Quick answer
Installing reo mesh and bar chairs requires positioning certified plastic spacers at 800mm to 1000mm grid intervals over a continuous damp-proof membrane. Reinforcement mesh sheets must overlap by a minimum of 225mm to 300mm and be tied securely, ensuring reinforcement stays suspended in the top third of the slab.
- Skill level
- Intermediate
- Time
- 0.5-1 day (depending on slab size and complexity)
- Trade
- Building & Construction
- Updated
- 29 November 2026
Tools you will need
- Hitachi / HiKOKI 18V Cordless Rebar Cutter and Bender
- Milwaukee 200mm (8") High-Leverage Ironworker Pliers
- Stabila 1200mm Type 196-2 Heavy-Duty Spirit Level
- Ox Tools 900mm (36") Heavy Duty Bolt Cutters
- Tajima Chalk-Rite Jam-Free Chalk Line Reel
- Makita 18V LXT Brushless 125mm Angle Grinder
- Lufkin 8m Shockforce Dual-Sided Tape Measure
🧱 Installing Reo Mesh and Bar Chairs for Concrete Slabs
What is involved in installing reo mesh and bar chairs for a concrete slab?
This guide details the correct installation of steel reinforcement (reo mesh and bar chairs) for concrete slabs, ensuring structural integrity and compliance with Australian Standards. Proper placement is critical for the slab's load-bearing capacity and crack resistance.
What skill level is required for reo mesh and bar chair installation?
Intermediate — Estimated time: 0.5-1 day (depending on slab size and complexity)
What tools are essential for reo mesh and bar chair installation?
Tape Measure: 8m or 10m for accurate layout. Reo Cutters/Bolt Cutters: Heavy-duty for cutting mesh and rebar. Tie Wire Twister/Nippers: For securing reo. Chalk Line: For marking overlap lines. Grinder with Metal Cutting Disc (optional): For precise cuts on rebar or mesh. Spirit Level: 1200mm for checking chair heights. Shovel/Rake: For final subgrade preparation. Wheelbarrow: For moving materials.What materials are needed for concrete slab reinforcement?
Steel Reinforcing Mesh: SL72, SL82, SL92, etc., as specified by engineering drawings. Bar Chairs: Plastic or steel, varying heights (50mm, 75mm, 100mm, etc.) to achieve required concrete cover. Tie Wire: 1.57mm black annealed tie wire. Plastic Film (Vapour Barrier): 200µm (micron) heavy-duty, if specified.What are the critical safety requirements for working with reo mesh?
⚠️ PPE: Hard hat, safety glasses, high-visibility clothing, steel-capped boots, cut-resistant gloves. ⚠️ Manual Handling: Use correct lifting techniques for mesh sheets. Team lift for large sheets. ⚠️ Trip Hazards: Keep work area clear of offcuts and tools. ⚠️ Cutting Hazards: Use appropriate guards on grinders. Be aware of kickback. ⚠️ Foot Protection: Always wear steel-capped boots when working with reo.Step-by-Step Guide
Step 1: Site Preparation and Vapour Barrier Installation
1️⃣ Subgrade Inspection: Ensure the subgrade is compacted, level, and free from debris, soft spots, or organic matter. Check that all services (plumbing, electrical conduits) are correctly installed and protected.
2️⃣ Vapour Barrier Laying: If specified, unroll the 200µm plastic film (vapour barrier) over the prepared subgrade. Overlap all joins by at least 200mm and tape them securely with construction tape to prevent moisture ingress. Ensure the barrier extends up the formwork edges.
Step 2: Laying the First Mesh Sheets
1️⃣ Initial Placement: Begin laying the first sheets of reinforcing mesh (e.g., SL82) from one corner of the slab, ensuring the mesh is correctly oriented as per the engineering drawings.
2️⃣ Edge Clearance: Maintain a minimum 25mm clearance between the edge of the mesh and the inside face of the formwork, or as specified by the engineer. This ensures adequate concrete cover.
3️⃣ Overlap Marking: For subsequent sheets, mark the required overlap using a chalk line. Australian Standard AS 3600 Concrete Structures typically requires a minimum overlap of 225mm for SL72 mesh, or as specified by the engineer (often 600mm or two mesh squares).
Step 3: Securing Mesh Overlaps
1️⃣ Overlap Alignment: Carefully align the overlapping mesh sheets, ensuring the correct overlap distance is maintained.
2️⃣ Tie Wire Application: Secure the overlapping mesh sheets together using tie wire. Tie every second or third intersection along the overlap, alternating the tie direction for maximum stability. Use a tie wire twister for efficient and secure ties.
