How to Build a Small Retaining Wall for a Garden
Learn how to build a small garden retaining wall under 1 metre. Step-by-step Australian trade guide covering trenching, drainage, base prep, and block laying.
Quick answer
To build a small garden retaining wall, excavate a trench, compact a 100mm to 150mm crushed rock footing, and embed the first block course below ground level. Lay interlocking concrete blocks with staggered joints, and install slotted drainage pipe surrounded by blue metal aggregate behind the wall to relieve hydrostatic pressure.
- Skill level
- Intermediate
- Time
- 1-2 days (depending on wall length and site conditions)
- Trade
- Building & Construction
- Updated
- 28 November 2026
Tools you will need
- Empire 1200mm e70 Series - Box Level
- Makita GA9020 2200W 230mm - Angle Grinder
- Ox Pro Heavy Duty 24oz - Deadblow Rubber Mallet
- Cyclone Square Mouth Post Hole - Shovel
- Wacker Neuson DPS1850H - Single Direction Plate Compactor
- Lufkin 8m Shockforce Nite-Eye - Heavy Duty Tape Measure
- Marshalltown 11 x 4.5 inch - Brick Trowel
🧱 Building a Small Garden Retaining Wall
What is involved in building a small garden retaining wall?
This guide outlines the process for constructing a small, non-structural retaining wall using concrete blocks, ideal for garden beds or minor landscaping changes. It focuses on walls under 1000mm in height, which typically do not require engineering certification in many Australian councils, though local regulations should always be checked.
What skill level is required to build a small garden retaining wall?
Intermediate — Estimated time: 1-2 days (depending on wall length and site conditions)
What tools are required to build a small garden retaining wall?
Shovel (square mouth and pointed) Pickaxe (for hard ground) Spirit level (1200mm and 600mm) Rubber mallet Tape measure (8m) String line and pegs Wheelbarrow Trowel (pointing and bricklayer's) Angle grinder with diamond blade (for cutting blocks) Safety glasses, gloves, ear protection, dust mask Compactor/Tamper (manual or plate compactor for larger projects) Bucket (for mixing mortar/concrete) Stiff brushWhat materials are required for a small garden retaining wall?
Retaining wall blocks (e.g., Besser blocks, segmental retaining wall blocks) – calculate quantity based on wall length and height, plus 5-10% for cuts/breakages. Road base/Crushed rock (e.g., DGB20) – approximately 0.15m³ per linear metre of wall for base and backfill. Concrete mix (pre-bagged or sand, cement, aggregate for 1:2:3 mix) – for footing. Mortar mix (pre-bagged or sand, cement, lime for 6:1:1 mix) – for block laying (if required by block type). Drainage aggregate (e.g., 10-20mm washed gravel) – approximately 0.1m³ per linear metre of wall. Geotextile fabric (non-woven) – sufficient to line behind drainage aggregate. Agricultural pipe (100mm diameter, slotted) – length of wall. Rebar/Pins (if specified by block system) WaterWhat safety requirements are essential for building a retaining wall?
⚠️ Safety
PPE: Always wear safety glasses, heavy-duty gloves, steel-capped boots, and hearing protection when cutting blocks or using power tools. A dust mask is essential when mixing concrete/mortar or cutting masonry. Manual Handling: Lift heavy blocks and bags of material correctly, bending knees and keeping your back straight. Use a wheelbarrow for transport. Excavation: Be aware of underground services (dial 1100 before you dig). Ensure trenches are stable and not prone to collapse. Power Tools: Use an RCD (Residual Current Device) with all power tools. Scaffolding: Not typically required for small garden walls under 1000mm, but ensure stable footing when working at height.Step-by-Step Guide
Step 1: 1️⃣ Site Preparation and Layout
Begin by clearing the area of any vegetation, rocks, or debris. Mark out the proposed line of your retaining wall using string lines and pegs. Ensure the line is straight and level. For curved walls, use flexible garden hose to mark the curve. Dig a trench for the footing that is at least 300mm wide and 150-200mm deep, ensuring it is level along its entire length. The depth should allow the first course of blocks to be partially buried for stability and a neat finish.
Step 2: 2️⃣ Prepare and Pour the Concrete Footing
Lay a 50-75mm layer of compacted road base in the trench. Mix concrete to a general-purpose ratio of 1:2:3 (1 part cement, 2 parts sand, 3 parts aggregate) or use a pre-bagged mix. Pour the concrete into the trench, ensuring a minimum depth of 100mm. Use a trowel and spirit level to create a perfectly level and smooth surface for the first course of blocks. Allow the concrete to cure for at least 24-48 hours before proceeding.
Step 3: 3️⃣ Laying the First Course of Blocks
Once the footing is cured, lay your first course of retaining wall blocks directly onto the concrete. For segmental retaining wall blocks, this is typically a dry-laid process. For Besser blocks, use a 10mm bed of mortar (mix 6:1:1 sand:cement:lime). Start at one end and work your way along, ensuring each block is perfectly level both horizontally and vertically with a spirit level and rubber mallet. Check the entire course for levelness and alignment with your string line. This first course is critical for the stability and appearance of the entire wall.
