How to build a small concrete patio

Learn how to build a small concrete patio to Australian standards. Get key specs for slab thickness, base compaction, reinforcement, drainage fall, and curing.

Quick answer

A residential concrete patio requires a 100 mm thick slab of N20 or N25 grade concrete poured over a 75 mm compacted road base. In accordance with AS 3727.1:2016, reinforce the slab with SL72 mesh on 50 mm bar chairs and provide a 1:100 fall away from existing structures.

Skill level
Intermediate
Time
2–3 days plus 7 days curing time before heavy use
Trade
Building & Construction
Updated
28 November 2026

Tools you will need

  • Wacker Neuson BPU 3050A - Reversible Plate Compactor
  • Stabila 196-2 LED - 1200mm Heavy-Duty Spirit Level
  • Marshalltown 10609 - 2400mm Concrete Screed Board
  • Marshalltown QLT - Magnesium Hand Float
  • Masterfinish MF764 - Concrete Edger Tool
  • Makita DHS680Z - 18V Brushless 165mm Circular Saw
  • Bromic - Heavy-Duty Wheelbarrow 100L
  • Ox Tools Pro - 50/65mm Plastic Bar Chairs

🧱 Trade Guide: How to Build a Small Concrete Patio

What is involved in building a small concrete patio in Australia?

A small concrete patio is a practical weekend project that can add durable outdoor living space and increase the usability of your backyard. For most Australian homes, the key to a long-lasting result is good site preparation, a compacted base, correct slab thickness, proper falls, and careful curing.

This guide covers a straightforward DIY patio slab suitable for outdoor seating and foot traffic. For a typical backyard patio, aim for a slab thickness of 100 mm, a compacted base of 75–100 mm, and a fall of about 10 mm per 1 m away from the house.

What skill level is required to build a small concrete patio?

Intermediate β€” Estimated time: 2–3 days plus 7 days curing time before heavy use

What tools are required for a small concrete patio project?

πŸ”§ Tools Required
Tape measure 5 m or longer
String line, timber pegs, and marking paint
Shovel, mattock, rake, and wheelbarrow
Plate compactor (hire is economical for one-off jobs)
Spirit level 1200 mm or laser level
Straightedge/screed board at least 2400 mm
Circular saw or handsaw for formwork timber
Hammer or impact driver/drill
Concrete mixer for small batches, or order ready-mix for larger pours
Concrete shovel and concrete rake
Magnesium float, steel trowel, and edging tool
Groover or concrete saw for control joints
Bolt cutters or mesh cutter for reinforcement
Bar chairs for reinforcing mesh support
Garden hose with spray nozzle or curing compound sprayer
PPE: safety glasses, hearing protection, P2 dust mask, alkali-resistant gloves, steel-cap boots, long sleeves, and knee pads

What materials are needed for a small concrete patio?

Concrete β€” for a patio measuring 3 m x 3 m x 100 mm, allow about 0.9 mΒ³ plus waste; order 1.0 mΒ³ if using ready-mix
Compacted road base or crushed rock β€” 75–100 mm thick across the full slab area
Reinforcing mesh β€” commonly SL72 mesh, cut to suit with overlaps as required
Bar chairs β€” 40–50 mm height to keep mesh off the ground
Formwork timber β€” typically 90 mm x 45 mm or 100 mm x 50 mm straight boards
Timber stakes/pegs for bracing formwork
Builder’s plastic or vapour barrier if required by site conditions
Expansion foam/joint filler where slab meets house, steps, or existing concrete
Curing compound or plastic sheeting for curing
Concrete sealer suitable for exterior patios, optional but recommended
Clean water for mixing, cleaning tools, and curing
If hand-mixing only: cement, sand, and aggregate using a general-purpose ratio of 1:2:3 by volume for small non-structural work; for higher-performance structural applications use 1:1.5:2.5 and follow engineering advice

Safety Requirements

Wear PPE at all times: safety glasses, gloves, long sleeves, long pants, steel-cap boots, and hearing protection.
Wet concrete is highly alkaline and can cause chemical burns. Avoid skin contact and wash off immediately.
Use a P2 mask when cutting timber, handling dry cement, or compacting dusty base materials to reduce silica and cement dust exposure.
Lift safely. Cement bags, mesh sheets, and formwork timber can be awkward and heavy; use two-person lifts where needed.
Keep power tools and extension leads clear of wet areas and use an RCD-protected supply.
Before excavation, check for underground services through local service location processes.
If working near raised edges, retaining walls, or drops, use compliant edge protection. Any scaffolding or elevated access must meet state safety requirements.
For residential concrete work, good practice should align with AS 3600 Concrete Structures. Check local council requirements for drainage, setbacks, and whether approvals are needed.

