How to lay bricks for a garden wall

Learn how to lay bricks for a garden wall to Australian standards. Get expert advice on concrete footings, mortar ratios, tool selection, and AS 3700 rules.

Quick answer

Laying a brick garden wall requires excavating a stable trench and pouring a reinforced concrete footing 150 to 200 mm deep. Bricks are bedded using a 1:1:6 cement, lime, and sand mortar mix with 10 mm joints. Australian Standard AS 3700 governs masonry construction, requiring engineered designs for walls exceeding 1000 mm.

Skill level
Intermediate
Time
1–2 days for a small wall up to around 5 m long and 600 mm high, plus curing time
Trade
Building & Construction
Updated
28 November 2026

Tools you will need

  • Marshalltown 19/11D - 10-Inch Philadelphia Pattern Brick Trowel
  • Stabila 196-2 LED - 1200 mm Box Beam Spirit Level
  • OX Pro Heavy Duty - 100 mm Brick Bolster Chisel
  • Plumb Club Hammer - 1.8 kg (4 lb) Fiberglass Handle
  • Ox Tools Pro - 100 m Braided Nylon Brick Line
  • Carborundum Double Sided - Half Round Brick Jointer
  • Tradetools Trade Master - 100 L Heavy Duty Steel Wheelbarrow

🧱 How to Lay Bricks for a Garden Wall

What is involved in laying bricks for a garden wall in Australia?

A brick garden wall is a solid, attractive way to define garden beds, edges, pathways, or front yard boundaries. For Australian homeowners, it’s a practical weekend project if the wall is low and non-structural, but it still needs proper set-out, footing preparation, and neat bricklaying technique to last.

This guide covers how to lay a simple straight garden wall using standard bricklaying methods, including footing preparation, mixing mortar, laying the first course, and keeping the wall straight, level, and plumb. For any retaining wall, boundary wall, or wall over 1000 mm high, check local council rules and obtain engineering advice in line with AS 3700 and relevant state requirements.

What skill level is required for a garden brick wall project?

Intermediate — Estimated time: 1–2 days for a small wall up to around 5 m long and 600 mm high, plus curing time

What specific tools are required for laying a garden brick wall?

Brick trowel, 10"–11" for spreading and buttering mortar
Spirit level, 1200 mm minimum, plus a small torpedo level
Brick line and line pins or line blocks
Tape measure, 5 m or 8 m
String line and builder’s square
Shovel and trenching spade
Wheelbarrow or mortar mixing tray
Hoe or mortar mixer for larger batches
Brick bolster and club hammer for cutting bricks
Brick jointer or iron for finishing joints
Gauging rod or marked story pole
Soft brush for cleaning brick faces
Rubber mallet
Bucket for water and cleanup
Compactor or hand tamper for base preparation
Angle grinder with masonry blade if cleaner cuts are needed
PPE: gloves, eye protection, hearing protection, dust mask, steel-cap boots

What materials are essential for building a garden brick wall?

Standard clay bricks or concrete bricks, quantity based on wall size
As a guide, allow about 50 bricks per m²
Mortar materials:
Cement
brickies sand
hydrated lime or pre-blended bricklaying mortar
Mortar mix for general bricklaying: typically 1:1:6 cement:lime:sand or suitable pre-mix mortar
Concrete for strip footing if required:
Use pre-mix concrete or site-mix 1:2:3 for general purpose
Crushed rock or road base for footing base, if needed
Reinforcement bars if specified by engineer or for higher-duty work
Damp-proof course (DPC) if required for appearance and moisture control
Clean potable water
Timber pegs and spray marker paint for set-out
Plastic sheeting or hessian for curing and weather protection

Safety Requirements

Wear gloves, safety glasses, steel-cap boots, and sun protection at all times.
Use hearing protection and a dust mask when cutting bricks or mixing dry materials.
Lift bricks correctly and avoid repetitive strain; bricks and mortar are heavy, so keep loads manageable.
Keep the work area tidy to prevent trips on tools, bricks, and mortar boards.
If using an angle grinder, follow manufacturer instructions and control silica dust.
For walls forming part of a retaining structure, boundary fence, or any wall needing structural performance, obtain engineering advice and ensure compliance with AS 3700.
Excavation near services must be checked before digging. Contact local service location providers before starting.
Scaffolding is generally not required for low garden walls, but any elevated work platform must be stable and compliant.

