How to Lay a Concrete Foundation for a Deck
Learn how to lay a durable concrete foundation for your deck in Australia. This guide covers footing design, reinforcement, and pouring techniques for a stable, compliant deck structure.
- Skill level
- Intermediate
- Time
- 1-2 days for set-out, digging and pouring, plus 7 days minimum curing before light loading and 28 days full cure
- Trade
- Building & Construction
- Updated
- 28 November 2026
Tools you will need
- Stanley FatMax Xtreme - Tape Measure (8m)
- Bunnings - Marking Paint (Orange)
- Makita DDA460 - Cordless Earth Auger (200mm)
- Cyclone - Long Handle Round Mouth Shovel
- Whirlaway - 80L Wheelbarrow
- Crommelins - Concrete Mixer (120L)
- Kincrome - Reo Tying Pliers
- Sola Big X - Spirit Level (1200mm)
- Bosch GRL 300 HV Professional - Rotary Laser Level
What is the primary purpose of a deck foundation?
Laying a concrete foundation for a deck is all about creating stable, correctly sized footings that transfer the deck load safely into the ground. For most Australian DIY decks, this means setting out the deck accurately, digging footing holes to engineer-approved depths, placing reinforcement where required, and pouring structural concrete with the post anchors aligned properly.
What skill level is required to lay a concrete deck foundation?
Intermediate — Estimated time: 1-2 days for set-out, digging and pouring, plus 7 days minimum curing before light loading and 28 days full cure
What essential tools are needed for laying a concrete deck foundation?
What materials are essential for concrete deck footings?
Safety Requirements
Step-by-Step Guide
Step 1: Confirm approvals, soil conditions and deck design
Before digging anything, confirm whether your deck needs council approval or a complying development pathway in your state or territory. Footing size depends on deck size, post spacing, soil class, wind exposure and whether the deck is freestanding or attached to the house, so check the plans and have structural details verified by an engineer if required.
For DIY planning, gather the following:
As a rough guide only, low decks often use isolated concrete footings under each post. Larger decks, elevated decks and decks on reactive clay commonly need deeper or wider footings than beginners expect.
Step 2: Set out the deck accurately
Mark the deck perimeter with pegs and string line. Use the 3:4:5 method or diagonal measurements to square the layout.
Check:
Mark each footing centre on the ground using spray paint. For beginner-friendly work, install profile boards outside the excavation area so your string lines stay in place while digging.
Step 3: Establish finished levels and footing depths
Use a laser level or builder’s level to set:
Footing depth must be measured from natural ground level unless engineering says otherwise. In many deck jobs, the top of concrete is kept 50 mm-100 mm above surrounding ground so the post connection stays out of standing water and splashback.
Do not guess the depth. Depth and diameter must match the approved design. In reactive or filled soils, deeper founding into natural undisturbed ground is often required.
Step 4: Locate underground services and prepare the site
Before excavation, identify:
Clear vegetation, remove topsoil and create safe access for digging and concrete delivery. If the site is sloping, cut a stable working platform and keep spoil piles away from hole edges.
Step 5: Excavate footing holes to the correct size
Dig each footing hole to the specified diameter and depth. Common auger sizes are 200 mm, 300 mm and 450 mm, but deck footings are often 300 mm-450 mm diameter for residential work depending on load.
Good excavation practice:
If a hole over-excavates, do not backfill with loose dirt. Bring it back to level with concrete or compacted approved material as directed by the engineer or plan.
Step 6: Install formwork if required above ground
If the footing needs to project above ground level, install formwork or round footing tubes. This is especially useful where:
Brace the forms so they do not move during the pour. Check the top height of all forms with the laser so all post anchors finish in the same plane or to the required stepped levels.
Step 7: Place reinforcement and anchors as specified
For lightly loaded small footings, some designs may not require reinforcement, but many engineered footings do. Install reo exactly as detailed, with minimum cover maintained so steel is not touching soil or formwork.
Typical reinforcement principles:
If using cast-in stirrups, make sure:
Step 8: Mix or order the right concrete
For deck footings, structural concrete is the right choice. Use:
Do not use overly wet concrete just because it is easier to place. Excess water weakens the mix and increases shrinkage.
As a guide:
Step 9: Pour the footings
Pour concrete into each hole continuously where possible. Use a shovel or rod to work the mix into the edges and remove air pockets, especially around reinforcement and anchors.
