Skip to main content

How to mortar and lay concrete blocks for a garden wall

A mortared concrete block garden wall is a practical way to create raised garden edges, define landscaping zones, or build a small non-structural boundary feature. For Australian DIY renovators, the key to a straight, durable wall is proper footing preparation, correct mortar consistency, and carefu

Skill level
Intermediate
Time
1–2 days for a small wall up to 5 m long and around 600 mm high, plus footing curing time
Trade
Building & Construction
Updated
29 November 2026

Tools you will need

  • Bricklayer’s trowel, 250 mm
  • Mortar board or spot board
  • Wheelbarrow or mortar mixing tray
  • Shovel for mixing and loading mortar
  • String line and line pins
  • Spirit level, ideally 1200 mm
  • Tape measure
  • Rubber mallet
  • Bolster chisel and club hammer
  • Masonry saw or angle grinder with diamond masonry blade

🧱 How to Mortar and Lay Concrete Blocks for a Garden Wall

What is involved in mortaring and laying concrete blocks for a garden wall?

A mortared concrete block garden wall is a practical way to create raised garden edges, define landscaping zones, or build a small non-structural boundary feature. For Australian DIY renovators, the key to a straight, durable wall is proper footing preparation, correct mortar consistency, and careful block alignment from the first course onward.

This guide covers a simple low garden wall using concrete blocks and mortar. If the wall is intended to retain soil, support surcharge loads, or exceeds local exempt height limits, engineering and council approval may be required, and structural design should comply with AS 3700 and relevant state and council requirements.

What skill level is required to mortar and lay concrete blocks for a garden wall?

Intermediate — Estimated time: 1–2 days for a small wall up to 5 m long and around 600 mm high, plus footing curing time

What tools are required to mortar and lay concrete blocks for a garden wall?

Bricklayer’s trowel, 250 mm–280 mm
Mortar board or spot board
Wheelbarrow or mortar mixing tray
Shovel for mixing and loading mortar
String line and line pins
Spirit level, ideally 1200 mm
Tape measure
Rubber mallet
Bolster chisel and club hammer
Masonry saw or angle grinder with diamond masonry blade
Jointing tool or brick jointer
Stiff brush for cleaning joints
Plate compactor for base prep if required, hired for larger jobs
Concrete mixer for larger walls; hire is usually more economical than purchase for one-off weekend work

What materials are required for a concrete block garden wall?

Concrete blocks, commonly 390 mm x 190 mm x 190 mm, quantity to suit wall length and height
Mortar mix materials:
Cement
Brickies sand
Lime or plasticiser if preferred for workability
General mortar water supply
Concrete for strip footing, using 1:2:3 general purpose mix where site-mixed
Reinforcement if specified by engineer or manufacturer
Crushed rock or road base for footing subgrade preparation
DPC or flashing material if required for moisture control
String line
Stakes or profiles
Caps or capping blocks if finishing top course
Clean fill or drainage gravel if used behind a lightly retaining landscape wall
Agricultural drain and geotextile fabric if retaining soil and drainage is required
Bonding agent only if specified for repairs or connecting to existing masonry

Safety Requirements

Wear PPE: safety glasses, gloves, hearing protection, long sleeves, long pants, and steel-capped boots
Use a P2 dust mask when cutting blocks or handling dry cement products
Follow safe manual handling practices; concrete blocks are heavy and repetitive lifting can cause strain
Keep work area level and tidy to reduce trip hazards
Use scaffolding or a stable work platform for higher work; do not stand on stacked blocks
Cement products are caustic and can burn skin; wash off wet mortar immediately
For retaining walls, check local council rules, drainage requirements, and whether engineering certification is required
Waterproofing behind associated planters or enclosed garden structures must comply with AS 3740 where applicable
Masonry and footings for structural applications should align with AS 3700 and AS 3600

Step-by-Step Guide

Step 1: Plan the wall and confirm whether it is structural

1️⃣ Check wall purpose and height

Work out whether the wall is decorative, a garden edge, or actually retaining soil. A simple freestanding garden wall or low edge wall is suitable for DIY, but if it retains soil, supports fences, sits near a driveway, or is over about 600 mm–1000 mm high depending on your local rules, you may need engineering and council approval.

Mark out the wall length, thickness, and finished height. For a standard block wall using 190 mm thick blocks, make sure the footing width is adequate and the wall location allows for drainage and access.

💡 For a beginner project, keep the wall low and straight rather than curved. Straight walls are easier to line, cut, and level.

