Skip to main content

How to build concrete steps

Concrete steps are a durable, low-maintenance way to improve front entries, garden paths and access on sloping blocks. For most homeowners, the job comes down to good set-out, solid base preparation, strong formwork and careful finishing. This guide covers simple cast-in-place external concrete ste

Skill level
Intermediate
Time
1-2 days build time, plus 7 days curing before regular use and 28 days to full concrete strength
Trade
Building & Construction
Updated
28 November 2026

Tools you will need

  • Tape measure, builder’s square and stringline for set
  • Laser level or 1200 mm spirit level
  • Shovel, mattock and rake for excavation
  • Plate compactor
  • Wheelbarrow or concrete buggy
  • Concrete mixer for bagged mixes, or arrange mini
  • Circular saw or handsaw for cutting formwork timber
  • Drill/driver and impact driver with exterior screws
  • Hammer and formwork stakes
  • Tie wire pliers

🧱 How to Build Concrete Steps: A DIY Trade Guide for Australian Homes

What are the benefits of building concrete steps in Australia?

Concrete steps are a durable, low-maintenance way to improve front entries, garden paths and access on sloping blocks. For most homeowners, the job comes down to good set-out, solid base preparation, strong formwork and careful finishing.

This guide covers simple cast-in-place external concrete steps suitable for residential foot traffic. If your steps are attached to the house structure, retain soil, support heavy loads or involve a drop requiring balustrades, get engineering advice and check local council and NCC requirements.

What skill level is required for building concrete steps in Australia?

Intermediate — Estimated time: 1-2 days build time, plus 7 days curing before regular use and 28 days to full concrete strength

What essential tools are needed for concrete step construction?

Tape measure, builder’s square and stringline for set-out
Laser level or 1200 mm spirit level
Shovel, mattock and rake for excavation
Plate compactor (60-90 kg) for sub-base compaction — usually better to hire for a one-off job
Wheelbarrow or concrete buggy
Concrete mixer for bagged mixes, or arrange mini-mix delivery if volume exceeds about 0.25-0.30 m³
Circular saw or handsaw for cutting formwork timber
Drill/driver and impact driver with exterior screws
Hammer and formwork stakes
Bolt cutters or angle grinder for cutting reinforcement mesh
Tie wire pliers
Screed board/straightedge, ideally 1.2-1.8 m
Magnesium float, steel trowel, edging tool and jointer
Stiff broom for slip-resistant finish
Garden sprayer or hose with fine mist for curing
PPE: safety glasses, hearing protection, P2 dust mask, alkali-resistant gloves, long sleeves and steel-cap boots

What materials are necessary for building durable concrete steps?

Concrete premix or ready-mix concrete, calculated to your stair volume plus 10% allowance
For small DIY jobs, bagged premix is fine
For larger pours, order 25-32 MPa ready-mix
Road base or crushed rock for a compacted base, typically 100-150 mm deep
Reinforcing mesh such as SL72 or SL82, cut to suit with 40-50 mm concrete cover
Bar chairs or dobies to support reinforcement
Formwork timber, commonly 90 x 35 mm or 140 x 35 mm boards
Stakes, usually 50 x 50 mm timber or steel form pegs
Structural plywood 17-19 mm if curved sides are needed
Exterior screws or formwork nails, typically 65-75 mm
Form release oil
10 mm compressible expansion joint foam if steps abut a slab, wall or brickwork
Plastic curing sheet or curing compound
Optional penetrating sealer for exterior concrete after curing

Safety Requirements

Wear safety glasses, steel-cap boots, hearing protection, gloves and a P2 mask when cutting timber, handling cement or cutting reinforcement.
Wet concrete is highly alkaline and can cause burns. Avoid skin contact and wash off splashes immediately.
Cement bags, formwork timber and reinforcement are awkward to lift. Use safe manual handling and get help with heavy loads.
Check for underground services before digging using Before You Dig Australia.
If working near a drop, excavation edge or elevated entry, use compliant edge protection or scaffolding as required.
External stairs must be uniform and safe to use. Check stair geometry, handrail and balustrade requirements under the NCC and your state or council rules.
Concrete work should align with AS 3600 Concrete Structures. If the steps are structural, suspended, retaining soil or tied into building footings, obtain engineering certification.
If the steps connect to a house slab or foundation on reactive soil, also consider footing movement and site conditions under AS 2870.

Step-by-Step Guide

Step 1: 1️⃣ Plan the step size and check compliance

Measure the total vertical rise from the finished ground level to the finished landing level.

For comfortable residential external steps, aim for:

Riser height around 150-170 mm
Tread depth around 280-300 mm
A consistent stair relationship where 2 x riser + tread = about 550-700 mm

Keep every riser and tread uniform. As a rule, variation between the largest and smallest riser or tread should be no more than 5 mm.

