How to Build a Simple Concrete Path
Learn how to build a simple concrete path in Australia. Master excavation, formwork, pouring to AS 3600 standards, and finishing for a durable result.
Quick answer
Building a simple concrete path requires excavating 150 millimetres, compacting a 50 millimetre crushed rock sub-base, and erecting timber formwork with a minimum 1:100 drainage fall. Pour 20 to 25 MPa concrete to a 100 millimetre depth, float the surface, and install control joints every 1.5 to 2 metres.
- Skill level
- Intermediate
- Time
- 1–2 days plus curing time
- Trade
- Building & Construction
- Updated
- 28 November 2026
Tools you will need
- Wacker Neuson DPS1850 - Vibratory Plate Compactor
- Stabila R-Type 1200mm - Spirit Level
- Kelso 100L Heavy Duty - Contractor Wheelbarrow
- Marshalltown 141D 150x75mm - Walking Edger
- Masterfinish 1200mm - Bull Float with Extension Handles
- OX Tools Pro Series 300mm - Pointing Trowel
- Westmix 2.2 cu ft - Electric Cement Mixer
🧱 How to Build a Simple Concrete Path
What is involved in building a simple concrete path in Australia?
A simple concrete path is a practical DIY project that improves access around the home, reduces mud, and gives the garden a cleaner finished look. For Australian homeowners, the key to a long-lasting result is good site preparation, correct base compaction, proper formwork, and placing the concrete at the right thickness.
This guide covers a straightforward ground-level concrete path suitable for general pedestrian use. For paths over reactive soils, near retaining walls, or where drainage and structural issues are present, seek site-specific advice and check local council and state requirements, with concrete work guided by AS 3600 where applicable.
What skill level is required for a concrete path project?
Intermediate — Estimated time: 1–2 days plus curing time
What tools are essential for laying a concrete path?
What materials are needed for a durable concrete path?
Safety Requirements
Step-by-Step Guide
Step 1: Set out the path
1️⃣ Mark the path location
Decide the width and route of the path. A comfortable garden path is usually 900–1200 mm wide for one person, while 1200–1500 mm gives a better feel for regular use.
Use string lines, pegs, and spray paint or sand to mark the edges. Keep curves smooth and practical rather than too tight.
Check where water currently flows and make sure the path will not trap water against the house, fence, or retaining wall. A finished fall of about 1:80 to 1:100 is common for drainage.
💡 Keep the path slightly crowned or fall it to one side so water sheds cleanly.
Step 2: Excavate to the correct depth
2️⃣ Dig out the path area
Excavate the full path width plus enough room for formwork. For a simple pedestrian path, dig down to allow for:
That means total excavation is often about 160–200 mm below finished path level, depending on site conditions.
Remove all grass, roots, topsoil, and soft material. Organic matter left underneath can settle later and cause cracking.
If the soil is very loose, wet, or reactive, improve the subgrade and consider professional advice before proceeding.
Step 3: Prepare and compact the base
3️⃣ Build a solid foundation
Spread road base in layers and compact thoroughly. For most DIY paths, a compacted sub-base of 75–100 mm is suitable.
Use a plate compactor for best results. Compact in passes until the base is firm and level. Hand tampers are acceptable only for very small sections.
Check levels with a string line and level. The base should already reflect the intended fall of the finished path.
💡 Do not skip compaction. Most failed paths crack because the ground underneath moves, not because the concrete itself was poor.
Step 4: Install formwork
4️⃣ Set the path shape and height
Fix straight timber form boards along both sides of the path. Use pegs at regular centres, typically every 600–1000 mm, closer on curves.
Set the top of the formwork to finished concrete level. Use a spirit level or laser level and confirm your drainage fall before pouring.
Brace the forms so they cannot spread or move under the weight of wet concrete. Apply a light release agent or dampen the timber to make stripping easier later.
For long paths, plan control joints at roughly 1.5–2 m intervals or at spacings no more than about 24–30 times the slab thickness.
Step 5: Place reinforcement if needed
5️⃣ Add mesh for crack control
A basic pedestrian path can sometimes be poured without reinforcement on stable ground, but reinforcement mesh is good practice and helps reduce cracking.
Use light mesh suited to the path size and support it on bar chairs so it sits in the upper half of the slab, not on the ground. Concrete should fully cover the steel.
Overlap mesh where required and tie it securely. If unsure about reinforcement requirements, especially on difficult ground, seek engineering advice.
💡 Mesh does not stop all cracks, but it helps hold the slab together if minor cracking occurs.
Step 6: Mix or order the concrete
6️⃣ Prepare the concrete properly
For small DIY jobs, bagged concrete mixed in a mixer is manageable. For larger paths, ready-mix is usually easier, faster, and often better value.
