How to form up concrete footings

Forming up concrete footings is a critical foundation task that sets out the structural load path for walls, columns and slabs. Accurate excavation, set-out, formwork installation and level control are essential to ensure compliance with AS 3600 Concrete Structures, engineering drawings, and rel

Skill level
Advanced
Time
1–2 days depending on footing length, site access, soil conditions and complexity
Trade
Building & Construction
Updated
28 November 2026

Tools you will need

  • Dumpy level as backup for set
  • Tape measures 5 m, 8 m and 30 m
  • String lines, line pins and profile boards
  • Framing square and builder’s square
  • Marking paint and chalk line
  • Shovels, trenching shovel and trenching hoe
  • Plate compactor for base preparation where required
  • Circular saw or drop saw for cutting formwork timber
  • Impact driver and drill
  • Formwork hammer and nail puller

🧱 How to Form Up Concrete Footings

What is involved in forming up concrete footings?

Forming up concrete footings is a critical foundation task that sets out the structural load path for walls, columns and slabs. Accurate excavation, set-out, formwork installation and level control are essential to ensure compliance with AS 3600 Concrete Structures, engineering drawings, and relevant state and council requirements.

This guide covers professional site preparation, set-out, boxing, bracing and pre-pour checks for strip footings and similar formed footing systems used on residential and light commercial work in Australia. All structural footing dimensions, reinforcement details and founding depths must match the engineer’s design and soil classification.

What skill level is required for forming concrete footings?

Advanced — Estimated time: 1–2 days depending on footing length, site access, soil conditions and complexity

What tools are required for forming concrete footings?

Builder’s laser level or rotating laser with receiver for accurate height transfer
Dumpy level as backup for set-out and level checks
Tape measures 5 m, 8 m and 30 m
String lines, line pins and profile boards
Framing square and builder’s square
Marking paint and chalk line
Shovels, trenching shovel and trenching hoe
Plate compactor for base preparation where required
Circular saw or drop saw for cutting formwork timber
Impact driver and drill
Formwork hammer and nail puller
Form ply clamps or timber stakes and nail plates
Crowbar/pry bar
Steel pins or timber pegs for bracing
Rebar chairs and tie wire reel
Reo tying pliers/nips
Spirit level 1200 mm
Vibrator access planning tools and pour sequence layout
Wheelbarrow or site buggy for materials handling
Temporary barrier mesh and safety signage

What materials are needed for concrete footing formwork?

Formwork timber, commonly 90 x 45 mm, 140 x 45 mm or sized to engineer’s footing depth
Form ply where specified for cleaner finish or complex shapes
Timber pegs or hardwood stakes at suitable spacing
Steel star pickets or form pins where appropriate
Nails, screws and bracing fixings
String line and profile boards
Crusher dust or compacted granular material for trimming base if specified
Poly sheet if nominated in project documentation
Reinforcement bars and trench mesh to engineer’s schedule
Rebar chairs and bar supports with correct cover allowance
Tie wire
Termite management components where required by project specification
Starter bars, dowels and hold-down bolts if shown on drawings
Concrete to specified strength class, typically 20 MPa, 25 MPa or as engineered
If site-mixing is approved for non-structural ancillary work: 1:2:3 general purpose, 1:1.5:2.5 structural

(Note: structural footings for buildings are generally supplied as engineered premix, not hand-mixed)

Safety Requirements

Wear PPE: hard hat, safety boots, gloves, eye protection, hearing protection and hi-vis clothing
Use correct manual handling techniques for formwork timber, reinforcement and wet concrete loads
Ensure trench safety controls are in place; deeper excavations may require battering, benching or engineered shoring
Maintain exclusion zones around excavation edges and plant movement areas
Check underground services before digging using DBYD plans and site verification
Use compliant access/egress for trenches and excavations
Scaffolding or edge protection may be required where footing work is adjacent to drops or suspended areas
Wet concrete can cause chemical burns; avoid skin contact
Structural work must follow engineer-certified drawings and relevant approvals
Concrete footing work must comply with AS 3600, and associated excavation/formwork practices should align with project documentation, NCC requirements and geotechnical recommendations

Step-by-Step Guide

Step 1: Review engineering, soil classification and set-out information

Confirm footing type, dimensions, founding depth, reinforcement schedule, cover requirements, construction joints and any step-downs from the engineer’s drawings. Check the site soil classification, geotechnical notes and slab or wall interface details before starting any excavation or formwork.

Verify all boundary offsets, building lines and datum levels against the survey set-out. On extensions, confirm ties to existing structures, existing footing levels and any underpinning interfaces before disturbing ground.

For residential footing systems, pay particular attention to founding depth below finished ground level, minimum bearing conditions and articulation requirements. Do not assume standard trench sizes; use only the documented dimensions.