A practical width for home use is 900-1200 mm. Wider steps look better at front entries, but they use more concrete and require stiffer formwork.

Before building, confirm:

Water will drain away from the house
The new steps won’t block weep holes or damp-proof courses
Handrails or balustrades are not required under the NCC
Council approval is not needed for your site conditions

Step 2: 2️⃣ Set out the footprint and finished levels

Drive in timber pegs and run stringlines to mark the width, sides and finished front edge of the steps.

Mark:

Total width
Total run, being the combined tread depth
Finished height of each riser
A slight fall on each tread, about 3-5 mm over 300 mm, so water sheds off the step

Double-check square by measuring diagonals. If the set-out is out by even 10-15 mm, the finished steps will look skewed.

If the steps meet an existing landing, set the top tread to finish flush with that level after allowing for your concrete finish.

Step 3: 3️⃣ Excavate to firm ground

Excavate the entire footprint of the steps plus at least 75-100 mm extra on each side for formwork and working room.

Remove:

Topsoil
Roots
Soft spots
Loose fill

Dig down enough to allow for:

100-150 mm compacted road base
Reinforcement cover
The concrete thickness under the lowest step, typically at least 100 mm

The subgrade must be firm and evenly compacted. If the ground is wet, soft or full of organic material, keep digging until you reach stable ground and rebuild with compacted fill.

If your site is steep and the sides of the steps will retain soil, stop and get advice. Retaining loads can change this from a simple DIY concrete job into structural work.

Step 4: 4️⃣ Install and compact the base

Spread road base in layers no thicker than 50 mm and compact each layer thoroughly with a plate compactor.

Build up to a finished compacted thickness of 100-150 mm. The base should be flat, dense and follow your step profile.

A properly compacted base does two jobs:

Reduces settlement and cracking
Gives your formwork and reinforcement a stable platform

If the steps are beside the house, leave room for a 10 mm expansion joint against masonry, slab edges or walls unless an engineer has specified a fixed connection.

💡 For one-off home projects, hiring a plate compactor is almost always cheaper and better than trying to compact by hand.

Step 5: 5️⃣ Build the formwork

Construct the side forms and riser boards from straight, sound timber. Common form boards are 90 x 35 mm or 140 x 35 mm, depending on the step height.

Set each riser board to the exact finished height and brace it well with stakes at roughly 600-900 mm centres. Use screws rather than nails where possible so adjustments are easier.

Check:

Width is consistent
Risers are plumb
Treads are level side to side
Each tread has a slight fall away from the house
Formwork is rigid and won’t bow when concrete is placed

Coat the inside faces with form release oil so the boards strip cleanly.

If you want a bullnose or rounded edge, plan the nosing detail now. For basic DIY steps, a square tread with a 10-15 mm edged arris is neat and durable.

Step 6: 6️⃣ Place reinforcement

Cut reinforcement mesh to fit inside the forms, allowing 40-50 mm cover from all edges.

Support the mesh on chairs or dobies so it sits in the concrete, not on the base. If the reinforcement is lying on the ground, it is doing very little.

For small pedestrian steps, SL72 or SL82 mesh is commonly used. If the steps are unusually wide, tall, suspended, support retaining walls or connect structurally to a building, the reinforcement must be engineered.

Do not randomly dowel into an existing slab or footing unless you know the structural arrangement. In many home jobs, a compressible isolation joint is safer than forcing a rigid connection.

Step 7: 7️⃣ Order or mix the concrete correctly

For external steps, use durable concrete suitable for weather exposure. A 25-32 MPa ready-mix is a good choice for residential foot traffic.

If mixing by hand or mixer:

General purpose mix: 1:2:3
Structural mix: 1:1.5:2.5

Add only enough water to make the concrete workable. Overwatering weakens the concrete, increases shrinkage and makes finishing harder.

As a quick example, 3 steps at 1200 mm wide with 170 mm risers and 300 mm treads need roughly 0.37 m³ of concrete, so you would order about 0.40 m³ to allow for waste and spillage.

A good rule:

Under 0.20-0.25 m³: bagged premix can be practical
Over 0.25-0.30 m³: mini-mix delivery is usually faster, cleaner and often better value

Step 8: 8️⃣ Pour and compact the concrete

Dampen the base lightly before the pour so it does not suck moisture out of the fresh concrete.

Place concrete starting from the bottom step and work upward. Push it well into corners and along riser boards. Use a shovel, rod or gentle tapping on the forms to remove trapped air.

Do not dump all the concrete in one heap and try to drag it around. Place it close to its final position.

Make sure reinforcement stays at the correct height while pouring. Lift mesh slightly if needed so it remains embedded with proper cover.

Strike off each tread with a straightedge and fill any low spots immediately.

Step 9: 9️⃣ Finish the treads and edges

Once the concrete has been struck off, float the surface with a magnesium float to close it up.