Step 2: Set out the wall accurately

2️⃣ Mark the footprint and levels

Drive in stakes at both ends of the wall and run a string line to mark the front face. Measure the wall thickness and mark the footing trench width.

Check the ground levels with a spirit level or string line. If the site slopes, decide whether the footing will be stepped or level. For neat DIY work, a level footing with stepped block courses is often easiest on mild slopes.

Double-check all measurements before digging. The first course dictates everything above it, so accuracy here saves a lot of grief later.

Step 3: Excavate and prepare the footing base

3️⃣ Dig the trench and compact the base

Excavate a strip footing trench to suitable depth for firm natural ground. For a small garden wall, a common starting point is around 100 mm–150 mm compacted base and 150 mm–200 mm concrete footing thickness, but footing size depends on wall height, soil type, and whether it is retaining.

A practical small wall footing might be around 300 mm–450 mm wide for a single skin block wall, subject to site conditions. Remove all loose material, organic matter, and soft spots.

Compact the base and add crushed rock if needed to create a stable founding surface.

⚠️ If the soil is reactive, sandy, or poorly compacted, or the wall retains any significant load, get engineering advice before proceeding.

Step 4: Pour the concrete footing

4️⃣ Create a flat, level foundation

Place and screed the concrete footing so the top is level and straight. Site-mixed concrete can use a 1:2:3 general purpose ratio for small non-structural work. For engineered structural work, mix design and reinforcement must suit the engineer’s details, and AS 3600 applies.

Use your spirit level and a straightedge to finish the top of the footing. Let the concrete firm up enough before laying blocks; next-day laying is common for small DIY jobs.

A level footing makes blocklaying much easier and reduces the need for thick mortar beds.

💡 Don’t rush this part. A poor footing usually causes a wavy wall, uneven joints, and extra cutting later.

Step 5: Mix the mortar correctly

5️⃣ Make a workable, consistent mortar

Mix mortar to a smooth, workable consistency that holds on the trowel without being sloppy. A common site mortar for blocklaying is around 1 cement : 1 lime : 6 sand or a cement and sand mix with plasticiser, depending on preference and product instructions.

Add water gradually. Mortar should be firm enough to support the block but soft enough to spread easily and form full joints.

Only mix what you can use in a workable period, especially in hot Australian weather. Re-tempering with too much extra water weakens the mortar and can affect bond.

💡 In summer, keep sand damp and work in smaller batches. Fast drying can ruin joint strength and alignment time.

Step 6: Lay the first course

6️⃣ Start from the corner or end and set the line

Spread a mortar bed around 10 mm thick along the footing for the first block position. Butter the vertical end joint, then place the first block carefully onto the bed.

Tap the block into place with the trowel handle or a rubber mallet until it is level both ways and aligned to the string line. Lay the next block with a similar 10 mm bed joint and vertical joint.

Continue along the first course, constantly checking:

level
alignment to string
joint thickness
straightness over multiple blocks

This first course is the most important step in the entire job. Take your time and correct any variation immediately.

Step 7: Build up the wall in courses

7️⃣ Stagger joints and keep plumb

Lay subsequent courses with staggered vertical joints, typically using a half-block bond pattern for strength and appearance. This is effectively a stretcher-style arrangement for blockwork.

Spread mortar evenly on top of the previous course and butter each end before placing the next block. Keep bed and perp joints consistent at around 10 mm.

Check every block for:

plumb
level
line
joint fullness

Use cut blocks where needed at ends or returns. Make clean cuts with a masonry saw or angle grinder fitted with a diamond blade.

If your wall ties into another structure or includes piers, reinforcement or connection details may be needed and should be designed appropriately.

Step 8: Tool the joints and clean as you go

8️⃣ Finish the mortar neatly

Allow the mortar to firm up slightly, then tool the joints with a jointer for a compact, weather-resistant finish. A tooled joint helps shed water better than rough, open joints.

Brush off crumbs and smears before they harden fully. Don’t leave heavy mortar stains on block faces, especially on architectural or split-face blocks.

A neat joint finish makes a basic DIY wall look much more professional.

Step 9: Add drainage if the wall retains soil

9️⃣ Prevent water build-up behind the wall

If the wall retains even a small amount of soil, install drainage behind it. Use free-draining gravel, geotextile fabric, and where needed an agricultural drain discharging to a lawful outlet.

Hydrostatic pressure is one of the main reasons retaining walls fail. Even low landscape walls can move, crack, or lean if water builds up behind them.