Step 2: Establish profiles, string lines and datum levels

Set profile boards clear of excavation lines so they remain undisturbed during digging. Run string lines to establish footing centre-lines or external faces, depending on the formwork method and site conditions.

Transfer the site datum using a laser or dumpy level and mark top-of-footing, top-of-form and excavation depth references on the profiles. Check diagonals for square and confirm all critical dimensions before breaking ground.

On stepped footings, clearly mark each transition point and level change. It is much easier to correct layout errors before excavation than after reinforcement is in place.

Step 3: Excavate to line, width and founding depth

Excavate footing trenches or pad locations to the exact engineer-specified width and depth. Keep trench bottoms as level and undisturbed as possible, particularly in reactive or soft soils where over-excavation can weaken bearing capacity.

Trim the base by hand where machine excavation has left loose material. Remove all softened, wet or organic material and replace only in accordance with engineering advice. If groundwater or seepage is present, dewater and stabilise before forming.

Where the footing is fully trench-poured in stable ground, side forms may be unnecessary in some sections. Where excavation faces are irregular, collapsing or oversized, full boxing will be required to maintain the specified concrete dimensions.

Step 4: Trim, compact and prepare the footing base

Check the trench bottom with a laser and straighten all footing lines. If the specification allows a compacted granular trimming layer, place and compact it uniformly without creating soft spots or variable footing depth.

Do not use loose spoil to bring levels up. Any build-up material under structural footings must be approved and properly compacted to the documented requirement. Founding surfaces must match the geotechnical and engineering intent.

If the project includes membrane, termite barriers or specific interface treatments, install them only in the sequence required by the documentation so they are not damaged during steel fixing and pouring.

Step 5: Install formwork to the correct dimensions

Box up the footing using straight, clean formwork timber sized to the required footing depth. Common members are 90 x 45 mm or 140 x 45 mm, but deeper footings may require larger sections, form ply or double walers depending on pour pressure and footing height.

Set forms to the string line and fix them to timber stakes or steel pins at regular spacing sufficient to resist movement during the pour. Keep stake spacing tighter on corners, step-downs, intersections and any deeper sections.

Ensure the internal form dimensions exactly match the footing width shown on the drawings. Measure at multiple points along the run and check that forms are plumb, straight and free of bow. If the top of footing is to finish level with the form top, use the laser to set all form edges precisely.

Step 6: Brace corners, junctions and step-downs

Reinforce all corners and tee-junctions with additional stakes, cleats and external bracing. These areas are the first to move during concrete placement, especially when pumping into confined footing forms.

For stepped footings, form the risers securely and check that each step length and height complies with the drawings. Stop-ends must be tight enough to prevent grout loss while still allowing concrete placement and vibration.

Where hold-down bolts, starter bars or column bars are required, ensure there is enough form clearance and bracing to keep everything in position during the pour.

Step 7: Fix reinforcement and maintain cover

Install reinforcement strictly to the engineer’s schedule, including bar sizes, laps, trench mesh orientation, corner bars and dowels. Tie all steel securely so it cannot roll, sag or lift during placement.

Support reinforcement on approved bar chairs to maintain the specified cover from the trench bottom and side forms. Cover is critical for durability and compliance under AS 3600. Do not use bricks, timber offcuts or rubble as makeshift supports.

Check lap lengths, starter bar projection and any penetrations through the footing before sign-off. Reinforcement must be clean and reasonably free from mud, heavy rust scale and contaminants before concrete placement.

Step 8: Check penetrations, services and cast-in items

Before the pour, confirm all hydraulic, electrical and stormwater penetrations are in the correct position and sleeved where required. Recheck against services drawings, wall locations and finished slab levels.

Install any cast-in bolts, post anchors, starter bars or connection plates using templates where accuracy is critical. Mark their locations on the formwork and verify dimensions from fixed control points rather than measuring from loose excavation edges.

This stage is also the last efficient opportunity to confirm termite management interfaces, articulation details and future masonry set-downs.

Step 9: Complete pre-pour inspection and compliance checks

Carry out a full pre-pour inspection covering dimensions, line, level, squareness, bearing surface, reinforcement, cover, bracing and access for the pour crew. Confirm the excavation is free of loose spoil, standing water and rubbish.

Arrange any mandatory inspections required by the certifier, engineer or local authority before concrete arrives. Structural work often requires documented hold points, especially on engineered residential and commercial projects.

Make sure pour access, pump setup, washout location and concrete order details are locked in. Confirm the specified strength grade, slump, aggregate size and volume before dispatch.

Step 10: Pour, vibrate and monitor form stability

During placement, discharge concrete evenly to avoid overloading one section of formwork. Monitor forms continuously for spread, kick-out or settlement, especially at stop-ends, corners and deep sections.