During the pour:
If using post stirrups, recheck:
Even a 10 mm-15 mm misalignment can cause frustrating post installation problems later.
Step 10: Recheck levels, line and set-out before initial set
Before the concrete hardens, check every footing against your string line and laser. Confirm:
Make small adjustments immediately. Once the concrete reaches initial set, leave it alone.
Step 11: Cure the concrete properly
Concrete gains strength through curing, not just drying. Protect the footings from rapid moisture loss, hot sun and heavy rain.
Best practice:
A common DIY mistake is building on fresh footings the next day. For most deck work, wait at least 7 days before light structural loading, and allow 28 days for full strength development.
Step 12: Backfill and prepare for post installation
Once the concrete has cured sufficiently, backfill around the footing with excavated material or approved fill in layers, compacting gently as you go. Do not damage waterproofing details, termite management elements or stirrup alignment.
Then:
If the deck is attached to the house, make sure final levels do not bridge damp-proof courses or create drainage issues against the wall.
Common Mistakes to Avoid
Pro Tips
Recommended Tools
Frequently asked questions
- What is the correct depth for deck footings in Australia?
- The correct depth for deck footings in Australia is typically determined by local council regulations, soil conditions, and the deck's structural engineer's specifications, but generally ranges from 450mm to 600mm below natural ground level to ensure stability and avoid soil movement. Footings must bear on undisturbed, natural ground, not fill, and extend below the frost line in colder regions.
- What type of concrete mix should I use for deck footings?
- For deck footings in Australia, use a structural concrete mix with a minimum 20 MPa compressive strength, such as a '20 N' or 'N20' mix, which is suitable for general footings and slabs. Ensure the slump is appropriate for placement, typically 80-100mm, and avoid adding excessive water as this significantly reduces strength and durability.
- How do I ensure my deck footings are level and aligned correctly?
- To ensure deck footings are level and aligned correctly, establish a precise grid using a string line, timber pegs, and a rotary laser level, like a 'Bosch GRL 300 HV Professional'. Mark footing centres accurately, then use a 1200mm spirit level, such as a 'Sola Big X', across formwork or screed rails to verify the final concrete surface is plumb and level before curing.
- What reinforcement (reo) is required for deck footings in Australia?
- Reinforcement for deck footings in Australia typically involves using N12 or N16 deformed reinforcing bar, formed into cages or 'starters' as per engineering drawings or AS 2870 requirements. These bars are crucial for resisting tensile stresses and preventing cracking, especially when embedded into concrete to anchor deck posts or piers.
- What are common mistakes to avoid when pouring deck footings?
- Common mistakes when pouring deck footings include guessing footing sizes instead of following engineering plans, founding on loose fill instead of firm natural ground, and adding too much water to the concrete mix, which compromises strength. Additionally, failing to properly compact the concrete can lead to voids and reduced structural integrity.
- How long does concrete need to cure before building on deck footings?
- Concrete footings require a minimum of 7 days of moist curing before light loading, such as framing, and achieve their full design strength after 28 days. Proper curing, by keeping the concrete damp, is essential to prevent premature drying, cracking, and to ensure optimal compressive strength and durability.
- What is the Australian standard for deck footing depth?
- The Australian standard for deck footing depth is primarily guided by AS 2870-2011 'Residential slabs and footings'. This standard mandates footings extend a minimum of 450mm below natural ground level, bearing on undisturbed soil, and deeper in reactive soil conditions or specific frost-prone areas, as determined by a geotechnical report or local council regulations.
- What concrete strength is recommended for Australian deck footings?
- For Australian deck footings, a minimum 20 MPa compressive strength concrete mix is recommended, aligning with AS 3600-2018 'Concrete structures'. This 'N20' or '20 N' mix ensures adequate structural integrity for transferring deck loads to the ground. Always ensure the concrete is placed with the correct slump, typically 80-100mm, to maintain strength and workability.
- How do you ensure accurate alignment and level for deck footings?
- To ensure accurate alignment and level for deck footings, establish a precise grid using string lines, timber pegs, and a rotary laser level, such as a Bosch GRL 300 HV Professional. Mark footing centres precisely, then use a 1200mm spirit level, like a Sola Big X, across formwork or screed rails to verify the final concrete surface is plumb and level before initial set.
Written by Bricko, the Building & Construction specialist at VIC.Tools.