A typical general-purpose site mix is 1:2:3
For structural applications, a richer mix such as 1:1.5:2.5 may be used, but for a simple garden path, use a suitable premixed concrete or supplier-recommended path mix.
Only add enough water to achieve a workable mix. Too much water weakens the concrete and increases shrinkage cracking.
Step 7: Pour and place the concrete
7️⃣ Fill the forms evenly
Pour the concrete into the formwork and spread it with a shovel or rake. Work from one end to the other and avoid leaving dry or cold joints.
Place the concrete to full depth, ensuring it flows around reinforcement and into corners. Tap the formwork lightly or rod the concrete to remove trapped air.
Keep the concrete slightly proud of the forms before screeding.
If the weather is hot or windy, work quickly and have enough help on hand. Concrete can go off faster than beginners expect.
Step 8: Screed and level the surface
8️⃣ Strike off to finished height
Use a straight screed board resting on the form edges and drag it across the concrete in a sawing motion. This removes excess material and brings the surface to level.
Fill low spots immediately and re-screed until the path is flat and consistent. Recheck the fall so water will drain correctly.
After screeding, use a float to smooth the surface and bring up a small amount of paste. Do not overwork it.
Step 9: Finish the concrete
9️⃣ Apply a safe, durable surface finish
Allow bleed water to rise and disappear before final finishing. Do not trowel while water is still on the surface.
For a standard outdoor path, a broom finish is best because it provides slip resistance. First float the surface, edge the sides neatly, then lightly drag a broom across the path perpendicular to travel.
Cut control joints while the concrete is still green, usually to a depth of about one-quarter of slab thickness. On a 100 mm thick path, that means about 25 mm deep joints.
Use edging tools along the sides for a neat finish and to reduce edge chipping.
💡 A broom finish is usually the best choice for Australian outdoor conditions, especially around gardens, pools, and wet areas.
Step 10: Cure the concrete properly
🔟 Protect and strengthen the slab
Curing is critical. Once the surface has set enough, keep the concrete moist for at least 5–7 days where practical.
You can do this by:
Avoid walking on the path for at least 24–48 hours, depending on weather. Wait longer before heavy loads.
Concrete continues gaining strength over time and is generally considered to reach design strength at about 28 days.
Step 11: Strip forms and tidy up
1️⃣1️⃣ Finish the edges and surrounding area
Remove the formwork carefully after the concrete has hardened enough to hold its shape, usually the next day or later depending on conditions.
Backfill the sides with soil, gravel, or mulch and shape the surrounding ground so water runs away properly.
If desired, apply a concrete sealer after full curing in line with the product instructions.
Common Mistakes to Avoid
Pro Tips
Recommended Tools
Frequently asked questions
- What thickness should a pedestrian concrete path be in Australia?
- A standard pedestrian concrete path in Australia must be a minimum of 75mm thick, though 100mm is recommended for long-term durability. Paths crossing driveways or carrying light vehicle traffic require at least 100mm to 125mm thickness reinforced with SL72 steel mesh, in accordance with AS 3600:2018 guidelines.
- Do you need reinforcing mesh for a simple garden path?
- Reinforcing mesh is not strictly mandatory for a 75mm to 100mm garden path on stable ground, but adding SL62 mesh significantly reduces cracking from ground movement. In areas with reactive clay soils, standard practice under AS 2870 requires reinforcing mesh placed on bar chairs to prevent differential settlement.
- How deep should you excavate before pouring a concrete path?
- Excavate between 125mm and 150mm total depth to allow for both the base and the concrete. This provides adequate depth for a 50mm compacted road base sub-base layer, such as crushed rock or scalpings, topped with a 75mm to 100mm slab that sits flush with surrounding turf.
- What slope or fall is required for outdoor concrete paths?
- Outdoor concrete paths require a minimum cross-fall drainage slope of 1:100, which equals a 10mm drop per metre of path width. For wet areas or paths adjacent to house footings, a 1:50 fall (20mm per metre) is recommended to direct surface water safely away from external walls.
- How far apart should control joints be placed in a concrete path?
- Control joints should be spaced at intervals of roughly 1.5 to 2 times the path width, typically every 1.5 to 2 metres. Joints must be cut to a depth of one-quarter the slab thickness using a grooving tool or concrete saw to guide shrinkage cracks neatly.
- How long should a concrete path cure before walking on it?
- Pedestrian foot traffic is safe after 24 to 48 hours, but the concrete takes 28 days to reach full design strength. Keep the slab continuously moist using wet burlap, plastic sheeting, or a curing compound for at least the first 3 to 7 days to prevent surface crazing.
Written by Bricko, the Building & Construction specialist at VIC.Tools.