How to lay bricks for a garden wall
Learn how to lay bricks for a garden wall to Australian standards. Get expert advice on concrete footings, mortar ratios, tool selection, and AS 3700 rules.
Quick answer
Laying a brick garden wall requires excavating a stable trench and pouring a reinforced concrete footing 150 to 200 mm deep. Bricks are bedded using a 1:1:6 cement, lime, and sand mortar mix with 10 mm joints. Australian Standard AS 3700 governs masonry construction, requiring engineered designs for walls exceeding 1000 mm.
- Skill level
- Intermediate
- Time
- 1–2 days for a small wall up to around 5 m long and 600 mm high, plus curing time
- Trade
- Building & Construction
- Updated
- 28 November 2026
Tools you will need
- Marshalltown 19/11D - 10-Inch Philadelphia Pattern Brick Trowel
- Stabila 196-2 LED - 1200 mm Box Beam Spirit Level
- OX Pro Heavy Duty - 100 mm Brick Bolster Chisel
- Plumb Club Hammer - 1.8 kg (4 lb) Fiberglass Handle
- Ox Tools Pro - 100 m Braided Nylon Brick Line
- Carborundum Double Sided - Half Round Brick Jointer
- Tradetools Trade Master - 100 L Heavy Duty Steel Wheelbarrow
🧱 How to Lay Bricks for a Garden Wall
What is involved in laying bricks for a garden wall in Australia?
A brick garden wall is a solid, attractive way to define garden beds, edges, pathways, or front yard boundaries. For Australian homeowners, it’s a practical weekend project if the wall is low and non-structural, but it still needs proper set-out, footing preparation, and neat bricklaying technique to last.
This guide covers how to lay a simple straight garden wall using standard bricklaying methods, including footing preparation, mixing mortar, laying the first course, and keeping the wall straight, level, and plumb. For any retaining wall, boundary wall, or wall over 1000 mm high, check local council rules and obtain engineering advice in line with AS 3700 and relevant state requirements.
What skill level is required for a garden brick wall project?
Intermediate — Estimated time: 1–2 days for a small wall up to around 5 m long and 600 mm high, plus curing time
What specific tools are required for laying a garden brick wall?
What materials are essential for building a garden brick wall?
Safety Requirements
Step-by-Step Guide
Step 1: Plan the wall and check compliance
1️⃣ Confirm the wall type
Decide whether the wall is purely decorative, a garden edging wall, or a small freestanding divider. This guide is suitable for a low, non-retaining garden wall.
If the wall is retaining soil, supporting loads, near a boundary, or over 1000 mm high, it may require engineering certification and council approval. Structural masonry should comply with AS 3700, and footing design should align with AS 3600 where concrete structural elements are involved.
2️⃣ Choose the wall size
For a beginner-friendly project, keep the wall to around 400–600 mm high and in a straight run. A single-skin wall is common for garden walls, but for improved stability, piers or returns at intervals may be needed on longer walls.
3️⃣ Estimate materials
Measure the wall length and height in metres, then calculate brick quantities. Standard Australian bricks vary, but many are around 230 mm x 110 mm x 76 mm plus mortar joints of about 10 mm.
💡 For cleaner appearance and easier setting out, work to full brick modules wherever possible so you reduce cutting.
Step 2: Set out the wall location
1️⃣ Mark the wall line
Use pegs and string line to mark the exact wall position. Measure carefully from fences, paths, or garden beds to keep the wall square and aligned.
2️⃣ Check for square and straightness
Use a builder’s square or 3-4-5 triangle method to confirm right angles if the wall turns a corner.
3️⃣ Mark footing width
For a typical low garden wall, the footing should be wider than the brick wall. A common starting point for a simple wall is footing width around 300–400 mm for a single-skin wall, but site conditions matter.
💡 Spend extra time on set-out. If the line is wrong at the start, the whole wall will look wrong no matter how neatly the bricks are laid.
