How to dig and pour strip footings

Strip footings are the standard continuous footing system used under loadbearing walls for extensions, boundary walls, small structures and masonry construction. The job is straightforward in principle, but on site the quality of the set-out, founding depth, trench cleanliness, reinforcement placeme

Skill level
Advanced
Time
1–3 days for a small footing run, depending on excavation conditions, access, reinforcement complexity and concrete supply
Trade
Building & Construction
Updated
29 November 2026

Tools you will need

  • Rotary laser level or dumpy level with staff for set
  • Tape measures in 5 m, 8 m and 30 m
  • Excavator in 1.7 t
  • Shovels, trenching spades and long
  • Pick/mattock for hard ground and trimming
  • Reo cutter/bender or battery angle grinder with metal cut
  • Rebar tying tools and tie wire
  • Bolt cutters and fencing pliers
  • Wheelbarrows, concrete rakes and come
  • Pump hose access gear if using line pump or boom pump

🧱 How to Dig and Pour Strip Footings for Australian Building Work

What are strip footings and why are they used in Australia?

Strip footings are the standard continuous footing system used under loadbearing walls for extensions, boundary walls, small structures and masonry construction. The job is straightforward in principle, but on site the quality of the set-out, founding depth, trench cleanliness, reinforcement placement and concrete placement all directly affect compliance, bearing performance and crack control.

For Australian work, strip footings must be constructed to the approved engineering drawings and relevant standards, particularly AS 3600, AS 2870, AS 3700, the NCC, and applicable state authority and council requirements. Any structural footing dimensions, reinforcement schedules or variations require engineering approval.

What skill level is required for digging and pouring strip footings?

Advanced — Estimated time: 1–3 days for a small footing run, depending on excavation conditions, access, reinforcement complexity and concrete supply

What essential tools are needed for strip footing excavation and pouring?

🔧 Tools Required

Rotary laser level or dumpy level with staff for set-out and depth control
String lines, line pins, profiles/batter boards and marking paint
Tape measures in 5 m, 8 m and 30 m
Excavator in 1.7 t–3.5 t class for trenching, or trenching machine where access suits
Shovels, trenching spades and long-handle clean-up shovels
Pick/mattock for hard ground and trimming
Plate compactor for founding layer preparation where specified
Concrete vibrator with small head for narrow trenches and congested reinforcement
Reo cutter/bender or battery angle grinder with metal cut-off discs
Rebar tying tools and tie wire
Bolt cutters and fencing pliers
Wheelbarrows, concrete rakes and come-alongs
Screed board, hand float and edging tools if top finish is exposed
Formwork tools: hammer, impact driver, circular saw, stakes, clamps
Pump hose access gear if using line pump or boom pump
PPE: hard hat, gloves, eye protection, steel caps, hearing protection, hi-vis, P2 respirator

Materials Required

Approved footing set-out plan and structural engineering drawings
Concrete to engineer’s specification, commonly 20 MPa, 25 MPa or higher as nominated
If hand mixing only for minor non-structural work: 1:2:3 general purpose or 1:1.5:2.5 structural, but ready-mix is preferred for structural footings
Reinforcement bars and trench mesh to engineer’s schedule, commonly N12, N16 or trench mesh cages
Rebar chairs, bar spacers or dobies to maintain cover
Tie wire
Formwork timber, pegs, stakes and bracing where trench walls will not hold or where footings step
Blinding layer material if specified, such as sand, crusher dust or lean-mix concrete
Termite management components where required by the design and local requirements
Starter bars, dowels or hold-down bolts if required for walling or columns
Poly sheeting for weather protection and curing management where needed
Water for clean-up and curing
Survey pegs, profiles and string line consumables
Marker paint and identification tags for reinforcement

