How to dig and pour strip footings
Strip footings are the standard continuous footing system used under loadbearing walls for extensions, boundary walls, small structures and masonry construction. The job is straightforward in principle, but on site the quality of the set-out, founding depth, trench cleanliness, reinforcement placeme
- Skill level
- Advanced
- Time
- 1–3 days for a small footing run, depending on excavation conditions, access, reinforcement complexity and concrete supply
- Trade
- Building & Construction
- Updated
- 29 November 2026
Tools you will need
- Rotary laser level or dumpy level with staff for set
- Tape measures in 5 m, 8 m and 30 m
- Excavator in 1.7 t
- Shovels, trenching spades and long
- Pick/mattock for hard ground and trimming
- Reo cutter/bender or battery angle grinder with metal cut
- Rebar tying tools and tie wire
- Bolt cutters and fencing pliers
- Wheelbarrows, concrete rakes and come
- Pump hose access gear if using line pump or boom pump
🧱 How to Dig and Pour Strip Footings for Australian Building Work
What are strip footings and why are they used in Australia?
Strip footings are the standard continuous footing system used under loadbearing walls for extensions, boundary walls, small structures and masonry construction. The job is straightforward in principle, but on site the quality of the set-out, founding depth, trench cleanliness, reinforcement placement and concrete placement all directly affect compliance, bearing performance and crack control.
For Australian work, strip footings must be constructed to the approved engineering drawings and relevant standards, particularly AS 3600, AS 2870, AS 3700, the NCC, and applicable state authority and council requirements. Any structural footing dimensions, reinforcement schedules or variations require engineering approval.
What skill level is required for digging and pouring strip footings?
Advanced — Estimated time: 1–3 days for a small footing run, depending on excavation conditions, access, reinforcement complexity and concrete supply
What essential tools are needed for strip footing excavation and pouring?
🔧 Tools Required
Materials Required
Safety Requirements
⚠️ Safety Requirements
Step-by-Step Guide
Step 1: 1️⃣ Review drawings, approvals and site conditions
Start by checking the latest approved architectural, structural and civil drawings. Confirm the footing type, width, depth, reinforcement schedule, step locations, laps, dowels, concrete strength, founding requirements and any notes on site classification.
For residential and small building work, footing design commonly references AS 2870 for site classification and residential footing performance, while concrete design and reinforcement detailing are governed by AS 3600. If the footing supports masonry, check wall requirements against AS 3700.
Confirm:
If the founding material on site does not match the assumptions in the drawings, stop and refer it back to the engineer before proceeding.
Step 2: 2️⃣ Set out profiles, lines and footing locations
Install profiles or batter boards clear of the excavation zone so string lines can remain in place during digging. Transfer building lines and offsets accurately from the survey control or nominated site datum.
Mark:
Use a laser or dumpy level to establish excavation depth from benchmark. For wall footings, accuracy in both line and level is critical, especially where masonry, boundary walls or retaining elements will sit directly above.
💡 Check diagonals for square and re-check all profiles after machine access starts. Small set-out errors at footing stage become major wall alignment issues later.
Step 3: 3️⃣ Locate services and prepare for excavation
Before digging, confirm all underground services including power, gas, water, sewer, stormwater and communications. Never rely solely on plans; pothole or hand expose suspect service zones.
Clear vegetation, loose debris, topsoil and soft organic material from the excavation area. Strip unsuitable surface material until you reach firm natural ground or the engineered founding layer.
Where access is tight or boundaries are close, plan:
If trench side stability is doubtful due to sandy, wet or fill conditions, arrange shoring or formwork before over-excavation occurs.
Step 4: 4️⃣ Excavate the strip footing trench to line, width and depth
Excavate to the exact dimensions shown on the structural drawings. Typical strip footing widths may range from 300 mm to 600 mm or more, with depths commonly 300 mm to 700 mm depending on loads, site class and engineering design, but always follow the nominated schedule.
Key trade requirements:
Where over-excavation occurs, rectify only as directed by the engineer, commonly with compacted engineered fill or additional concrete of approved strength.
If the trench is in reactive clay, avoid leaving it open longer than necessary, especially in wet weather or extreme drying conditions.
Step 5: 5️⃣ Inspect founding material and trim the base
Once excavation is complete, inspect the founding material. The base must be firm, consistent and free from mud, slush, roots, topsoil and uncompacted loose material.
Trim by hand to final level. Use the laser frequently and check several points across width and along length. If the base is soft, saturated or variable:
On some jobs, a thin blinding layer or lean-mix concrete is used to create a clean, level base for reinforcement placement. This is especially helpful in wet or rough trenches.
💡 A clean trench base saves time during steel fixing and greatly improves cover control.
Step 6: 6️⃣ Install formwork where trenches cannot hold shape
Not all strip footings are cast directly into ground. Use formwork where:
Set forms true to line and level, brace properly and check internal width. Ensure any formed steps match the engineer’s detail and allow adequate lap lengths and bar continuity.
Release agents can be used on form faces where a clean strip is required, but keep them clear of reinforcement and construction joints.
