How to Lay a Concrete Foundation for a Deck

Learn how to lay a durable concrete foundation for your deck in Australia. This guide covers footing design, reinforcement, and pouring techniques for a stable, compliant deck structure.

Skill level
Intermediate
Time
1-2 days for set-out, digging and pouring, plus 7 days minimum curing before light loading and 28 days full cure
Trade
Building & Construction
Updated
28 November 2026

Tools you will need

  • Stanley FatMax Xtreme - Tape Measure (8m)
  • Bunnings - Marking Paint (Orange)
  • Makita DDA460 - Cordless Earth Auger (200mm)
  • Cyclone - Long Handle Round Mouth Shovel
  • Whirlaway - 80L Wheelbarrow
  • Crommelins - Concrete Mixer (120L)
  • Kincrome - Reo Tying Pliers
  • Sola Big X - Spirit Level (1200mm)
  • Bosch GRL 300 HV Professional - Rotary Laser Level

What is the primary purpose of a deck foundation?

Laying a concrete foundation for a deck is all about creating stable, correctly sized footings that transfer the deck load safely into the ground. For most Australian DIY decks, this means setting out the deck accurately, digging footing holes to engineer-approved depths, placing reinforcement where required, and pouring structural concrete with the post anchors aligned properly.

What skill level is required to lay a concrete deck foundation?

Intermediate — Estimated time: 1-2 days for set-out, digging and pouring, plus 7 days minimum curing before light loading and 28 days full cure

What essential tools are needed for laying a concrete deck foundation?

Tape measure, 8 m or longer, for accurate set-out
String line, line level and timber pegs for establishing deck grid and footing centres
Rotary laser level or builder’s level for checking heights and finished deck levels
Marking paint or lime for footing layout on the ground
Post hole shovel and crowbar for hand excavation of footing holes
Mechanical auger, 200 mm-450 mm diameter, for multiple footings or hard ground; usually better hired than bought for one-off jobs
Shovel and trenching spade for cleaning out footing bases
Wheelbarrow, 80 L-100 L capacity
Concrete mixer, 120 L-160 L, if mixing on site; hire is usually more economical unless you do regular masonry/concrete work
Buckets for water dosing and material batching
Reinforcement cutters/benders or angle grinder with metal cutting disc for reo preparation
Reo tying pliers and tie wire
Spirit level, 1200 mm recommended
Hammer drill/impact driver if fixing stirrups or brackets after curing
Concrete rake or square-mouth shovel for placing concrete
Screed board or straightedge for levelling footing tops where needed
Steel trowel or float for finishing exposed footing tops
Temporary bracing timber and clamps for holding stirrups or templates in position
PPE: safety boots, gloves, safety glasses, hearing protection, P2 dust mask and sunscreen

What materials are essential for concrete deck footings?

Structural concrete, minimum 25 MPa premix or site-mixed structural concrete at approximately 1:1.5:2.5 cement:sand:aggregate
Cement, 20 kg bags, if mixing on site
Washed sand and 10 mm-20 mm aggregate for site-mixed concrete
Reinforcement as specified by engineer, commonly N12 bars, trench mesh or ligatures for larger footings
Galvanised post stirrups or anchor bolts suitable for deck posts and outdoor exposure
Formwork materials if footings project above ground: 19 mm form ply or round footing form tubes
Compacted road base or crusher dust for levelling where required around working area
Plastic membrane or damp barrier only where detailed by design; generally not used in bored pier footings
String line pegs and profile boards
Tie wire for reinforcement
Timber stakes and bracing for formwork
Water for mixing and curing
Curing compound, plastic sheeting or damp hessian for curing concrete
Termite management components if required by local regulations or where deck is attached to the dwelling
Example footing sizes for small residential decks are commonly in the range of 300 mm-450 mm diameter and 450 mm-900 mm deep, but final dimensions must follow engineering, soil conditions and council requirements