Safety Requirements

⚠️ Safety Requirements

Confirm underground services before excavation through Before You Dig Australia and physical service locating where required.
Structural footings are not a “set by eye” task. Build strictly to the engineer’s footing schedule and approved plans.
Trench excavation presents collapse risk. Provide benching, battering, shoring or exclusion zones as required by soil conditions and trench depth.
Follow site SWMS requirements for excavation, concrete placement, powered equipment and reinforcement handling.
Wear PPE: hard hat, safety glasses, gloves, steel-capped boots, hi-vis clothing, hearing protection and P2 respirator when cutting reo or exposed cement products.
Use correct manual handling for reinforcement, formwork and hose work. Long bars and mesh require team lifts or mechanical handling.
Keep personnel clear of suspended excavator buckets and pump lines under pressure.
Wet concrete is caustic. Avoid skin contact and wash off immediately.
Maintain safe access/egress to trenches and manage slips around wet excavation edges.
Scaffolding or edge protection may be required where footing excavations are adjacent to drops, retaining works or elevated slab edges.
Waterproofing associated with adjoining wet areas or retaining interfaces must comply with AS 3740 where relevant, though strip footings themselves are governed primarily by structural and geotechnical requirements.

Step-by-Step Guide

Step 1: 1️⃣ Review drawings, approvals and site conditions

Start by checking the latest approved architectural, structural and civil drawings. Confirm the footing type, width, depth, reinforcement schedule, step locations, laps, dowels, concrete strength, founding requirements and any notes on site classification.

For residential and small building work, footing design commonly references AS 2870 for site classification and residential footing performance, while concrete design and reinforcement detailing are governed by AS 3600. If the footing supports masonry, check wall requirements against AS 3700.

Confirm:

Building alignment and setbacks
Easements and boundary offsets
Finished floor levels and datum
Termite management details
Stormwater or drainage crossings
Any requirement for inspection before pour

If the founding material on site does not match the assumptions in the drawings, stop and refer it back to the engineer before proceeding.

Step 2: 2️⃣ Set out profiles, lines and footing locations

Install profiles or batter boards clear of the excavation zone so string lines can remain in place during digging. Transfer building lines and offsets accurately from the survey control or nominated site datum.

Mark:

Footing centreline
Footing width
Step points
Internal and external corners
Pier or pad intersections
Starter bar locations

Use a laser or dumpy level to establish excavation depth from benchmark. For wall footings, accuracy in both line and level is critical, especially where masonry, boundary walls or retaining elements will sit directly above.

💡 Check diagonals for square and re-check all profiles after machine access starts. Small set-out errors at footing stage become major wall alignment issues later.

Step 3: 3️⃣ Locate services and prepare for excavation

Before digging, confirm all underground services including power, gas, water, sewer, stormwater and communications. Never rely solely on plans; pothole or hand expose suspect service zones.

Clear vegetation, loose debris, topsoil and soft organic material from the excavation area. Strip unsuitable surface material until you reach firm natural ground or the engineered founding layer.

Where access is tight or boundaries are close, plan:

Excavator swing clearance
Stockpile location
Spoil removal
Concrete truck or pump setup
Safe pedestrian access around trenches

If trench side stability is doubtful due to sandy, wet or fill conditions, arrange shoring or formwork before over-excavation occurs.

Step 4: 4️⃣ Excavate the strip footing trench to line, width and depth

Excavate to the exact dimensions shown on the structural drawings. Typical strip footing widths may range from 300 mm to 600 mm or more, with depths commonly 300 mm to 700 mm depending on loads, site class and engineering design, but always follow the nominated schedule.

Key trade requirements:

Keep trench bottoms level and undisturbed
Do not over-dig and backfill loosely
Maintain full footing width along the run
Cut clean vertical or battered sides depending on soil stability
Form steps neatly where footing levels change
Remove all loose spoil from the trench base

Where over-excavation occurs, rectify only as directed by the engineer, commonly with compacted engineered fill or additional concrete of approved strength.

If the trench is in reactive clay, avoid leaving it open longer than necessary, especially in wet weather or extreme drying conditions.

Step 5: 5️⃣ Inspect founding material and trim the base

Once excavation is complete, inspect the founding material. The base must be firm, consistent and free from mud, slush, roots, topsoil and uncompacted loose material.

Trim by hand to final level. Use the laser frequently and check several points across width and along length. If the base is soft, saturated or variable:

Excavate further only with approval
Replace unsuitable material as specified
Consider blinding where required
Call the engineer if founding conditions differ from design assumptions

On some jobs, a thin blinding layer or lean-mix concrete is used to create a clean, level base for reinforcement placement. This is especially helpful in wet or rough trenches.

💡 A clean trench base saves time during steel fixing and greatly improves cover control.

