How to Repair Mortar Joints in Brickwork

Learn how to repair mortar joints in brickwork. Repointing stops water ingress and spalling by replacing cracked mortar to AS 3700 masonry standards.

Quick answer

Repairing mortar joints in brickwork involves raking out degraded mortar to a minimum depth of 15 mm, dampening the joint, and packing fresh cement-lime mortar securely into the gap. Matching mortar strength to the existing brick is essential under Australian Standard AS 3700 to prevent brick spalling and moisture ingress.

Skill level
Intermediate
Time
4–8 hours per 5 m² of brickwork, plus 2–7 days curing time
Trade
Building & Construction
Updated
28 November 2026

Tools you will need

  • Makita GA5040RZ - 125 mm Angle Grinder with Dust Extraction Shroud
  • Kango 8 mm x 200 mm - Diamond Mortar Raking Blade
  • Estwing 570 g (20 oz) - Club Hammer with Shock Reduction Grip
  • Footprint 225 mm - Plugging Chisel
  • Marshalltown 150 mm x 10 mm - Brick Jointer / Tuck Pointer
  • Ox Pro Heavy Duty - Aluminium Mortar Hawk (300 mm x 300 mm)
  • Hozelock 1.25 L - Multi-Spray Pressure Mister Bottle
  • Tradeware 100 L - Heavy Duty Steel Brickies Wheelbarrow

What is involved in repairing mortar joints in brickwork?

Repairing mortar joints, also called repointing, restores the weather resistance and appearance of brickwork by removing loose or cracked mortar and replacing it with fresh mortar matched to the original joint. For older Australian homes, this is a practical maintenance job that helps stop water ingress, reduce brick damage, and extend the life of the wall.

What skill level is required for repairing mortar joints?

Intermediate — Estimated time: 4–8 hours per 5 m² of brickwork, plus 2–7 days curing time

What tools are required for repointing brickwork?

Plugging chisel, 6–10 mm and 12–20 mm wide, for controlled mortar removal
Brick bolster and club hammer for stubborn joints
Tuckpointing grinder or 100–125 mm angle grinder with mortar raking blade and dust shroud, for faster removal on larger areas
Joint raker or carbide mortar rake for hand work around soft or older bricks
Pointing trowel, 6 mm and 10 mm, for packing mortar into joints
Hawk or mortar board for holding mortar at working height
Jointing tools, such as a bucket-handle jointer and square jointer, to match the existing profile
Stiff masonry brush and soft hand brush for dust removal and finishing
Spray bottle or low-pressure garden sprayer for dampening joints
Measuring bucket for accurate mortar mix ratios
Mixing bucket or wheelbarrow
Paddle mixer or mortar hoe for consistent mixing
Sponge and clean rags for final clean-up
Ladder or mobile scaffold for work above 1.8–2.0 m
PPE: P2 respirator, safety glasses, hearing protection, gloves, long sleeves, and steel-cap boots

What materials are needed for mortar joint repairs?

Repointing mortar or site-mixed mortar matched to the existing wall colour, strength, and texture
Brickies sand or washed fine sand, matched as closely as possible to existing mortar sand
General purpose cement
Hydrated lime for improved workability and flexibility where appropriate
Clean water
Mortar pigment if required for colour matching
Masking tape and plastic sheeting to protect adjacent finishes
Test board or spare brick for checking mortar colour before full application

Typical mortar options:

General repointing for sound modern brickwork: 1 part cement : 1 part hydrated lime : 5–6 parts sand
General purpose mortar: approximately 1:2:3 cement:sand:aggregate is common for concrete, but not suitable for brick joint repointing
Heritage or very soft older brickwork: use a lime-rich mortar or lime mortar matched to the original; avoid hard cement-rich mixes and seek specialist advice

Approximate quantities:

20 kg pre-blended mortar: suitable for roughly 1.5–3.0 m² of repointing, depending on joint width and rake-out depth
Water: add gradually to achieve a firm, workable mix that holds on a trowel without slumping

Safety Requirements

Wear a P2 respirator when grinding or raking mortar, as brick and mortar dust may contain respirable crystalline silica
Use safety glasses, hearing protection, gloves, long sleeves, and steel-cap boots at all times
If using an angle grinder, fit a dust shroud and connect to a suitable M-class or HEPA-rated dust extractor where possible
Do not use grinders on soft, friable, or heritage brickwork unless you are experienced; hand tools are safer for older homes
Use a stable ladder for short-duration access only; for extended work above 2.0 m, use a properly erected mobile scaffold
Avoid repointing in full sun, strong wind, rain, or when temperatures are below 5°C or above 35°C
Check walls for movement, bowing, stepped cracking, or loose bricks before starting; if present, seek a licensed builder or engineer, as repointing will not fix structural issues
Structural masonry work should comply with AS 3700 Masonry Structures, and significant remedial works may require engineering certification and council or heritage approval
For homes in heritage overlays or with pre-1940s lime mortar, confirm council requirements before removing original mortar

Step-by-Step Guide

Step 1: Inspect the brickwork and confirm the repair scope

Walk the wall and identify which joints are cracked, recessed, powdery, or missing mortar. Tap the mortar lightly with a plugging chisel; loose mortar will sound hollow and break away easily. Also inspect the bricks themselves for spalling, movement, and salt attack.