Then:

Edge the front nosings with an edging tool, typically 10-15 mm
Re-check the fall on each tread
Smooth any ridges or hollows
Apply a broom finish once the surface has firmed up

For external steps, a broom finish is the safest option. Run the broom across each tread to create grip, especially for wet conditions.

Avoid over-trowelling. A slick, polished surface may look tidy on the day but becomes slippery and can scale or craze.

Step 10: 🔟 Cure, strip forms and protect the new steps

Concrete needs moisture to gain strength. As soon as the surface is hard enough not to mark, begin curing.

Good curing options:

Cover with plastic sheeting
Apply curing compound
Mist lightly and keep covered

Aim to cure for at least 7 days. In hot, windy Australian conditions, curing is critical.

Strip the riser forms after about 24-48 hours if the concrete is firm enough. Avoid heavy use for at least 7 days and remember concrete reaches full design strength at about 28 days.

If desired, apply a penetrating sealer after the concrete has fully cured.

Common Mistakes to Avoid

1.Making risers and treads inconsistent. Even a small variation feels unsafe and looks unprofessional.
2.Skipping proper base compaction. Poorly compacted ground is one of the main causes of cracking and settlement.
3.Using weak or poorly braced formwork. If the form bows during the pour, the finished steps will be crooked.
4.Adding too much water to the mix. This weakens the concrete and often leads to dusty, cracked or flaky surfaces.
5.Finishing the surface too smooth. External steps should have a slip-resistant broom finish, not a polished trowel finish.

Pro Tips

💡 Order about 10% more concrete than your calculated volume. Running short mid-pour creates cold joints and messy patching.
💡 For one-off jobs, hire the plate compactor and mixer, but buy the hand tools. That is usually the best value for DIY homeowners.
💡 If the steps are against the house, leave a 10 mm expansion joint so movement does not crack the wall or slab edge.
💡 Pour in mild weather if possible. Hot sun and wind can ruin the finish and make curing much harder.
💡 A simple broom finish and neat edged nosings often look better and last longer than trying for a fancy trowelled finish on outdoor steps.

Recommended Tools

🔧 Recommended Tools

OX Pro Magnesium Float — reliable for flattening and closing the surface before final texture
Spear & Jackson or Stabila laser/level kit — helps keep risers and treads accurate
Husqvarna plate compactor (hire) — worth hiring rather than buying for proper base preparation
Makita paddle mixer or small Belle mixer — useful if using bagged premix on smaller jobs
OX Pro Edger and concrete broom — gives clean nosings and a safe non-slip finish

Frequently asked questions

What is involved in build concrete steps?
Concrete steps are a durable, low-maintenance way to improve front entries, garden paths and access on sloping blocks. For most homeowners, the job comes down to good set-out, solid base preparation, strong formwork and careful finishing. This guide covers simple cast-in-place external concrete ste
What skill level do I need for build concrete steps?
Intermediate — Estimated time: 1-2 days build time, plus 7 days curing before regular use and 28 days to full concrete strength
What are common mistakes when build concrete steps?
1. Making risers and treads inconsistent. Even a small variation feels unsafe and looks unprofessional. 2. Skipping proper base compaction. Poorly compacted ground is one of the main causes of cracking and settlement. 3. Using weak or poorly braced formwork. If the form bows during the pour, the finished steps will be crooked. 4. Adding too much water to the mix. This weakens the concrete and o
What tools do I need for build concrete steps?
This guide includes a comprehensive tools list. Key building & construction tools are detailed in the Tools Required section.
What is the Australian standard for concrete strength in external steps?
The Australian standard AS 3600:2018 Concrete Structures recommends a minimum 25 MPa concrete strength for external residential applications, with 32 MPa often preferred for enhanced durability and resistance to weathering. This ensures the steps can withstand Australian environmental conditions and foot traffic over time.
How long does concrete need to cure before use in Australia?
In Australia, concrete steps require a minimum of 7 days curing before light foot traffic and 28 days to reach their full design strength. Proper curing, as per AS 3600:2018, is critical for achieving optimal strength and preventing surface cracking, especially in varying Australian climates.
What PPE is mandatory for concrete work in Australia?
According to SafeWork Australia guidelines, mandatory PPE for concrete work includes safety glasses (AS/NZS 1337.1), hearing protection (AS/NZS 1270), P2 dust masks (AS/NZS 1716), alkali-resistant gloves, long sleeves, and steel-cap boots (AS/NZS 2210.3). This protects against chemical burns, dust inhalation, and physical injury.
What is the National Construction Code (NCC) requirement for step dimensions?
The National Construction Code (NCC) Volume Two, Part 3.9.1, specifies that risers for steps must be between 115 mm and 190 mm, and treads between 240 mm and 355 mm. These dimensions, along with consistent rise and going, are crucial for safe and compliant step construction in Australia.

Written by Bricko, the Building & Construction specialist at VIC.Tools.