Step 6: 6️⃣ Install formwork where trenches cannot hold shape

Not all strip footings are cast directly into ground. Use formwork where:

Soil will not stand safely
Footings project above ground
Step-downs need clean faces
Boundary conditions require vertical control
Rock or uneven trench walls make dimensions unreliable

Set forms true to line and level, brace properly and check internal width. Ensure any formed steps match the engineer’s detail and allow adequate lap lengths and bar continuity.

Release agents can be used on form faces where a clean strip is required, but keep them clear of reinforcement and construction joints.

Step 7: 7️⃣ Fix reinforcement and maintain cover

Place reinforcement strictly to the footing schedule. Common arrangements include bottom bars, trench mesh, ligatures, corner bars, starter bars and dowels for intersecting walls or columns.

Critical points:

Use correct bar diameter and grade
Tie bars securely so they do not move during pour
Maintain lap lengths exactly as detailed
Place corner and intersection reinforcement as specified
Support steel on chairs or dobies to maintain cover
Do not allow steel to sit in mud or directly on the soil

Concrete cover is a compliance issue under AS 3600. The exact cover depends on exposure classification and footing detail, so use the engineer’s nominated cover, commonly 50 mm or greater for cast-in-ground footings.

If holding bolts or starter bars are required, set them now and brace them so they remain plumb during pouring.

💡 Paint-mark lap zones and bar callouts before inspection. It speeds up engineer or certifier sign-off and reduces missed steel.

Step 8: 8️⃣ Complete pre-pour checks and inspections

Before concrete arrives, carry out a full pre-pour inspection. This is where most avoidable defects are caught.

Check:

Width, depth and line of trench
Step locations and level changes
Trench base cleanliness
Reinforcement size, laps, tying and cover
Starter bars and anchors
Formwork integrity and bracing
Pump access and pour sequence
Weather forecast
Inspection sign-off if required by certifier, engineer or council

Take photos of steel, cover spacers and trench condition before the pour. For commercial or higher-risk work, record batch requirements and planned test procedures in advance.

Step 9: 9️⃣ Order and place concrete correctly

For structural strip footings, ready-mix concrete is the standard. Order the strength, slump and aggregate size to suit the footing dimensions and reinforcement congestion. Many strip footings are poured in 20 MPa or 25 MPa concrete, but the drawings govern.

Where hand mixing is used only for very small approved jobs:

1:2:3 = general purpose
1:1.5:2.5 = structural

However, for professional structural footing work, a batched ready-mix supply is the correct approach for consistency and compliance.

During placement:

Pour continuously where possible
Avoid segregation from excessive drop height
Work along the trench methodically
Use a vibrator carefully to consolidate around steel and step sections
Do not over-vibrate, especially in wet mixes
Keep reinforcement and starter bars in position

Bring concrete to the nominated top level. If the footing will receive masonry or formwork above, strike the surface level enough to suit the next trade stage.

Step 10: 🔟 Finish, cure and protect the footing

Strip footings generally do not need a decorative finish, but the top surface should be level, consistent and ready to receive the wall, slab edge, blockwork or starter construction.

Immediately after placement:

Re-check starter bars and bolts for line and plumb
Patch low spots while concrete is plastic
Protect from rain impact, rapid drying and contamination
Cure in accordance with the concrete supplier’s and engineer’s requirements

Good curing improves strength gain and reduces shrinkage cracking. In hot, windy or dry conditions, use curing compound, wet hessian or plastic sheeting as appropriate once the surface has firmed.

Avoid loading the footing early. Allow adequate curing time before brickwork, blockwork, framing or backfilling.

Step 11: 1️⃣1️⃣ Strip forms, backfill and prepare for the next stage

Once the concrete has achieved sufficient strength, remove any side forms carefully without damaging edges. Backfill only after confirming:

Concrete strength is adequate
Waterproofing or termite detailing is complete where applicable
Drainage lines or penetrations are installed
The next structural stage is ready

Place backfill in controlled layers and compact appropriately to avoid future settlement beside walls or slab edges. Keep heavy plant away from green concrete and unsupported masonry.

If the footing supports masonry, ensure the bearing surface is clean and within tolerance before commencing brick or block laying.