⚠️ A wall retaining soil is no longer just a simple garden wall in many cases. Check local requirements, especially for heights, boundaries, and setbacks.

Step 10: Cure and protect the finished wall

🔟 Let the mortar gain strength properly

Protect fresh blockwork from heavy rain, direct hot sun, and rapid drying for at least 24–48 hours. Light misting may help in hot, dry conditions, but don’t saturate fresh joints.

Avoid backfilling against a retaining wall until mortar and any concrete elements have adequately cured. Follow manufacturer guidance where proprietary blocks or mortar additives are used.

If fitting capping blocks, install them last on a fresh mortar bed once the wall body is firm and true.

Common Mistakes to Avoid

1.Laying the first course out of level, which causes every course above to run crooked
2.Using mortar that is too wet, leading to weak joints and blocks slipping out of line
3.Making joints inconsistent instead of maintaining roughly 10 mm bed and perp joints
4.Building a retaining wall without drainage, causing pressure build-up and premature failure
5.Skipping footing preparation and laying directly on unstable or soft ground
6.Not checking local council rules for retaining walls, boundary walls, or height limits
7.Cutting blocks without proper dust control or PPE

Pro Tips

💡 Dry-lay a few blocks first to work out where cuts will fall so you can avoid tiny awkward end pieces.
💡 Use a tight string line for every course, not just the first one. Professionals rely on the line constantly.
💡 Keep your trowel, board, and block faces clean as you work. It is much easier than cleaning hardened mortar later.
💡 For larger jobs, hiring a mixer and plate compactor is usually cheaper and faster than buying budget units you may only use once.
💡 If appearance matters, choose matching half blocks or corner units from the same manufacturer rather than cutting everything on site.

Recommended Tools

OX Pro Brick Trowel 280 mm — reliable size and balance for spreading mortar and buttering joints
Stabila 1200 mm Spirit Level — accurate levelling for first course and ongoing checks
Makita 230 mm Angle Grinder with diamond masonry blade — useful for cutting concrete blocks cleanly
Belle Minimix 150 Concrete Mixer — ideal hire or purchase option for footings and mortar on medium DIY jobs
Flextool Plate Compactor — best hired for compacting trench base and crushed rock preparation

Frequently asked questions

What is involved in mortar and lay concrete blocks for a garden wall?
A mortared concrete block garden wall is a practical way to create raised garden edges, define landscaping zones, or build a small non-structural boundary feature. For Australian DIY renovators, the key to a straight, durable wall is proper footing preparation, correct mortar consistency, and carefu
What skill level do I need for mortar and lay concrete blocks for a garden wall?
Intermediate — Estimated time: 1–2 days for a small wall up to 5 m long and around 600 mm high, plus footing curing time
What are common mistakes when mortar and lay concrete blocks for a garden wall?
1. Laying the first course out of level, which causes every course above to run crooked 2. Using mortar that is too wet, leading to weak joints and blocks slipping out of line 3. Making joints inconsistent instead of maintaining roughly 10 mm bed and perp joints 4. Building a retaining wall without drainage, causing pressure build-up and premature failure 5. Skipping footing preparatio
What tools do I need for mortar and lay concrete blocks for a garden wall?
This guide includes a comprehensive tools list. Key building & construction tools are detailed in the Tools Required section.
What is the Australian standard for masonry structures?
The primary Australian standard for masonry structures is AS 3700:2018 Masonry Structures. This standard outlines requirements for the design and construction of masonry, including concrete block walls, ensuring structural integrity and safety. For low, non-structural garden walls, adherence to good building practice is usually sufficient, but any wall retaining soil or exceeding height limits must comply with AS 3700.
How deep should a footing be for a concrete block garden wall in Australia?
For a non-structural garden wall up to 600mm high, a footing depth of at least 200mm below natural ground level is generally recommended, with a width at least twice the block width. According to the Concrete Masonry Association of Australia (CMAA), local soil conditions and wall height will influence specific requirements, and a structural engineer should be consulted for retaining walls or taller structures.
What mortar mix ratio is recommended for concrete blocks in Australia?
For general purpose concrete block laying in Australia, a common mortar mix ratio is 1 part cement to 1 part lime (or plasticiser) to 6 parts brickies sand (1:1:6). This mix, as per AS/NZS 3700, provides good workability and strength for non-structural applications. Always ensure the sand is clean and free from impurities for optimal mortar performance.

Written by Bricko, the Building & Construction specialist at VIC.Tools.