Quick answer
Mortar capping a brick garden edging requires cleaning the brickwork, priming with a bonding agent, and applying a 1:1:6 cement, lime, and sand mix at 20 millimetres thickness. Trowel a slight slope toward the garden to shed water, then damp-cure the capping for 72 hours to prevent shrinkage cracking.
- Skill level
- Beginner / Intermediate
- Time
- 4–8 hours for approximately 5–10 m of garden edging
- Trade
- Building & Construction
- Updated
- 28 November 2026
Tools you will need
- Marshalltown 19/11 Durasoft - 250mm London Brick Trowel
- Kraft Tool Elite Series - 150mm Pointing Trowel
- Stabila 70-2 - 600mm Double Plum Spirit Level
- Spear & Jackson - Soft Bristle Coco Fibre Bricklayer's Brush
- Ox Tools Pro - Concave Brick Jointer 1/2in x 5/8in
- Cyclone Heavy Duty - 20L Mixing Tub
🧱 How to Mortar Cap a Brick Garden Edging
What is mortar capping for brick garden edging?
Mortar capping a brick garden edging is a simple way to tidy up the top of an existing brick border, improve its appearance, and help protect the brickwork from water sitting in open joints. It is a practical weekend DIY job for Australian homeowners, especially when preparing a garden for spring, sale, or rental presentation.
Done properly, the cap should be neat, slightly sloped, and well bonded to the brickwork below. For small non-structural garden edging, this is generally a straightforward maintenance task, but any structural masonry should comply with AS 3700 and larger works may require professional advice.
What skill level is required for mortar capping a garden edge?
Beginner / Intermediate — Estimated time: 4–8 hours for approximately 5–10 m of garden edging
What tools are essential for mortar capping a brick garden edging?
What materials are needed for mortar capping a brick garden edging?
Typical mortar options:
Safety Requirements
Step-by-Step Guide
Step 1: Inspect the existing brick edging
1️⃣ Check condition and suitability
Inspect the garden edging to make sure the bricks are stable, reasonably level, and not loose. Mortar capping is only worthwhile if the base brickwork is sound.
Look for:
If the edging is unstable, repair or rebuild those sections first. Mortar capping should not be used to hide structural movement.
Step 2: Decide on the capping finish
2️⃣ Choose the look you want
There are two common ways to mortar cap a brick garden edging:
For most DIY garden edging jobs, a mortar-only cap is the easiest and cheapest option. A finished cap should ideally have a slight fall so water sheds off rather than sitting on top.
Aim for a cap thickness of approximately 15–25 mm above the highest point of the existing brickwork, depending on how uneven the top is.
Step 3: Clean and prepare the brickwork
3️⃣ Create a solid bonding surface
Brush off all dirt, mulch, moss, loose mortar, and plant matter from the top and sides of the edging. Use a stiff broom and hand brush.
If there is old flaky mortar on top, chip it back to a firm surface. Lightly dampen the bricks before applying fresh mortar. This helps prevent dry bricks from sucking moisture out of the new mortar too quickly.
Do not soak the wall. The brickwork should be damp, not dripping wet.
If the surface is very smooth, dusty, or weathered, apply a bonding slurry or proprietary masonry bonding agent as per the manufacturer’s instructions.
💡 A clean, slightly damp surface is one of the biggest factors in getting the mortar cap to bond properly and resist early cracking.
Step 4: Set up guides for a neat, even cap
4️⃣ Use string lines and visual guides
Run a string line along the top of the edging to establish the finished height. If the brick edging curves, work in shorter visual sections and use the existing line of the bricks as your guide.
For straight runs, you can set temporary screed guides using timber battens or carefully applied mortar pads at each end. This helps beginners keep the cap level and consistent.
Allow for a slight slope of around 5–10 mm across the cap width or a gentle crown so water runs off.
Step 5: Mix the mortar
5️⃣ Get the mortar to the right consistency
Mix a small batch first so it does not go off before you use it. For a traditional, workable mortar suitable for non-structural brick garden edging, a common site mix is 1:1:6 cement:lime:sand.
If using a simpler DIY mix, 1:2:3 can be used for general purpose applications, though it can be stiffer and less forgiving to finish.
Add clean water gradually until the mortar is workable and holds on the trowel without slumping. It should be firm enough to shape but wet enough to bond properly.
Do not make the mix too wet. Overwatered mortar is harder to finish, weaker at the surface, and more likely to crack or slump.