Step-by-Step Guide

Step 1: 1️⃣ Plan the patio size, levels, and drainage

Choose the patio location and decide on the finished size. A common beginner-friendly size is 3 m x 3 m, which is large enough for a small table setting but still manageable for a DIY pour.

Set the finished height so water falls away from the house, not toward it. A practical fall is 10 mm per 1 m. If the patio is against the home, keep the finished slab level below weep holes and damp-proof course lines.

Mark out the perimeter using string lines and pegs. Measure diagonals to confirm the slab is square. At this stage, also decide whether the slab will be plain concrete, broom finish, or later tiled or coated.

Step 2: 2️⃣ Excavate and prepare the subgrade

Excavate the area to allow for the slab thickness and base layer. For a patio with a 100 mm slab and 75–100 mm compacted base, dig down about 175–200 mm from finished level.

Remove topsoil, roots, soft spots, and loose material. Organic material under the slab is a common cause of settlement and cracking later. Trim the soil level and compact the exposed subgrade thoroughly.

If the ground is very soft, wet, or reactive, you may need additional preparation or engineering advice. For standard backyard patio slabs, the aim is a firm, evenly compacted platform.

Step 3: 3️⃣ Install and compact the base

Spread road base or crushed rock evenly across the excavation to a compacted thickness of 75–100 mm. Compact it in layers rather than dumping it all in at once.

Use a plate compactor until the base is dense and stable underfoot. Recheck your levels as you go and maintain the required fall away from the house.

A well-compacted base is one of the most important parts of the job. Even strong concrete can crack if the base beneath it moves or settles.

Step 4: 4️⃣ Set the formwork

Install straight timber formwork around the perimeter at the finished slab height. Use 90 mm x 45 mm or similar straight boards, firmly pegged and braced so they do not move during the pour.

Check the formwork for square, level, and fall. The top edge of the formwork becomes your screed guide, so take your time here. If one board is twisted or out of level, the finished patio will show it.

Where the new slab touches the house, existing concrete, or fixed structures, install expansion joint material. This allows slight movement and helps prevent edge cracking.

Step 5: 5️⃣ Place reinforcement

Lay reinforcing mesh such as SL72 over the prepared base, cutting sheets to fit as needed. Support the mesh on bar chairs so it sits off the ground, generally around the middle to upper part of the slab thickness.

Do not let the mesh sit directly on the base. Reinforcement lying on the ground does very little once the concrete is poured. Keep overlaps consistent and avoid mesh hard against the slab edges.

For a simple patio, reinforcement helps control cracking but does not replace proper base preparation, slab thickness, and jointing.

Step 6: 6️⃣ Pour and spread the concrete

For a patio around 1.0 mΒ³ or less, you may use bagged concrete or a mixer, but ready-mix is often the better option for consistency and speed. If mixing by hand for very small jobs, a general-purpose ratio of 1:2:3 can be used, but for most patios a ready-mix around 20–25 MPa is preferred.

Pour the concrete evenly into the formwork and spread it with a rake or shovel. Work quickly enough to keep a wet edge and avoid cold joints.

Use a screed board resting on the formwork edges to strike off the concrete to the correct level. Move the screed in a sawing motion while pulling it across the slab.

Step 7: 7️⃣ Finish the surface

After screeding, use a bull float or magnesium float to smooth the surface and bring up a consistent paste. Do not overwork the slab or add excess water to the top.

Once the bleed water has disappeared, finish the surface to suit the intended use. A broom finish is ideal for most outdoor patios because it provides slip resistance in wet conditions.

Run an edging tool around the perimeter to tidy the slab edges and reduce chipping. If you want a smoother decorative finish, use a steel trowel lightly, but avoid making the surface too slippery for outdoor use.

Step 8: 8️⃣ Cut or tool control joints

Concrete will crack somewhere, so plan where it happens. Install control joints while the concrete is green with a groover, or saw cut them after the slab has hardened enough, usually within 6–24 hours depending on weather and mix.

For a slab thickness of 100 mm, aim for panel sizes no greater than about 2.4–3.0 m between joints. A small square patio may only need one central joint line or jointing to suit the slab shape.

Make joints about one-quarter of the slab depth, so approximately 25 mm deep for a 100 mm slab.

Step 9: 9️⃣ Cure the concrete properly

Curing is critical for strength and durability. Once finishing is complete and the surface can handle it, apply curing compound or cover the slab with plastic sheeting to retain moisture.

