How to build brick garden edging
Brick garden edging is a practical weekend project that gives garden beds a clean finish, keeps mulch and soil contained, and improves street appeal without a large budget. For most Australian homes, a single-brick edging laid flat or on edge over a small concrete footing is the most durable and beg
- Skill level
- Beginner to Intermediate
- Time
- 1 day for 5–10 m, plus 24–48 hours curing time
- Trade
- Building & Construction
- Updated
- 28 November 2026
Tools you will need
- Brick trowel, 250
- Pointing trowel for tight joints and clean
- Brick bolster and club hammer for cutting bricks
- Tape measure, minimum 5 m
- String line and line pins/stakes
- Spirit level, 600 mm minimum
- Rubber mallet
- Shovel and trenching spade
- Hand tamper or plate compactor for longer runs
- Wheelbarrow
What is the purpose of building brick garden edging?
Brick garden edging is a practical weekend project that gives garden beds a clean finish, keeps mulch and soil contained, and improves street appeal without a large budget. For most Australian homes, a single-brick edging laid flat or on edge over a small concrete footing is the most durable and beginner-friendly option.
What skill level is required for building brick garden edging?
Beginner to Intermediate — Estimated time: 1 day for 5–10 m, plus 24–48 hours curing time
What tools are required for building brick garden edging?
What materials are needed for building brick garden edging?
What safety requirements are essential when building brick garden edging?
Step-by-Step Guide
Step 1: Plan the edging layout
Decide whether the bricks will be:
For beginners, the easiest and most durable option is a single row laid flat or on edge on a concrete footing.
Mark the garden edge using:
Check the line from several angles before digging. Measure the total length so you can calculate brick quantities and allow an extra 5–10% for cuts and breakages.
Step 2: Check levels and drainage
Use a spirit level and straightedge to check existing ground levels. Garden edging should follow the landscape neatly, but it should not trap water against paths, lawns, or house slabs.
As a guide:
Avoid setting the edging too high in low spots, as it will look uneven and create ponding.
Step 3: Excavate the trench
Dig a trench along the set-out line.
Typical trench sizes:
Remove all grass roots, soft soil, and organic material. Trim the trench neatly so the footing stays consistent in width. If the ground is very soft or sandy, excavate a little deeper and add 50 mm compacted road base before the concrete.
Step 4: Compact the base
Compact the trench base using a hand tamper. For runs over about 10 m, hiring a small plate compactor is usually more economical and gives a better result than buying one for a one-off project.
The base should feel firm underfoot and show no obvious loose spots. A poorly compacted base is one of the main causes of cracked mortar joints and uneven brick lines later.
Step 5: Pour the footing
For a long-lasting edging, pour a small strip footing.
Recommended footing sizes:
Concrete mix:
Slightly dampen the trench before placing concrete. Pour the footing and screed it roughly level. It does not need a polished finish, but it should be flat enough to accept a mortar bed.
For small DIY jobs, you can lay the bricks while the footing is still green if you work carefully and do not disturb alignment. For beginners, it is often easier to let the footing firm up first, then lay the bricks on a mortar bed.
Step 6: Prepare the mortar
Mix bricklaying mortar to a workable consistency.
A typical DIY brick mortar mix is:
Add water gradually until the mortar holds on the trowel without slumping. It should be workable, not runny. Only mix what you can use in about 30–45 minutes, especially in hot Australian conditions.
If you want the joints to match existing brickwork, you can add oxide colour, but measure it consistently between batches.
Step 7: Lay the first bricks
Spread a 10–15 mm mortar bed on the footing for the first section. Start at the most visible end, a straight edge, or a corner.
Set the first brick carefully:
Continue laying bricks with:
Butter the end of each brick with mortar before placing the next one. Keep checking:
For curved edging, use shorter visual checks and do not rely only on a straight spirit level. Step back regularly to confirm the curve looks smooth.
Step 8: Cut bricks where required
At ends, bends, or tight curves, you may need cut bricks.