Safety Requirements

Wear safety boots, gloves, eye protection and hearing protection when digging, cutting steel or mixing concrete
Use a P2 dust mask when handling cement and dry materials; wet concrete is caustic and can cause chemical burns
Confirm underground services before digging by checking site plans and using Before You Dig Australia information
Manual handling is critical: cement bags, reo and wet concrete are heavy; use correct lifting technique and wheelbarrows
Keep excavation edges stable and never leave open holes unprotected where children or pets can access them
If working above 2 m or near an existing raised structure, comply with scaffold and fall protection requirements
Structural work for decks and footings should comply with the NCC, AS 3600 for concrete, AS 2870 where soil and footing behaviour is relevant, and any applicable state or council building approval requirements
If the deck is attached to the house or carries significant loads, obtain engineering certification for footing size, reinforcement and tie-down details

Step-by-Step Guide

Step 1: Confirm approvals, soil conditions and deck design

Before digging anything, confirm whether your deck needs council approval or a complying development pathway in your state or territory. Footing size depends on deck size, post spacing, soil class, wind exposure and whether the deck is freestanding or attached to the house, so check the plans and have structural details verified by an engineer if required.

For DIY planning, gather the following:

Overall deck length and width
Post layout and spacing
Finished deck height above ground
Soil type and slope
House attachment details if applicable

As a rough guide only, low decks often use isolated concrete footings under each post. Larger decks, elevated decks and decks on reactive clay commonly need deeper or wider footings than beginners expect.

Step 2: Set out the deck accurately

Mark the deck perimeter with pegs and string line. Use the 3:4:5 method or diagonal measurements to square the layout.

Check:

Width and length are correct
Diagonals match
Deck is the right distance from boundaries and the house
Footing centres line up with bearer and joist layout

Mark each footing centre on the ground using spray paint. For beginner-friendly work, install profile boards outside the excavation area so your string lines stay in place while digging.

Step 3: Establish finished levels and footing depths

Use a laser level or builder’s level to set:

Finished deck height
Top of bearers
Top of posts or stirrups
Desired height of the concrete footing top relative to finished ground

Footing depth must be measured from natural ground level unless engineering says otherwise. In many deck jobs, the top of concrete is kept 50 mm-100 mm above surrounding ground so the post connection stays out of standing water and splashback.

Do not guess the depth. Depth and diameter must match the approved design. In reactive or filled soils, deeper founding into natural undisturbed ground is often required.

Step 4: Locate underground services and prepare the site

Before excavation, identify:

Stormwater pipes
Sewer lines
Water mains
Electrical conduits
Gas lines
NBN or communications services

Clear vegetation, remove topsoil and create safe access for digging and concrete delivery. If the site is sloping, cut a stable working platform and keep spoil piles away from hole edges.

Step 5: Excavate footing holes to the correct size

Dig each footing hole to the specified diameter and depth. Common auger sizes are 200 mm, 300 mm and 450 mm, but deck footings are often 300 mm-450 mm diameter for residential work depending on load.

Good excavation practice:

Dig to firm, undisturbed natural ground
Keep the sides reasonably straight
Clean loose soil from the base
Do not bell out the top and leave a narrow base unless designed that way
Recheck depth with a tape measure from string line or benchmark

If a hole over-excavates, do not backfill with loose dirt. Bring it back to level with concrete or compacted approved material as directed by the engineer or plan.

Step 6: Install formwork if required above ground

If the footing needs to project above ground level, install formwork or round footing tubes. This is especially useful where:

Ground is sloping
You want neat exposed pier tops
You need consistent anchor height

Brace the forms so they do not move during the pour. Check the top height of all forms with the laser so all post anchors finish in the same plane or to the required stepped levels.

Step 7: Place reinforcement and anchors as specified

For lightly loaded small footings, some designs may not require reinforcement, but many engineered footings do. Install reo exactly as detailed, with minimum cover maintained so steel is not touching soil or formwork.