If you see any of the following, stop and get professional advice:

Diagonal or stepped cracks wider than 3 mm
Bulging or leaning walls
Loose lintels
Damp-related issues coming from flashing, rising damp, or plumbing leaks
Large areas of soft or salt-contaminated bricks

As a DIY rule, repointing is suitable for aesthetic defects and localised weathered joints, not for structural wall movement.

Step 2: Match the existing mortar before you start

The replacement mortar should be slightly softer than the brick, not harder. On many older Australian homes, a hard cement-rich mortar can damage soft clay bricks by trapping moisture and forcing the brick face to break down.

Check:

Colour: grey, off-white, cream, or buff
Sand texture: fine or coarse
Joint profile: flush, bucket-handle, weather-struck, or struck
Mortar hardness: older lime mortars are generally softer

For a small patch, prepare 2–3 test mixes on a spare brick or inconspicuous area. Let them dry for 24–48 hours, because mortar usually dries lighter than when first placed.

Step 3: Prepare the work area

Cover paths, windows, garden beds, and painted surfaces with plastic sheeting. Remove any vines, dirt, cobwebs, or loose surface contamination. If the wall has been painted or sealed, repointing results may be inconsistent unless coatings are removed first.

Set up:

Ladder or mobile scaffold
Dust extraction if grinding
Buckets for clean water and waste mortar
Separate hand tools for delicate brick areas

Only work on a manageable section, typically 1–2 m² at a time.

Step 4: Remove damaged mortar to the correct depth

Rake out defective mortar to a minimum depth of 15–20 mm, or about 2 to 2.5 times the width of the joint, whichever is greater. Remove all loose, crumbly, and cracked mortar until you reach sound material.

Best method by wall type:

Soft old bricks: use a plugging chisel, joint raker, and hammer by hand
Harder modern bricks: a tuckpointing grinder can be used carefully on bed joints, then finish perps by hand
Tight corners and around openings: always use hand tools

Important technique:

Keep tools centred in the joint
Do not widen the joint unnecessarily
Do not chip brick arrises, as this is the most common DIY damage
Rake horizontal bed joints first, then vertical perp joints

Clean out all debris as you go.

Step 5: Brush and wash the joints clean

Use a stiff masonry brush to remove all dust and loose particles from the raked joints. Then lightly rinse or spray the wall so the joints are clean but not saturated.

Mortar will not bond properly to dusty joints. Fine dust left behind can cause the new mortar to debond or crack early.

Step 6: Pre-dampen the brickwork

Before repointing, dampen the brick faces and joints with a spray bottle or low-pressure sprayer. The bricks should be cool and slightly damp, with no standing water.

This step is critical in Australia’s warm and dry conditions. Dry bricks can suck moisture out of fresh mortar too quickly, leading to:

poor bond
shrinkage cracking
weak joints
colour inconsistency

In hot weather, you may need to re-dampen the area several times.

Step 7: Mix the mortar correctly

Mix only small batches that can be used within 30–45 minutes. A suitable general repointing mix for many non-heritage brick homes is:

1 part cement
1 part hydrated lime
5–6 parts clean brickies sand

Add water slowly until the mortar is firm, workable, and able to stay on the pointing trowel. It should not be wet or sloppy. For patch repairs, pre-blended repointing mortar can be more consistent and easier for DIY use.

Important:

Match the original mortar strength as closely as possible
Do not use structural concrete mixes for repointing
For heritage walls or lime mortar homes, use an appropriate lime-based mortar and seek specialist advice

Let the mixed mortar sit for 5–10 minutes, then remix briefly before use.

Step 8: Pack the vertical joints first

Using a small pointing trowel, mortar gun, or hawk and jointer, firmly press mortar into the vertical perp joints first. Work the mortar in layers if the joint is deeper than 15 mm, ensuring there are no voids behind the face.

Compact the mortar tightly. The goal is a fully filled joint, not just a thin surface skim.

Finish the mortar slightly proud of the brick face at first.

Step 9: Fill the horizontal bed joints

After the perp joints, fill the horizontal bed joints. Again, press the mortar firmly into the back of the joint, then build it out to the face.

For wide or deep joints:

apply in 2 passes
allow the first lift to firm slightly before the second
avoid overfilling and smearing across brick faces

Only repoint as much area as you can tool before the mortar stiffens.

Step 10: Tool the joints to match the existing profile

Once the mortar has started to firm up and is thumbprint hard, tool the joints to the same finish as the original wall. Common profiles include:

Bucket-handle: compressed, rounded finish; very durable and common on Australian homes
Flush: finished level with brick face
Weather-struck: sloped to shed water
Recessed: used for appearance, but less weather-resistant

Tooling compresses the mortar face and improves durability. Avoid tooling too early, as this drags mortar out of the joint. Avoid tooling too late, as the mortar will crumble and not compact properly.