For occasional cuts:
For multiple cuts or neater curved work:
Always wear eye, hearing, and dust protection. Dry cutting creates significant dust, so keep exposure low and work in a well-ventilated outdoor area.
Step 9: Haunch and support the edging
Once the bricks are aligned, place mortar or concrete haunching along the garden side and/or rear side of the edging to lock it in place.
Typical haunching size:
This is especially important for:
Keep haunching low enough that it can be covered with soil or mulch for a neat finish.
Step 10: Finish the joints
Tool the joints when the mortar has started to firm up but is not fully hard. A slightly concave joint is usually best because it sheds water better and gives a tidy finish.
Brush off loose mortar with a soft or stiff brush once the joints are thumbprint hard. Do not smear wet mortar across the brick faces. Clean any marks early with a damp sponge, but avoid overwetting the joints.
Step 11: Backfill and tidy the area
After the edging has firmed up, backfill both sides carefully:
Compact lightly by hand. Do not push hard against fresh brickwork. Recheck that the edging remains straight or evenly curved after backfilling.
Step 12: Cure the work properly
Protect the brick edging from heavy rain, hose pressure, and foot traffic for at least 24 hours. In hot, dry, or windy weather, lightly mist the mortar for the first day to slow drying and reduce shrinkage cracking.
Allow:
Common Mistakes to Avoid
Pro Tips
Recommended Tools
Frequently asked questions
- What is involved in build brick garden edging?
- Brick garden edging is a practical weekend project that gives garden beds a clean finish, keeps mulch and soil contained, and improves street appeal without a large budget. For most Australian homes, a single-brick edging laid flat or on edge over a small concrete footing is the most durable and beg
- What skill level do I need for build brick garden edging?
- Beginner to Intermediate — Estimated time: 1 day for 5–10 m, plus 24–48 hours curing time
- What are common mistakes when build brick garden edging?
- 1. Skipping the footing or base preparation — bricks laid straight onto loose soil often move, settle, or lean within a season. 2. Using mortar that is too wet — sloppy mortar weakens joints and makes it difficult to keep bricks level. 3. Not using a string line — even minor alignment errors become obvious over a 5–10 m run. 4. Poor compaction in soft spots — one weak section in th
- What tools do I need for build brick garden edging?
- This guide includes a comprehensive tools list. Key building & construction tools are detailed in the Tools Required section.
- What is involved in building brick garden edging?
- Brick garden edging is a practical weekend project that gives garden beds a clean finish, keeps mulch and soil contained, and improves street appeal without a large budget. For most Australian homes, a single-brick edging laid flat or on edge over a small concrete footing is the most durable and beginner-friendly option, ensuring longevity and stability.
- What skill level do I need for building brick garden edging?
- Building brick garden edging typically requires a Beginner to Intermediate skill level. The estimated time for completion is 1 day for 5–10 metres of edging, plus an additional 24–48 hours for the concrete footing and mortar to cure properly. Basic bricklaying skills and attention to detail are beneficial for a professional finish.
- What are common mistakes when building brick garden edging?
- Common mistakes include skipping the footing or base preparation, which leads to movement and settling over time. Using mortar that is too wet weakens joints and makes levelling difficult. Not using a string line results in uneven alignment, and poor compaction in soft spots creates weak sections. These errors compromise the edging's durability and appearance.
- What is the recommended mortar mix for brick garden edging in Australia?
- For brick garden edging in Australia, a general-purpose M3 mortar mix is recommended. This typically consists of 1 part general purpose cement to 4-5 parts bricklayer’s sand, with enough clean water to achieve a workable consistency. According to AS 3700:2018, this mix provides adequate strength for non-structural applications like garden edging.
- How much concrete is needed for a brick garden edging footing?
- For a typical single-brick garden edging, a footing approximately 100-150mm wide and 50-75mm deep is usually sufficient. A recommended mix is 1:2:3 cement:sand:aggregate. As a guide, one 20kg bag of premixed concrete will cover approximately 0.01 cubic metres, so calculate your linear metres to determine the total quantity required.