Step-by-Step Guide

Step 1: Plan the wall and check compliance

1️⃣ Confirm the wall type

Decide whether the wall is purely decorative, a garden edging wall, or a small freestanding divider. This guide is suitable for a low, non-retaining garden wall.

If the wall is retaining soil, supporting loads, near a boundary, or over 1000 mm high, it may require engineering certification and council approval. Structural masonry should comply with AS 3700, and footing design should align with AS 3600 where concrete structural elements are involved.

2️⃣ Choose the wall size

For a beginner-friendly project, keep the wall to around 400–600 mm high and in a straight run. A single-skin wall is common for garden walls, but for improved stability, piers or returns at intervals may be needed on longer walls.

3️⃣ Estimate materials

Measure the wall length and height in metres, then calculate brick quantities. Standard Australian bricks vary, but many are around 230 mm x 110 mm x 76 mm plus mortar joints of about 10 mm.

💡 For cleaner appearance and easier setting out, work to full brick modules wherever possible so you reduce cutting.

Step 2: Set out the wall location

1️⃣ Mark the wall line

Use pegs and string line to mark the exact wall position. Measure carefully from fences, paths, or garden beds to keep the wall square and aligned.

2️⃣ Check for square and straightness

Use a builder’s square or 3-4-5 triangle method to confirm right angles if the wall turns a corner.

3️⃣ Mark footing width

For a typical low garden wall, the footing should be wider than the brick wall. A common starting point for a simple wall is footing width around 300–400 mm for a single-skin wall, but site conditions matter.

💡 Spend extra time on set-out. If the line is wrong at the start, the whole wall will look wrong no matter how neatly the bricks are laid.

Step 3: Excavate and prepare the footing

1️⃣ Dig the trench

Excavate a straight trench along the wall line. For a small garden wall, a typical trench might be around 200 mm deep by 300–400 mm wide, depending on ground conditions.

Soft, reactive, or filled soils may require a deeper and stronger footing. In many Australian areas with clay movement, footing depth is important for durability.

2️⃣ Compact the base

Remove loose soil and compact the trench base. Add a thin layer of compacted crushed rock if needed to create a firm working platform.

3️⃣ Form and pour the footing

For low non-structural walls, pour a level concrete strip footing. A typical footing thickness may be around 100–150 mm depending on the wall and soil.

Use a general-purpose concrete mix of 1:2:3 if mixing on site, or use bagged concrete for convenience. Screed the top level and allow it to cure before laying bricks.

💡 A level footing makes bricklaying dramatically easier. If the footing is uneven, you’ll waste time trying to correct it with mortar.

Step 4: Dry-set and establish your gauge

1️⃣ Dry-lay the first course

Place a row of bricks without mortar along the footing to check spacing, joint widths, and where cuts will fall.

2️⃣ Set joint widths

A standard horizontal and vertical mortar joint is about 10 mm. Adjust the set-out so cuts are balanced and not awkwardly small.

3️⃣ Create a gauge rod

Mark the height of each brick course on a timber rod, allowing for brick height plus mortar joint. This keeps every course consistent.

💡 Beginners often skip dry-laying, but it helps avoid ending up with a tiny cut brick at the end of the wall.

Step 5: Mix the mortar correctly

1️⃣ Choose the mix

For bricklaying mortar, use a suitable pre-blended mortar or a traditional mix such as 1:1:6 cement:lime:sand for workable brick mortar. For structural applications, mortar specification should match the design requirements.