Use mechanical vibration where required to consolidate concrete around reinforcement and into corners, but do not over-vibrate to the point of segregation. Keep an eye on top levels and screed or rod off to the nominated height.

If using premixed structural concrete, follow the supplier’s placement window and site temperature requirements. For ancillary non-structural site-mix reference only, common ratios are 1:2:3 general purpose and 1:1.5:2.5 structural, though building footings should be supplied to engineered specification.

Step 11: Finish, protect and strip forms

Strike off the top of footing to level or prepare the surface finish required for the next construction stage. Where walls or masonry will bear on the footing, ensure the surface is suitable for set-out and does not leave excessive high spots.

Protect fresh concrete from rain, rapid drying and site traffic. Cure in accordance with project requirements to achieve strength and minimise shrinkage issues. Strip forms only after the concrete has gained sufficient strength to avoid edge damage.

After stripping, inspect the footing for honeycombing, dimensional accuracy and cast-in item alignment. Any rectification to structural footings should be referred to the engineer before proceeding.

Common Mistakes to Avoid

1.Setting out from unreliable reference points instead of fixed survey controls, causing wall and column misalignment
2.Over-excavating trench bases and backfilling with loose spoil, which compromises bearing capacity
3.Allowing formwork to bow or spread because of inadequate staking and bracing
4.Placing reinforcement directly on the ground instead of using approved chairs to maintain cover
5.Pouring before checking penetrations, bolts, starter bars and inspection hold points
6.Ignoring groundwater, soft spots or collapsed trench edges that alter the footing dimensions
7.Assuming “standard” footing sizes rather than following the engineer-certified drawings exactly

Pro Tips

1.💡 Use double string lines or offset profiles on long runs so you can check both line and form face without disturbing control points
2.💡 Pre-cut stakes, cleats and braces in batches before boxing starts to speed up production on repetitive footing runs
3.💡 On reactive sites, keep excavation open time to a minimum so trench bases do not soften before steel and concrete go in
4.💡 Mark top-of-concrete levels directly on the inside of forms at regular intervals to help the pump crew maintain consistent height
5.💡 For stepped footings, build and label each step sequence from the drawings before starting to avoid level confusion on site
6.💡 Hiring a rotary laser, trench compactor or concrete vibrator often makes more economic sense than purchasing if footing work is occasional; high-use crews benefit from owning layout and formwork tools outright

Recommended Tools

Topcon RL-H5A Rotary Laser Level — reliable level transfer for footing set-out and form height control
OX Pro Formwork Hammer — purpose-built for nailing, stripping and form adjustments
Makita 18V Impact Driver — efficient for screws and brace fixing during boxing
Reo Bar Tying Pliers/Nips — essential for fast, secure reinforcement tying
Flextool Concrete Vibrator — suitable for consolidating footing concrete and reducing voids

Frequently asked questions

What is involved in form up concrete footings?
Forming up concrete footings is a critical foundation task that sets out the structural load path for walls, columns and slabs. Accurate excavation, set-out, formwork installation and level control are essential to ensure compliance with AS 3600 Concrete Structures, engineering drawings, and rel
What skill level do I need for form up concrete footings?
Advanced — Estimated time: 1–2 days depending on footing length, site access, soil conditions and complexity
What are common mistakes when form up concrete footings?
1. Setting out from unreliable reference points instead of fixed survey controls, causing wall and column misalignment 2. Over-excavating trench bases and backfilling with loose spoil, which compromises bearing capacity 3. Allowing formwork to bow or spread because of inadequate staking and bracing 4. Placing reinforcement directly on the ground instead of using approved chairs to maintain c
What tools do I need for form up concrete footings?
This guide includes a comprehensive tools list. Key building & construction tools are detailed in the Tools Required section.
What is the Australian standard for concrete footings?
The primary Australian standard for concrete footings is AS 3600 Concrete Structures, which outlines design and construction requirements. For residential applications, AS 2870 Residential slabs and footings also applies, detailing requirements based on soil classification and site conditions. Always consult the latest edition and engineering specifications.
How do you ensure footing levels are accurate?
Accurate footing levels are achieved using a builder’s laser level or rotating laser with a receiver, calibrated regularly according to manufacturer guidelines. A dumpy level serves as a crucial backup for verification. According to AS 3600, level tolerances must be maintained to prevent structural issues and ensure uniform load transfer.
What are the safety considerations for footing excavation?
Safety for footing excavation involves assessing soil stability, providing adequate shoring or battering for trenches deeper than 1.5 metres, and implementing exclusion zones. According to SafeWork Australia's 'Excavation Work' Code of Practice, all excavations must be inspected by a competent person before work commences and after any event that could affect stability.

Written by Bricko, the Building & Construction specialist at VIC.Tools.