3️⃣ Cutting Excess: Use reo cutters or bolt cutters to trim any mesh that extends beyond the required slab dimensions or interferes with penetrations.
Step 4: Installing Bar Chairs
1️⃣ Chair Spacing: Place bar chairs (e.g., 75mm high) evenly beneath the mesh. Standard spacing is typically 600mm to 800mm centres in both directions, or as specified by the engineer. More chairs may be required in high-load areas or where the mesh needs extra support.
2️⃣ Height Verification: Ensure the bar chairs lift the mesh to the correct height, providing the specified concrete cover (e.g., 50mm top and bottom cover for a 100mm slab with mesh in the middle). Use a spirit level to check the mesh is consistently level across the slab.
3️⃣ Securing Chairs: While not always necessary, some chairs can be tied to the mesh with tie wire, especially in areas prone to disturbance during concrete pour.
Step 5: Reinforcement for Penetrations and Edges
1️⃣ Penetration Trimming: Carefully trim mesh around all pipe penetrations, ensuring a minimum 50mm clearance from the pipe.
2️⃣ Trimmer Bars/Extra Reo: Install additional reinforcing bars (e.g., N12 rebar) around larger penetrations or openings as specified by the engineer. These are typically tied to the main mesh.
3️⃣ Edge Beams/Thickenings: If the slab includes edge beams or thickenings, ensure the specified rebar (e.g., N12, N16) is correctly placed and tied into the mesh, maintaining required concrete cover. Use appropriate chairs for these deeper sections.
Common Mistakes to Avoid
Pro Tips
💡 Pre-cut Tie Wire: Cut tie wire into 150-200mm lengths beforehand to speed up the tying process. 💡 Mesh Layout Plan: Before starting, draw a simple plan of how mesh sheets will be laid to minimise cuts and waste. 💡 Chair Selection: Use plastic bar chairs on vapour barriers to avoid puncturing the film. Steel chairs are acceptable on compacted earth. 💡 Walk Boards: Use timber walk boards across the mesh during the pour to prevent displacing the reo. 💡 Engineer's Inspection: Always ensure the engineer or certifier inspects the reo installation before the concrete pour.Recommended Tools
Knipex Rebar Cutter (Bolt Cutter): For effortless cutting of mesh and rebar up to 10mm. OX Pro Tie Wire Twister: Speeds up the tying process and reduces hand fatigue. Stanley FatMax Tape Measure (8m): Durable and accurate for all measuring tasks. Makita 18V Brushless Angle Grinder: For quick and precise cuts on rebar when needed (ensure correct safety guards).Frequently asked questions
- What is the Australian standard for concrete slab reinforcement?
- Residential concrete slab reinforcement is governed by AS 2870:2011 (Residential Slabs and Footings) and AS 3600:2018 (Concrete Structures). These standards define steel ductility classes, bar chair spacing, minimum concrete cover, and trench mesh requirements to prevent structural cracking, ground movement failure, and steel corrosion over the slab design life.
- How much overlap is required for reo mesh in Australia?
- Reinforcing mesh requires a minimum overlap of 225mm to 300mm, or at least two full transverse wire overlaps, in accordance with AS 2870 and AS 3600. Lapping ensures continuous tensile load transfer across the slab. Sheets must be secured tightly using tie wire at 500mm intervals to prevent displacement.
- How far apart should bar chairs be placed under reo mesh?
- Bar chairs must be placed roughly 800mm to 1000mm apart in a grid pattern, equating to approximately 1.5 to 2 chairs per square metre. Spacing must support the weight of steel fixers and wet concrete without sagging, maintaining minimum design cover above the moisture barrier.
- What size bar chairs do I need for a 100mm concrete slab?
- A standard 100mm residential slab requires 50/65mm combination plastic bar chairs to maintain 30mm to 40mm of top cover. Steel reinforcement should sit within the top third of the slab depth, elevated off the polythene vapour barrier to ensure effective crack control and structural load capacity.
- Can I use bricks or pavers instead of plastic bar chairs?
- No, clay bricks, timber, and standard pavers are strictly prohibited under Australian Standards for supporting reinforcement mesh. Porous materials draw moisture through the vapour barrier directly into the steel, causing premature corrosion, rust expansion, and concrete spalling. Only use certified plastic bar chairs or concrete spacer blocks.
- What type of mesh is used for residential driveways and house slabs?
- Residential driveways and house slabs typically require SL72 or SL82 welded wire reinforcing mesh made from 500 MPa grade steel. SL72 features 6.75mm wires at 200mm centres, while SL82 features 7.6mm wires, providing superior shrinkage crack resistance under standard passenger vehicle loads.
Written by Bricko, the Building & Construction specialist at VIC.Tools.