2️⃣ Mix to the right consistency

The mortar should be workable and hold its shape on the trowel without being too wet. It should spread easily but not slump off the brick.

3️⃣ Only mix what you can use

In warm Australian weather, mortar can dry out quickly. Mix manageable batches and remix lightly if needed, but do not add excessive water once it begins to set.

💡 Mortar that is too wet makes bricks slide out of line; mortar that is too dry won’t bond properly or tool cleanly.

Step 6: Lay the first course

1️⃣ Start at the ends

Lay the first bricks at each end of the wall first, checking each one for level and alignment.

2️⃣ Spread the bed mortar

Use the trowel to spread a bed of mortar about 10 mm thick on the footing. Furrow the mortar slightly with the trowel edge to help bedding.

3️⃣ Butter the end joints

Apply mortar to the end of the brick before placing it against the previous one.

4️⃣ Tap into place

Set the brick gently into the mortar and tap it with the trowel handle or rubber mallet until it is level and aligned to the string line.

5️⃣ Check constantly

Use the spirit level to check level along the top and plumb on the face. The first course is the most important course in the whole wall.

💡 If the first course is straight, level, and to gauge, the rest of the wall becomes much easier.

Step 7: Build the leads and run the string line

1️⃣ Build the corners or end leads first

Raise the ends of the wall by several courses, checking plumb, level, and gauge as you go. These act as guides for the rest of the wall.

2️⃣ Use a string line for each course

Stretch the line tightly between the leads for every course. The line should just touch the face edge of the brick without being pushed out.

3️⃣ Lay intermediate bricks to the line

Fill in between the leads, placing each brick to the line and maintaining consistent 10 mm joints.

For a simple garden wall, stretcher bond is the easiest and most common pattern. It is beginner-friendly and gives a clean, classic appearance.

Step 8: Maintain bond, level, and plumb

1️⃣ Follow the bond pattern

In stretcher bond, each brick overlaps the brick below by roughly half a brick. This improves wall integrity and appearance.

2️⃣ Check every course

Use the level horizontally and vertically every few bricks. Also sight along the wall face to catch bowing early.

3️⃣ Keep joints uniform

Consistent joint thickness is key to a professional look. Scrape off excess mortar as you work so it doesn’t stain the face.

💡 Don’t rely only on your eye. Use the level and line constantly—professional bricklayers check more often than most DIYers realise.

Step 9: Cut bricks where required

1️⃣ Mark accurately

Use a pencil or chalk to mark cut lines clearly.

2️⃣ Cut safely

Use a brick bolster and hammer for basic cuts, or an angle grinder with masonry blade for cleaner, more accurate cuts.

3️⃣ Place cut bricks neatly

Try to keep cut bricks away from the most visible sections if possible, especially on the ends or top course.

💡 Buying a few extra bricks gives you room for breakages and helps you select the best-looking bricks for the most visible areas.

Step 10: Tool the joints and clean the wall

1️⃣ Let mortar firm up slightly

Wait until the mortar is thumbprint hard before jointing. If you tool too early, it will smear; too late and it won’t compact properly.

2️⃣ Finish the joints

Use a brick jointer to compress and shape the mortar joints. A tooled joint helps shed water and improves durability.

3️⃣ Brush the face clean

Use a soft brush to remove crumbs and loose mortar. Avoid excessive wet cleaning while the mortar is fresh, as this can stain the brickwork.

For outdoor walls exposed to weather, neatly compacted joints are important for long-term performance.

Step 11: Cure and protect the wall

1️⃣ Protect from sun and rain

Fresh mortar should not dry too quickly or be washed out by rain. Cover the wall with plastic sheeting if poor weather is expected.

2️⃣ Allow proper curing

Leave the wall undisturbed while the mortar gains strength. Avoid loading, leaning on, or attaching anything to it too early.

3️⃣ Inspect the finished wall

Check the wall for plumb, straightness, joint consistency, and any mortar smears. Minor cleaning is easier before the mortar fully hardens.