Keep the slab curing for at least 7 days for a better result, especially in hot, dry, or windy Australian conditions. Avoid letting the slab dry out too quickly, as this increases the risk of shrinkage cracking and weak surface dusting.

Light foot traffic is usually possible after 24–48 hours, but wait longer before placing heavy furniture or planters.

Step 10: πŸ”Ÿ Strip forms and seal if desired

Remove the formwork after the concrete has gained enough strength, usually after 24–48 hours, taking care not to chip the slab edges.

Backfill around the slab edges if required and make sure surface water drains away cleanly. If you want easier cleaning and better stain resistance, apply an exterior concrete sealer once the slab has cured as per the product instructions.

Sealing is especially worthwhile under BBQ areas, outdoor dining spaces, or where leaves and garden tannins may stain the surface.

Common Mistakes to Avoid

1.Skipping proper excavation and pouring straight onto loose soil or topsoil.
2.Using a slab that is too thin; for a durable patio, 100 mm is a safer DIY target.
3.Failing to provide fall, causing water to pond against the house or on the patio.
4.Letting reinforcing mesh sit on the ground instead of supporting it on bar chairs.
5.Adding too much water to the mix, which weakens the concrete and increases cracking.
6.Over-trowelling the surface or finishing while bleed water is still present.
7.Not cutting control joints soon enough, leading to random cracking.
8.Neglecting curing, especially during hot or windy weather.

Pro Tips

πŸ’‘ For patios over about 1 mΒ³, ready-mix is usually more economical and gives a more consistent result than mixing bags all day.
πŸ’‘ Hire a plate compactor rather than buying one for a one-off project; good compaction is worth the hire cost.
πŸ’‘ Use a broom finish for outdoor slabs in Australia. It is safer under wet feet and easier for beginners to execute well.
πŸ’‘ Order about 5–10% extra concrete to cover minor over-excavation, waste, and uneven subgrade.
πŸ’‘ If pouring beside the house, keep slab levels below weep holes and maintain clear drainage paths.
πŸ’‘ Pour early in the day during warm weather to avoid rapid set and finishing stress.
πŸ’‘ If you want a decorative look, consider exposed aggregate or colour-through concrete, but these finishes are easier with experienced help.

Recommended Tools

πŸ”§ Recommended Tools
Plate compactor β€” essential for properly compacting the base; best hired for weekend projects
2400 mm aluminium screed β€” helps achieve a flatter slab with less effort
Magnesium float β€” ideal for initial finishing before brooming
Concrete groover or early-entry saw β€” useful for neat control joints
Laser level β€” speeds up setting falls and formwork levels accurately

Frequently asked questions

What is the standard thickness for a concrete patio in Australia?
A residential concrete patio slab in Australia must be a minimum of 75 mm to 100 mm thick, laid over a compacted sub-base of 75 mm crushed rock. For pedestrian traffic, 100 mm is standard practice under AS 3727.1:2016 to prevent cracking and accommodate steel reinforcing mesh on bar chairs.
How much fall does an outdoor concrete slab need?
An outdoor concrete patio slab requires a minimum fall of 1:100, which equals 10 mm of fall per 1 metre of run away from the building. Under the National Construction Code, proper surface drainage directs rainwater away from footings and prevents pooling against external brickwork or weep holes.
What type of mesh is used for a concrete patio?
SL72 steel reinforcing mesh is standard for residential concrete patio slabs in Australia. For lighter foot-traffic paths, SL62 is sometimes substituted, but SL72 provides superior crack control against ground movement. The mesh must be supported on plastic bar chairs at a height of 50 mm to 60 mm.
What Australian standard applies to residential concrete patios?
AS 3727.1:2016 (Pavements - Residential, Part 1: Design and construction) governs residential concrete patio slabs, footpaths, and driveways across Australia. It specifies structural guidelines including minimum sub-grade preparation, concrete strength grades (typically N20 or N25), reinforcement coverage, and expansion joint spacing to prevent shrinkage cracking.
How long should concrete cure before walking on a patio?
A fresh concrete patio can take light foot traffic after 24 to 48 hours, but requires a full 28 days to reach design strength. Keep the slab continuously damp using curing compounds or plastic sheeting for at least 7 days to prevent surface crazing and ensure long-term durability.
What concrete mix ratio is best for a DIY patio slab?
A standard structural mix for an outdoor patio uses 1 part cement, 2 parts concrete sand, and 3 parts aggregate, yielding an N20 to N25 strength grade. Pre-blended commercial bags such as Dingo or Boral High Strength Concrete can also be used for small, hand-mixed outdoor slabs.

Written by Bricko, the Building & Construction specialist at VIC.Tools.