Step 11: Brush off the wall and tidy the brick faces

When the mortar has firmed further, lightly brush the joints and brick faces with a soft brush to remove crumbs and create a neat finish. Do not use excessive water or acid cleaners on fresh mortar.

If mortar smears remain on the brick face:

let them dry slightly
remove gently with a dry or slightly damp sponge
avoid wire brushing soft bricks

Acid cleaning is not recommended for fresh DIY repointing and can damage both the mortar and some brick types.

Step 12: Cure the mortar properly

Fresh mortar needs slow curing to gain strength and reduce shrinkage. Lightly mist the repaired area for the next 2–3 days in warm or windy weather. Protect it from direct sun, strong wind, and rain with hessian or breathable sheeting if needed.

Good curing practice:

Keep the wall damp, not soaked
Do not repoint in extreme weather
Avoid pressure washing or painting for at least 2–4 weeks

Mortar colour will continue to change as it cures.

Step 13: Inspect the finished work

After 24–48 hours, check the joints for:

shrinkage cracks
gaps at brick edges
hollow or underfilled spots
poor colour match
inconsistent profile

Touch up small defects promptly while the colour difference is still manageable. If large areas are mismatched, it is usually better to redo a full panel rather than isolated patches.

Common Mistakes to Avoid

1.Using mortar that is too hard for the brickwork, especially on older homes with soft clay bricks or lime mortar.
2.Raking out joints too shallow; less than 15 mm often leads to poor bond and early failure.
3.Damaging brick edges with an angle grinder or chisel by cutting outside the joint line.
4.Repointing dusty or dry joints without proper cleaning and dampening first.
5.Smearing mortar over brick faces and trying to wash it off with too much water or acid before it has cured.

Pro Tips

Repoint a full visual section, such as between downpipes or window openings, rather than scattered individual joints, for a more uniform finish.
On older Australian brickwork, hand raking is slower but often gives a cleaner result and far less brick damage than a grinder.
Match the joint profile exactly; even a good colour match will look wrong if the tooling finish is different.
If you are unsure about mortar colour, make it slightly lighter rather than darker, as repairs tend to stand out less over time.
Hiring a mortar rake, dust extractor, and mobile scaffold is usually more economical than buying them for one-off repairs, but purchase hand tools and jointing tools as they are low-cost and useful for future maintenance.

Recommended Tools

100–125 mm angle grinder with tuckpointing blade and dust shroud — useful for faster raking on hard modern mortar, but only where brick condition allows
Carbide mortar rake — excellent for controlled hand removal around soft bricks and window reveals
Marshalltown or Ox brick jointer set — reliable for matching bucket-handle and flush joint profiles
Pointing trowel set, 6 mm and 10 mm — gives better control when packing narrow bed and perp joints
P2 respirator and M-class dust extractor — essential for silica dust control during mortar removal

Frequently asked questions

How deep do you need to grind out mortar joints before repointing?
Mortar joints must be raked out to a minimum depth of 15 mm to 20 mm, or roughly twice the joint width. Raking to a solid, square profile ensures the fresh mortar locks mechanically into the joint. Removing insufficient depth prevents adequate adhesion and leads to early bond failure and cracking.
What mix ratio should be used for repointing brick mortar in Australia?
Modern Australian brickwork generally uses an M3 mortar mix of 1 part cement, 1 part hydrated lime, and 6 parts washed brickies sand. Older homes built before 1950 require a softer, lime-rich mix such as 1 part lime to 3 parts sand to prevent damage to softer clay bricks.
Can you use an angle grinder to remove old mortar from brick joints?
Yes, a 125 mm angle grinder fitted with a diamond mortar-raking blade and dust extraction shroud is standard. However, you must avoid nicking the brick arrises. Hand chisels, such as plugging chisels, should always be used near corners, perpendicular perpends, and on historic or heritage masonry.
Why is it important to wet brick joints before applying new mortar?
Dry clay bricks act like sponges, rapidly drawing water out of fresh mortar before the cement can properly hydrate. Misting the cleaned joints with water prevents flash drying, avoids shrinkage cracking, and ensures the mortar cures to full compressive strength in accordance with Australian masonry construction standards.
What is the difference between repointing and tuckpointing?
Repointing is the structural replacement of deteriorated mortar joints flush with or slightly recessed into the brick edge. Tuckpointing is a specialist decorative finish where the joint is filled with mortar matching the brick colour, followed by a narrow, contrasting ribbon of lime putty applied precisely down the centre.
How long does repointed mortar take to cure in Australian conditions?
Repointed mortar achieves initial set within 24 to 48 hours, but requires up to 28 days for full compressive curing. Keep fresh joints sheltered from direct sun and wind, lightly misting them daily for the first three days to manage heat-induced shrinkage, especially in warmer Australian climates.