Typical reinforcement principles:

Use bar chairs or small concrete spacers to maintain cover
Tie bars securely with tie wire
Keep reinforcement centrally positioned in the footing
Set anchor bolts or galvanised stirrups using a temporary timber template for alignment

If using cast-in stirrups, make sure:

They are centred on the footing
All stirrups line up with the post grid
The bracket height suits the post and bearer design
The metal finish is suitable for exterior use, ideally hot-dip galvanised

Step 8: Mix or order the right concrete

For deck footings, structural concrete is the right choice. Use:

Premixed concrete, minimum 25 MPa, for best consistency
Or a structural site mix at approximately 1 part cement : 1.5 parts sand : 2.5 parts aggregate

Do not use overly wet concrete just because it is easier to place. Excess water weakens the mix and increases shrinkage.

As a guide:

For one or two small footings, hand mixing may be manageable
For several footings, a 120 L-160 L mixer is far faster
For larger deck projects, ordering premix is usually more economical and gives better quality than bag mixing

Step 9: Pour the footings

Pour concrete into each hole continuously where possible. Use a shovel or rod to work the mix into the edges and remove air pockets, especially around reinforcement and anchors.

During the pour:

Keep checking anchor position and plumb
Do not allow reinforcement to shift
Fill to the required level
Lightly rod or tap the sides of formwork to consolidate the mix
Finish the top with a trowel or screed

If using post stirrups, recheck:

Centre position
Direction of the stirrup slot
Height above finished concrete
Alignment with the deck frame

Even a 10 mm-15 mm misalignment can cause frustrating post installation problems later.

Step 10: Recheck levels, line and set-out before initial set

Before the concrete hardens, check every footing against your string line and laser. Confirm:

Footing centres are correct
Top levels are consistent
Anchor bolts or stirrups are square to the deck frame
Spacing between footings matches the plan

Make small adjustments immediately. Once the concrete reaches initial set, leave it alone.

Step 11: Cure the concrete properly

Concrete gains strength through curing, not just drying. Protect the footings from rapid moisture loss, hot sun and heavy rain.

Best practice:

Cover with plastic sheeting or damp hessian after initial set
Keep the surface moist for at least 7 days where practical
Avoid heavy loading too early

A common DIY mistake is building on fresh footings the next day. For most deck work, wait at least 7 days before light structural loading, and allow 28 days for full strength development.

Step 12: Backfill and prepare for post installation

Once the concrete has cured sufficiently, backfill around the footing with excavated material or approved fill in layers, compacting gently as you go. Do not damage waterproofing details, termite management elements or stirrup alignment.

Then:

Trim the site level around the footings
Ensure water drains away from posts and footing tops
Install posts into stirrups or fix brackets as per the deck plan
Reconfirm post heights before cutting timber

If the deck is attached to the house, make sure final levels do not bridge damp-proof courses or create drainage issues against the wall.

Common Mistakes to Avoid

1.Guessing footing size instead of following engineering or approved plans. Undersized footings are one of the main causes of deck movement and settlement.
2.Digging into loose fill or soft ground rather than founding on firm natural material. Concrete is only as good as the soil under it.
3.Adding too much water to the concrete mix. This makes placement easier but significantly reduces strength.
4.Setting stirrups or anchor bolts out of line. Poor alignment causes major issues when installing posts and bearers.
5.Loading the footings too early. Concrete needs proper curing time to achieve its design strength.

Pro Tips

Use a temporary timber template across multiple footings to keep all post stirrups perfectly aligned and at the same height.
For more than 4-6 footings, hire a mechanical auger. It saves hours of labour and gives cleaner, more consistent holes than hand digging.
Order premixed concrete if the total volume is more than about 0.3 m3. It is usually cheaper and more reliable than buying bags and mixing all day.
Keep the top of the footing slightly above finished ground level, around 50 mm-100 mm, to reduce splashback, rot risk and corrosion at the post connection.
On sloping sites, step the footing heights carefully from a laser benchmark rather than trying to measure each one from uneven ground.