Step 7: 7️⃣ Fix reinforcement and maintain cover
Place reinforcement strictly to the footing schedule. Common arrangements include bottom bars, trench mesh, ligatures, corner bars, starter bars and dowels for intersecting walls or columns.
Critical points:
Concrete cover is a compliance issue under AS 3600. The exact cover depends on exposure classification and footing detail, so use the engineer’s nominated cover, commonly 50 mm or greater for cast-in-ground footings.
If holding bolts or starter bars are required, set them now and brace them so they remain plumb during pouring.
💡 Paint-mark lap zones and bar callouts before inspection. It speeds up engineer or certifier sign-off and reduces missed steel.
Step 8: 8️⃣ Complete pre-pour checks and inspections
Before concrete arrives, carry out a full pre-pour inspection. This is where most avoidable defects are caught.
Check:
Take photos of steel, cover spacers and trench condition before the pour. For commercial or higher-risk work, record batch requirements and planned test procedures in advance.
Step 9: 9️⃣ Order and place concrete correctly
For structural strip footings, ready-mix concrete is the standard. Order the strength, slump and aggregate size to suit the footing dimensions and reinforcement congestion. Many strip footings are poured in 20 MPa or 25 MPa concrete, but the drawings govern.
Where hand mixing is used only for very small approved jobs:
However, for professional structural footing work, a batched ready-mix supply is the correct approach for consistency and compliance.
During placement:
Bring concrete to the nominated top level. If the footing will receive masonry or formwork above, strike the surface level enough to suit the next trade stage.
Step 10: 🔟 Finish, cure and protect the footing
Strip footings generally do not need a decorative finish, but the top surface should be level, consistent and ready to receive the wall, slab edge, blockwork or starter construction.
Immediately after placement:
Good curing improves strength gain and reduces shrinkage cracking. In hot, windy or dry conditions, use curing compound, wet hessian or plastic sheeting as appropriate once the surface has firmed.
Avoid loading the footing early. Allow adequate curing time before brickwork, blockwork, framing or backfilling.
Step 11: 1️⃣1️⃣ Strip forms, backfill and prepare for the next stage
Once the concrete has achieved sufficient strength, remove any side forms carefully without damaging edges. Backfill only after confirming:
Place backfill in controlled layers and compact appropriately to avoid future settlement beside walls or slab edges. Keep heavy plant away from green concrete and unsupported masonry.
If the footing supports masonry, ensure the bearing surface is clean and within tolerance before commencing brick or block laying.
Common Mistakes to Avoid
Pro Tips
Recommended Tools
🔧 Recommended Tools
Frequently asked questions
- What is involved in dig and pour strip footings?
- Strip footings are the standard continuous footing system used under loadbearing walls for extensions, boundary walls, small structures and masonry construction. The job is straightforward in principle, but on site the quality of the set-out, founding depth, trench cleanliness, reinforcement placeme
- What skill level do I need for dig and pour strip footings?
- Advanced — Estimated time: 1–3 days for a small footing run, depending on excavation conditions, access, reinforcement complexity and concrete supply
- What are common mistakes when dig and pour strip footings?
- 1. Excavating to approximate depth instead of laser-controlled level, resulting in variable footing thickness and non-compliant founding. 2. Pouring onto soft, wet or contaminated trench bottoms without trimming or engineer review. 3. Letting reinforcement sit on the ground with inadequate cover, which breaches AS 3600 durability requirements. 4. Over-digging trench sections and loosely bac
- What tools do I need for dig and pour strip footings?
- This guide includes a comprehensive tools list. Key building & construction tools are detailed in the Tools Required section.
- What is the Australian standard for concrete cover in footings?
- The Australian standard for concrete cover in footings is AS 3600:2018, which specifies minimum cover requirements to protect reinforcement from corrosion. For footings in contact with the ground, a minimum cover of 40mm is typically required, though this can vary based on exposure conditions and engineer specifications. Always consult the approved engineering drawings.
- How deep should strip footings be in Australia?
- The required depth for strip footings in Australia is determined by site-specific geotechnical conditions, soil bearing capacity, and the structure's load, as specified by an engineer. AS 2870:2011 provides guidance for residential slabs and footings, but the final depth must adhere to the approved engineering design to ensure adequate bearing and stability.
- What are the legal requirements for excavator operation on Australian sites?
- According to SafeWork Australia, operators of excavators on Australian sites must hold the appropriate high-risk work licence (e.g., Excavator Licence LE) and be deemed competent. All machinery must be regularly inspected and maintained in accordance with manufacturer specifications and relevant Australian Standards to ensure safe operation.
- What is the instant asset write-off threshold for tradies in Australia?
- For the 2023-24 financial year, the instant asset write-off threshold in Australia is $20,000 for eligible businesses with an aggregated turnover of less than $50 million. This allows tradies to immediately deduct the full cost of eligible assets, such as excavators or laser levels, up to this amount. Always confirm current thresholds with the Australian Taxation Office (ATO).
Written by Bricko, the Building & Construction specialist at VIC.Tools.