Step 4: 4️⃣ Installing Drainage and Backfill
Behind the first course of blocks, lay a 100mm slotted agricultural pipe, ensuring it slopes gently towards an outlet point to allow water to escape. Cover the pipe and the area directly behind the blocks with a 300mm layer of 10-20mm drainage aggregate. Wrap this aggregate in geotextile fabric to prevent soil from clogging the drainage system. This step is crucial for preventing hydrostatic pressure build-up behind the wall, which can lead to failure.
Step 5: 5️⃣ Laying Subsequent Courses
Continue laying subsequent courses of blocks. For segmental retaining wall blocks, follow the manufacturer's instructions, which often involve interlocking lips or pins. For Besser blocks, lay each course with a 10mm mortar joint, ensuring a staggered (stretcher bond) pattern for strength. Regularly check for levelness, plumb, and alignment. Fill the cores of Besser blocks with concrete if specified by the block manufacturer or for added strength. As you build up, continue to backfill behind the wall with drainage aggregate and then compacted soil, ensuring the geotextile fabric separates the drainage layer from the soil.
Step 6: 6️⃣ Capping and Finishing
Once the wall reaches the desired height, install the capping blocks. These are typically laid with mortar or adhesive, providing a neat and finished top surface. For Besser blocks, you might use a solid top block or pour a concrete cap. Clean off any excess mortar or concrete from the face of the blocks with a stiff brush and water before it sets. Allow the wall to cure for several days before applying significant pressure or backfilling completely.
Common Mistakes to Avoid
Pro Tips
💡 Dry Run: Before mixing any concrete or mortar, lay out your first course of blocks dry on the ground to check your measurements and cuts. 💡 Waterproofing: For walls retaining very wet soil or near water features, consider applying a bitumen-based waterproofing membrane to the back of the blocks before backfilling. 💡 Batch Mixing: If mixing your own concrete/mortar, work in manageable batches to prevent it from setting before you can use it. 💡 Tool Cleaning: Clean all tools immediately after use, especially those used for concrete and mortar, to prevent material from hardening on them. 💡 Block Cutting: When cutting blocks with an angle grinder, score all four sides first, then cut through. Use a wet saw for cleaner cuts and less dust if available.Recommended Tools
🔧 Makita 230mm Angle Grinder: Essential for precise and efficient cutting of retaining wall blocks. 🔧 Stanley FatMax 8m Tape Measure: Durable and accurate for all your measuring needs. 🔧 Ox Tools Pro Spirit Level Set (1200mm & 600mm): Crucial for ensuring your wall is perfectly level and plumb. 🔧 Husqvarna K 770 Power Cutter: For larger projects or frequent block cutting, consider hiring a dedicated power cutter for speed and precision.Frequently asked questions
- What is the maximum retaining wall height without council approval in Australia?
- In most Australian states, a retaining wall under 1000mm in total height does not require council approval or engineering certification, provided it does not carry surcharge loads. However, regulations vary by local council, with some jurisdictions setting the threshold at 600mm or requiring setback permits near property boundaries.
- What is the best base for a small garden retaining wall?
- A compacted road base foundation using DGB20 road base or 20mm crushed rock compacted to a minimum depth of 100mm to 150mm provides the ideal footing. The trench should be twice the width of the retaining block and topped with a 20mm sand-and-cement levelling pad for stability.
- How do you install drainage behind a garden retaining wall?
- Install a 100mm slotted agricultural pipe wrapped in geotextile sock at the base of the wall's rear face, vented to stormwater or daylight. Backfill with 10mm to 20mm blue metal aggregate to within 100mm of the top surface to eliminate hydrostatic pressure as outlined in AS 4678:2002.
- Do concrete retaining blocks require mortar for walls under 1 metre?
- Dry-stack interlocking concrete retaining blocks, such as Boral Keystone or Austral Masonry Heron blocks, do not require wet mortar joints for garden walls under 1000mm. Instead, blocks rely on an engineered pin or rear lip system, with landscape-grade polyurethane adhesive used solely on the capping units.
- How deep should the trench be for a small retaining wall?
- Dig the trench deep enough to accommodate a 100mm to 150mm compacted aggregate base plus the full embedment of the first block course, typically at least 10 percent of the wall's total height or 100mm. Burying the first course locks the wall into the subgrade to prevent toe kickout.
- What are the most common retaining wall failures to avoid?
- The primary causes of retaining wall failure are inadequate subsurface drainage and an uneven or uncompacted foundation base. Trapped groundwater creates severe hydrostatic pressure that pushes walls forward, while unlevel first courses compound vertically, leading to stepping, structural cracking, and eventual blowouts under soil expansion.