Common Mistakes to Avoid

1.Excavating to approximate depth instead of laser-controlled level, resulting in variable footing thickness and non-compliant founding.
2.Pouring onto soft, wet or contaminated trench bottoms without trimming or engineer review.
3.Letting reinforcement sit on the ground with inadequate cover, which breaches AS 3600 durability requirements.
4.Over-digging trench sections and loosely backfilling them before pour, creating weak zones under the footing.
5.Failing to check step locations, dowels and hold-down positions before concrete arrives.
6.Using the wrong concrete slump or adding excess water on site, which reduces strength and increases shrinkage.
7.Leaving trenches open too long in reactive or wet ground, causing collapse, softening or dimensional loss.

Pro Tips

1.Mark finished concrete level on stakes or form pins every 2 m–3 m so the pour crew can maintain top level without constant re-measuring.
2.For long footing runs, stage excavation and pouring to suit weather and ground stability instead of opening the entire trench at once.
3.Use dobies rather than improvised brick or rubble packing under reinforcement. Cover accuracy is much better and inspections are cleaner.
4.If pumping into narrow trenches, nominate a concrete mix that suits hose placement and steel congestion. It reduces segregation and speeds consolidation.
5.Hire larger plant only when production justifies it. For short runs or tight sites, a 1.7 t excavator and small plate compactor are usually more economical than purchasing, while laser levels and hand tools are worth owning for repeat footing work.

Recommended Tools

🔧 Recommended Tools

Leica Rugby rotary laser level — reliable for accurate footing depth and level transfer
Wacker Neuson plate compactor — solid choice for trench-edge and backfill compaction
Hikoki or Makita battery angle grinder — efficient for cutting reinforcement on footing jobs
Flextool concrete vibrator — suitable for consolidating concrete in narrow strip trenches
OX Pro stringline and profile gear — dependable for precise trade set-out

Frequently asked questions

What is involved in dig and pour strip footings?
Strip footings are the standard continuous footing system used under loadbearing walls for extensions, boundary walls, small structures and masonry construction. The job is straightforward in principle, but on site the quality of the set-out, founding depth, trench cleanliness, reinforcement placeme
What skill level do I need for dig and pour strip footings?
Advanced — Estimated time: 1–3 days for a small footing run, depending on excavation conditions, access, reinforcement complexity and concrete supply
What are common mistakes when dig and pour strip footings?
1. Excavating to approximate depth instead of laser-controlled level, resulting in variable footing thickness and non-compliant founding. 2. Pouring onto soft, wet or contaminated trench bottoms without trimming or engineer review. 3. Letting reinforcement sit on the ground with inadequate cover, which breaches AS 3600 durability requirements. 4. Over-digging trench sections and loosely bac
What tools do I need for dig and pour strip footings?
This guide includes a comprehensive tools list. Key building & construction tools are detailed in the Tools Required section.
What is the Australian standard for concrete cover in footings?
The Australian standard for concrete cover in footings is AS 3600:2018, which specifies minimum cover requirements to protect reinforcement from corrosion. For footings in contact with the ground, a minimum cover of 40mm is typically required, though this can vary based on exposure conditions and engineer specifications. Always consult the approved engineering drawings.
How deep should strip footings be in Australia?
The required depth for strip footings in Australia is determined by site-specific geotechnical conditions, soil bearing capacity, and the structure's load, as specified by an engineer. AS 2870:2011 provides guidance for residential slabs and footings, but the final depth must adhere to the approved engineering design to ensure adequate bearing and stability.
What are the legal requirements for excavator operation on Australian sites?
According to SafeWork Australia, operators of excavators on Australian sites must hold the appropriate high-risk work licence (e.g., Excavator Licence LE) and be deemed competent. All machinery must be regularly inspected and maintained in accordance with manufacturer specifications and relevant Australian Standards to ensure safe operation.
What is the instant asset write-off threshold for tradies in Australia?
For the 2023-24 financial year, the instant asset write-off threshold in Australia is $20,000 for eligible businesses with an aggregated turnover of less than $50 million. This allows tradies to immediately deduct the full cost of eligible assets, such as excavators or laser levels, up to this amount. Always confirm current thresholds with the Australian Taxation Office (ATO).

Written by Bricko, the Building & Construction specialist at VIC.Tools.