Step 3: Excavate and prepare the footing
1️⃣ Dig the trench
Excavate a straight trench along the wall line. For a small garden wall, a typical trench might be around 200 mm deep by 300–400 mm wide, depending on ground conditions.
Soft, reactive, or filled soils may require a deeper and stronger footing. In many Australian areas with clay movement, footing depth is important for durability.
2️⃣ Compact the base
Remove loose soil and compact the trench base. Add a thin layer of compacted crushed rock if needed to create a firm working platform.
3️⃣ Form and pour the footing
For low non-structural walls, pour a level concrete strip footing. A typical footing thickness may be around 100–150 mm depending on the wall and soil.
Use a general-purpose concrete mix of 1:2:3 if mixing on site, or use bagged concrete for convenience. Screed the top level and allow it to cure before laying bricks.
💡 A level footing makes bricklaying dramatically easier. If the footing is uneven, you’ll waste time trying to correct it with mortar.
Step 4: Dry-set and establish your gauge
1️⃣ Dry-lay the first course
Place a row of bricks without mortar along the footing to check spacing, joint widths, and where cuts will fall.
2️⃣ Set joint widths
A standard horizontal and vertical mortar joint is about 10 mm. Adjust the set-out so cuts are balanced and not awkwardly small.
3️⃣ Create a gauge rod
Mark the height of each brick course on a timber rod, allowing for brick height plus mortar joint. This keeps every course consistent.
💡 Beginners often skip dry-laying, but it helps avoid ending up with a tiny cut brick at the end of the wall.
Step 5: Mix the mortar correctly
1️⃣ Choose the mix
For bricklaying mortar, use a suitable pre-blended mortar or a traditional mix such as 1:1:6 cement:lime:sand for workable brick mortar. For structural applications, mortar specification should match the design requirements.
2️⃣ Mix to the right consistency
The mortar should be workable and hold its shape on the trowel without being too wet. It should spread easily but not slump off the brick.
3️⃣ Only mix what you can use
In warm Australian weather, mortar can dry out quickly. Mix manageable batches and remix lightly if needed, but do not add excessive water once it begins to set.
💡 Mortar that is too wet makes bricks slide out of line; mortar that is too dry won’t bond properly or tool cleanly.
Step 6: Lay the first course
1️⃣ Start at the ends
Lay the first bricks at each end of the wall first, checking each one for level and alignment.
2️⃣ Spread the bed mortar
Use the trowel to spread a bed of mortar about 10 mm thick on the footing. Furrow the mortar slightly with the trowel edge to help bedding.
3️⃣ Butter the end joints
Apply mortar to the end of the brick before placing it against the previous one.
4️⃣ Tap into place
Set the brick gently into the mortar and tap it with the trowel handle or rubber mallet until it is level and aligned to the string line.
5️⃣ Check constantly
Use the spirit level to check level along the top and plumb on the face. The first course is the most important course in the whole wall.
💡 If the first course is straight, level, and to gauge, the rest of the wall becomes much easier.
Step 7: Build the leads and run the string line
1️⃣ Build the corners or end leads first
Raise the ends of the wall by several courses, checking plumb, level, and gauge as you go. These act as guides for the rest of the wall.
2️⃣ Use a string line for each course
Stretch the line tightly between the leads for every course. The line should just touch the face edge of the brick without being pushed out.
3️⃣ Lay intermediate bricks to the line
Fill in between the leads, placing each brick to the line and maintaining consistent 10 mm joints.
For a simple garden wall, stretcher bond is the easiest and most common pattern. It is beginner-friendly and gives a clean, classic appearance.
Step 8: Maintain bond, level, and plumb
1️⃣ Follow the bond pattern
In stretcher bond, each brick overlaps the brick below by roughly half a brick. This improves wall integrity and appearance.
2️⃣ Check every course
Use the level horizontally and vertically every few bricks. Also sight along the wall face to catch bowing early.
3️⃣ Keep joints uniform
Consistent joint thickness is key to a professional look. Scrape off excess mortar as you work so it doesn’t stain the face.
💡 Don’t rely only on your eye. Use the level and line constantly—professional bricklayers check more often than most DIYers realise.
