be level within 5mm over 3 metres.
- What is the purpose of drainage aggregate and an ag pipe behind a retaining wall?
- Drainage aggregate and an ag pipe are crucial for preventing hydrostatic pressure build-up behind the wall, which can lead to structural failure. The 10-20mm drainage aggregate (e.g., 'blue metal' or 'scoria') allows water to percolate freely, while the slotted ag pipe (e.g., Vinidex Draincoil) collects this water and directs it away, safeguarding the wall's integrity and longevity.
- What are common mistakes to avoid when building a concrete block retaining wall?
- Common mistakes include skipping council and engineering checks for walls over 1000 mm, building on an uncompacted base, or neglecting drainage behind the wall. Using clay or organic soil as backfill, or failing to compact each course of blocks properly, can also compromise the wall's stability and lifespan, leading to costly repairs and potential safety hazards.
- How do you properly lay and secure the concrete blocks for a durable retaining wall?
- Properly laying and securing concrete blocks involves ensuring each course is level and plumb, with blocks offset in a running bond pattern for structural integrity. The first course must be perfectly embedded and level, followed by applying a high-strength construction adhesive like Sika Sikaflex 11FC between subsequent courses to bond them firmly together, enhancing stability.
Written by Bricko, the Building & Construction specialist at VIC.Tools.