💡 For beginners, a pre-blended bricklaying mortar from an Australian hardware supplier can give more consistent results and reduce mixing errors.
Step 6: Apply a bonding bed
6️⃣ Lay the first mortar coat
Using the trowel, spread a firm bed of mortar over a manageable section, usually around 500 mm–1000 mm at a time. Press the mortar down well so it keys into the brick surface and joints.
If the top of the edging is uneven, fill low spots first. Compact the mortar rather than just smearing it over the surface.
For a mortar-only cap, build the mortar slightly proud of the finished height so you can shape it neatly.
Step 7: Form the mortar cap
7️⃣ Shape the top for appearance and drainage
Use the brick trowel and pointing trowel to shape the cap. Common profiles include:
Keep the width consistent and ensure the cap overhangs evenly if that is the intended finish. A neat cap often sits flush with the face of the edging or overhangs only slightly, around 5–10 mm each side.
Smooth the mortar in long passes and compress the surface as you finish. This improves durability and appearance.
Check regularly with the spirit level and by eye from both ends.
Step 8: Finish the edges and joints
8️⃣ Tidy the detail work
Once the mortar has started to firm up, use a pointing trowel or jointing tool to sharpen the edges and create a clean, consistent finish.
Brush off crumbs and lightly sponge any mortar smears from the brick faces before they harden. Keep the sponge only slightly damp so you do not stain or wash out the mortar surface.
If you are capping with bricks rather than mortar only, bed each brick into fresh mortar, tap it into line with a rubber mallet, and fill the joints fully before tooling them neatly.
Step 9: Cure and protect the work
9️⃣ Let the mortar gain strength properly
Protect the finished cap from direct hot sun, heavy rain, sprinklers, and foot traffic. In warm or windy Australian conditions, cover the edging loosely with plastic sheeting after the mortar has firmed enough not to mark.
Light curing over the first 24–48 hours helps reduce rapid moisture loss and shrinkage cracking. Avoid hosing it heavily.
Mortar will usually firm up within a day, but allow at least 48–72 hours before exposing it to normal garden activity. Full curing continues for much longer.
Step 10: Clean up and inspect
🔟 Check the finished result
Once the mortar has set, inspect the entire run for:
Minor imperfections can sometimes be patched early, but extensive cracking usually points to poor preparation, overwatering, or rapid drying.
A successful cap should look even, well bonded, and neatly finished along the full length of the garden edging.
Common Mistakes to Avoid
Pro Tips
Recommended Tools
Frequently asked questions
- What is the best mortar mix ratio for capping brick garden edging?
- The best mortar mix ratio for garden edging is 1:1:6, comprising one part general purpose cement, one part hydrated lime, and six parts clean brickies sand. This blend provides essential flexibility and moisture resistance, reducing cracking caused by thermal movement and garden watering cycles.
- Why does mortar capping crack and pull away from garden bricks?
- Mortar caps fail primarily due to poor surface preparation, excessive mix water, or rapid drying in direct sunlight. Failing to clean loose dirt, omitting an acrylic bonding slurry, or applying mortar over dry, porous bricks draws moisture from the mix, resulting in shrinkage cracks and bond failure.
- How thick should a mortar cap be on brick garden edging?
- A mortar cap should be approximately 20 to 25 millimetres thick at the apex, tapering with a slight cross-fall towards the garden bed. A minimum thickness of 15 millimetres prevents the mortar from crumbling, while the sloped profile stops water pooling on the brickwork.
- Do you need a bonding agent when applying fresh mortar over old bricks?
- A bonding agent or neat cement slurry is essential when capping weathered garden bricks to prevent delamination. Priming the pre-dampened brick tops with an SBR or acrylic bonding agent like Bondall BondCrete ensures the new capping bonds securely to the older, porous substrate.
- How long must mortar capping cure before mulching or mowing nearby?
- Mortar capping requires at least 48 to 72 hours of curing before receiving light disturbance, and a full seven days to achieve structural strength. Keep the capping lightly misted with water under damp hessian or plastic sheeting during the first three days to ensure proper cement hydration.
- What Australian standard applies to domestic brick garden edging?
- Low garden edging is non-structural and exempt from strict certification, but any retaining border exceeding 400 millimetres in soil-retaining height must comply with AS 3700:2018 Masonry Structures. Masonry retaining walls require adequate weep holes, waterproofing, and continuous footing systems.