Step 9: Cut bricks where required
1️⃣ Mark accurately
Use a pencil or chalk to mark cut lines clearly.
2️⃣ Cut safely
Use a brick bolster and hammer for basic cuts, or an angle grinder with masonry blade for cleaner, more accurate cuts.
3️⃣ Place cut bricks neatly
Try to keep cut bricks away from the most visible sections if possible, especially on the ends or top course.
💡 Buying a few extra bricks gives you room for breakages and helps you select the best-looking bricks for the most visible areas.
Step 10: Tool the joints and clean the wall
1️⃣ Let mortar firm up slightly
Wait until the mortar is thumbprint hard before jointing. If you tool too early, it will smear; too late and it won’t compact properly.
2️⃣ Finish the joints
Use a brick jointer to compress and shape the mortar joints. A tooled joint helps shed water and improves durability.
3️⃣ Brush the face clean
Use a soft brush to remove crumbs and loose mortar. Avoid excessive wet cleaning while the mortar is fresh, as this can stain the brickwork.
For outdoor walls exposed to weather, neatly compacted joints are important for long-term performance.
Step 11: Cure and protect the wall
1️⃣ Protect from sun and rain
Fresh mortar should not dry too quickly or be washed out by rain. Cover the wall with plastic sheeting if poor weather is expected.
2️⃣ Allow proper curing
Leave the wall undisturbed while the mortar gains strength. Avoid loading, leaning on, or attaching anything to it too early.
3️⃣ Inspect the finished wall
Check the wall for plumb, straightness, joint consistency, and any mortar smears. Minor cleaning is easier before the mortar fully hardens.
💡 In hot or windy Australian conditions, light curing protection can make a big difference to mortar strength and finish quality.
Common Mistakes to Avoid
Pro Tips
Recommended Tools
Frequently asked questions
- What is the best mortar mix ratio for an Australian garden wall?
- The standard mortar mix for an Australian garden wall is a 1:1:6 ratio, comprising one part General Purpose (GP) cement, one part hydrated lime, and six parts clean brickies sand. This composition yields an M3 durability class under AS 3700, balancing workable adhesion with adequate weather and moisture resistance for external garden brickwork.
- How deep should a concrete footing be for a brick garden wall?
- A low, non-structural brick garden wall up to 600 mm high typically requires a concrete strip footing at least 150 mm to 200 mm deep and twice the wall's width. Footings must rest on stable, undisturbed soil and incorporate SL72 reinforcing mesh to resist ground movement, adhering to AS 2870 guidelines.
- Do I need council approval to build a brick garden wall in Australia?
- Council approval is generally not required for freestanding, non-structural brick garden walls under 1000 mm in height in most Australian jurisdictions. However, any masonry wall acting as a retaining structure, exceeding 1 metre, or positioned along front boundaries requires council development approval and certified engineering documentation under AS 3700.
- What are the standard dimensions of a brick in Australia?
- The standard Australian building brick measures 230 mm long by 110 mm wide by 76 mm high. Factoring in a standard 10 mm mortar joint on all sides, standard modular planning uses nominal unit dimensions of 240 mm by 110 mm by 86 mm, which allows roughly 48.5 standard bricks per square metre.
- How do you keep brick courses level and straight across a long wall?
- Set up external brick corners (leads) first using a spirit level and story pole to establish gauge, then stretch a nylon builder's line between them on line blocks. Lay intervening bricks so their top outer edges align flush with the line, leaving a 1 mm clearance to prevent line displacement.
- What PPE is required when cutting bricks and mixing mortar in Australia?
- SafeWork Australia mandates wearing eye protection complying with AS/NZS 1337.1, alkali-resistant PVC gloves to prevent chemical burns from wet cement, and a P2 respirator to prevent silica dust inhalation during brick cutting. Steel-capped boots rated to AS/NZS 2210.3 and Class 4 or 5 hearing protection are also mandatory.
Written by Bricko, the Building & Construction specialist at VIC.Tools.