Recommended Tools

Rotary laser level — makes footing height and deck set-out far more accurate than relying on a string line alone
300 mm earth auger — ideal for common residential deck footing sizes and much faster than manual digging
120 L-160 L electric concrete mixer — suitable for small to medium DIY footing jobs if premix access is difficult
Reo tying pliers — quick, simple tool for securing reinforcement neatly and safely
Hot-dip galvanised adjustable post stirrups — worth searching for because they improve durability and help keep timber posts clear of wet concrete

Frequently asked questions

What is the correct depth for deck footings in Australia?
The correct depth for deck footings in Australia is typically determined by local council regulations, soil conditions, and the deck's structural engineer's specifications, but generally ranges from 450mm to 600mm below natural ground level to ensure stability and avoid soil movement. Footings must bear on undisturbed, natural ground, not fill, and extend below the frost line in colder regions.
What type of concrete mix should I use for deck footings?
For deck footings in Australia, use a structural concrete mix with a minimum 20 MPa compressive strength, such as a '20 N' or 'N20' mix, which is suitable for general footings and slabs. Ensure the slump is appropriate for placement, typically 80-100mm, and avoid adding excessive water as this significantly reduces strength and durability.
How do I ensure my deck footings are level and aligned correctly?
To ensure deck footings are level and aligned correctly, establish a precise grid using a string line, timber pegs, and a rotary laser level, like a 'Bosch GRL 300 HV Professional'. Mark footing centres accurately, then use a 1200mm spirit level, such as a 'Sola Big X', across formwork or screed rails to verify the final concrete surface is plumb and level before curing.
What reinforcement (reo) is required for deck footings in Australia?
Reinforcement for deck footings in Australia typically involves using N12 or N16 deformed reinforcing bar, formed into cages or 'starters' as per engineering drawings or AS 2870 requirements. These bars are crucial for resisting tensile stresses and preventing cracking, especially when embedded into concrete to anchor deck posts or piers.
What are common mistakes to avoid when pouring deck footings?
Common mistakes when pouring deck footings include guessing footing sizes instead of following engineering plans, founding on loose fill instead of firm natural ground, and adding too much water to the concrete mix, which compromises strength. Additionally, failing to properly compact the concrete can lead to voids and reduced structural integrity.
How long does concrete need to cure before building on deck footings?
Concrete footings require a minimum of 7 days of moist curing before light loading, such as framing, and achieve their full design strength after 28 days. Proper curing, by keeping the concrete damp, is essential to prevent premature drying, cracking, and to ensure optimal compressive strength and durability.
What is the Australian standard for deck footing depth?
The Australian standard for deck footing depth is primarily guided by AS 2870-2011 'Residential slabs and footings'. This standard mandates footings extend a minimum of 450mm below natural ground level, bearing on undisturbed soil, and deeper in reactive soil conditions or specific frost-prone areas, as determined by a geotechnical report or local council regulations.
What concrete strength is recommended for Australian deck footings?
For Australian deck footings, a minimum 20 MPa compressive strength concrete mix is recommended, aligning with AS 3600-2018 'Concrete structures'. This 'N20' or '20 N' mix ensures adequate structural integrity for transferring deck loads to the ground. Always ensure the concrete is placed with the correct slump, typically 80-100mm, to maintain strength and workability.
How do you ensure accurate alignment and level for deck footings?
To ensure accurate alignment and level for deck footings, establish a precise grid using string lines, timber pegs, and a rotary laser level, such as a Bosch GRL 300 HV Professional. Mark footing centres precisely, then use a 1200mm spirit level, like a Sola Big X, across formwork or screed rails to verify the final concrete surface is plumb and level before initial set.