💡 In hot or windy Australian conditions, light curing protection can make a big difference to mortar strength and finish quality.

Common Mistakes to Avoid

1.Laying bricks on an uneven or poorly prepared footing, which causes the wall to run out of level quickly.
2.Making the mortar too wet, leading to slipping bricks, messy joints, and weak bedding.
3.Failing to use a string line for every course, resulting in a wavy wall.
4.Inconsistent mortar joints, especially vertical joints, which makes the wall look amateur.
5.Building a wall too high or too long without piers, returns, or engineering advice.
6.Not checking local council and boundary requirements before building near property lines.
7.Cleaning brick faces with too much water while mortar is fresh, causing staining and smear marks.

Pro Tips

💡 Use stretcher bond for your first garden wall—it’s the simplest pattern to keep straight and is ideal for DIY work.
💡 Buy at least 5–10% extra bricks to allow for cuts, chips, and future repairs.
💡 Pre-blended mortar can be worth the extra cost for DIYers because it gives more consistent results and saves time.
💡 On long straight walls, add a return, pier, or change in direction for improved stability and appearance.
💡 Hire a mixer for larger jobs rather than buying one if you’ll only use it once or twice; for a single weekend wall, a mixing tray is often more economical.
💡 Keep your trowel, level, and brick faces clean as you go—small clean-ups during the job are much easier than heavy cleaning later.

Recommended Tools

Ox Pro Brick Trowel 11" — reliable all-round trowel for spreading and buttering mortar
Stabila 1200 mm Spirit Level — accurate level for keeping courses straight and plumb
Estwing Brick Hammer or brick bolster set — useful for trimming and splitting bricks
Makita Angle Grinder with masonry blade — good for cleaner cuts on caps and end bricks
Cement Australia Mortar Mix or equivalent pre-blended bricklaying mortar — convenient option for DIY consistency

Frequently asked questions

What is the best mortar mix ratio for an Australian garden wall?
The standard mortar mix for an Australian garden wall is a 1:1:6 ratio, comprising one part General Purpose (GP) cement, one part hydrated lime, and six parts clean brickies sand. This composition yields an M3 durability class under AS 3700, balancing workable adhesion with adequate weather and moisture resistance for external garden brickwork.
How deep should a concrete footing be for a brick garden wall?
A low, non-structural brick garden wall up to 600 mm high typically requires a concrete strip footing at least 150 mm to 200 mm deep and twice the wall's width. Footings must rest on stable, undisturbed soil and incorporate SL72 reinforcing mesh to resist ground movement, adhering to AS 2870 guidelines.
Do I need council approval to build a brick garden wall in Australia?
Council approval is generally not required for freestanding, non-structural brick garden walls under 1000 mm in height in most Australian jurisdictions. However, any masonry wall acting as a retaining structure, exceeding 1 metre, or positioned along front boundaries requires council development approval and certified engineering documentation under AS 3700.
What are the standard dimensions of a brick in Australia?
The standard Australian building brick measures 230 mm long by 110 mm wide by 76 mm high. Factoring in a standard 10 mm mortar joint on all sides, standard modular planning uses nominal unit dimensions of 240 mm by 110 mm by 86 mm, which allows roughly 48.5 standard bricks per square metre.
How do you keep brick courses level and straight across a long wall?
Set up external brick corners (leads) first using a spirit level and story pole to establish gauge, then stretch a nylon builder's line between them on line blocks. Lay intervening bricks so their top outer edges align flush with the line, leaving a 1 mm clearance to prevent line displacement.
What PPE is required when cutting bricks and mixing mortar in Australia?
SafeWork Australia mandates wearing eye protection complying with AS/NZS 1337.1, alkali-resistant PVC gloves to prevent chemical burns from wet cement, and a P2 respirator to prevent silica dust inhalation during brick cutting. Steel-capped boots rated to AS/NZS 2210.3 and Class 4 or 5 hearing protection are also mandatory.

Written by Bricko, the Building & Construction specialist at VIC.Tools.