Fence posts are set by excavating a hole one-third of the total post length deep and three times the post width wide. Place 50mm of drainage gravel beneath the post, plumb and brace it, then pour concrete, sloping the top surface away from the post to shed water.
- Skill level
- Beginner
- Time
- 1-2 hours per post, excluding concrete curing time
- Trade
- Building & Construction
- Updated
- 28 November 2026
Tools you will need
- Cyclone - Post Hole Digger Clamshell
- Ryobi RPHD-1800 - 2-Stroke Petrol Post Hole Digger
- Stabila 196-2 - 1200mm Heavy Duty Spirit Level
- Bailey - 100L Steel Tray Heavy Duty Wheelbarrow
- Trojan - Round Mouth Fibreglass Shovel
- Stanley FatMax - 8m Magnetic Tape Measure
- Boral Cement - Rapid Set Concrete 20kg
- Marshalltown - 150mm x 75mm Pointing Trowel
Why is proper fence post installation important in Australia?
This guide provides a comprehensive, step-by-step process for correctly setting fence posts in concrete, ensuring a strong, durable, and plumb fence. Proper post installation is crucial for the longevity and stability of any fence, whether for boundary lines, gates, or privacy screens.
What skill level is required to set fence posts in concrete?
Beginner — [Estimated time: 1-2 hours per post, excluding concrete curing time]
What tools are essential for setting fence posts in concrete?
Post Hole Digger: Manual clamshell type or petrol-powered auger (150mm - 200mm diameter recommended). Consider hire vs. purchase for auger. Shovel: Square mouth for digging, round mouth for mixing. Wheelbarrow: For mixing concrete. Spirit Level: 1200mm (4-foot) for checking plumb, and a smaller 600mm (2-foot) for general use. Tape Measure: 8m or 10m. String Line & Line Level: For establishing a straight fence line and consistent post height. Marking Paint or Chalk: For layout. Trowel or Finishing Trowel: For shaping concrete. Bucket: 10L or 20L for water. Stirring Stick/Rod: For mixing concrete. Gloves: Heavy-duty work gloves. Safety Glasses: AS/NZS 1337.1 compliant. Ear Protection: If using a petrol auger. Timber Stakes and Bracing: For temporarily supporting posts (e.g., 50x50mm timber, 2.4m long). Clamps or Screws: For attaching braces. Drill/Driver: If using screws for braces.What materials are needed for concreting fence posts?
Fence Posts: Timber (e.g., H4 treated pine 90x90mm or 100x100mm) or steel (e.g., 65x65mm galvanised SHS). Quantity as per fence length. Rapid Set Concrete Mix: Pre-bagged, typically 20kg bags. Approximately 1-2 bags per post, depending on hole size. (e.g., Boral, Cement Australia). Water: For mixing concrete. Gravel/Aggregate (optional): For drainage at the bottom of the post hole. Nails or Screws: For temporary bracing.What are the key safety requirements for setting fence posts?
Personal Protective Equipment (PPE): Always wear safety glasses, heavy-duty gloves, and sturdy enclosed footwear. Use ear protection when operating noisy machinery like petrol augers. Manual Handling: Be aware of the weight of concrete bags and posts. Lift with your legs, not your back. Get assistance for heavy lifting. Underground Services: Before digging, always call Dial Before You Dig (1100) to locate any underground services (water, gas, electricity, communications). Digging without checking can be extremely dangerous and costly. Scaffolding: Not typically required for fence posts, but ensure stable footing when working. Working with Concrete: Wet concrete is alkaline and can cause skin irritation or burns. Avoid prolonged skin contact. Wash thoroughly with water if contact occurs.Step-by-Step Guide
Step 1: Plan and Mark Out the Fence Line
Begin by accurately planning your fence layout. Use a tape measure to determine post spacing (typically 1.8m to 2.4m for timber fences). Drive timber stakes at each end of the proposed fence line and run a string line taut between them. Use marking paint or chalk to mark the exact centre of each post hole along the string line. Ensure the line is level using a line level.
Step 2: Dig the Post Holes
Using your post hole digger or auger, excavate the holes. For a standard 1.8m to 2.4m high fence, post holes should be approximately 600mm deep and 200-250mm in diameter. For taller or heavier fences, or in loose soil, increase depth to 750mm. The hole depth should be roughly one-third of the post's above-ground height. Ensure the sides of the hole are as straight as possible. If using timber posts, consider adding 50-100mm of gravel at the bottom of the hole for drainage to prevent rot, especially for non-treated timber.
Step 3: Prepare the Post and Concrete Mix
For timber posts, ensure the bottom section that will be buried is adequately treated (e.g., H4 treated pine for in-ground contact). For steel posts, ensure they are galvanised. Place the required number of rapid set concrete bags into your wheelbarrow. Read the manufacturer's instructions for the specific water-to-mix ratio. Generally, for rapid set, you add water directly to the hole after placing the dry mix. For standard concrete, mix thoroughly in the wheelbarrow to a workable, slump-free consistency (like thick porridge). A general purpose concrete mix ratio is 1 part cement, 2 parts sand, 3 parts aggregate (1:2:3).
Step 4: Position and Plumb the First Post
Place the first post into its hole. Use your 1200mm spirit level to check that the post is perfectly plumb (vertical) on at least two adjacent sides. Use temporary timber braces (e.g., 50x50mm timber) secured to the post and staked into the ground to hold it firmly in position. Ensure the top of the post aligns with your string line for consistent height.
Step 5: Pour and Set the Concrete
If using rapid set concrete: Pour the dry concrete mix around the post in the hole. Then, slowly add water according to the manufacturer's instructions, ensuring it penetrates the entire mix. Use a stirring stick to agitate the mix and remove air pockets.
If using pre-mixed concrete: Shovel the mixed concrete into the hole around the post, filling it to just above ground level. Tamp the concrete with a shovel or rod to remove air pockets. Slope the top of the concrete away from the post to shed water and prevent pooling, which can lead to rot or corrosion.
Step 6: Brace and Cure
Re-check the post for plumb immediately after pouring the concrete, as it may shift slightly. Adjust if necessary. Leave the temporary braces in place until the concrete has fully cured. Rapid set concrete typically sets in 15-30 minutes, but full strength is achieved over 24-48 hours. Standard concrete requires 24-48 hours before applying significant load, with full strength reached in 28 days. Refer to AS 3600 Concrete Structures for curing guidelines.
Step 7: Repeat for Remaining Posts
Once the first post is securely set and plumb, move to the next post. Use your string line to maintain alignment and consistent spacing. For long fence runs, it's often best to set the end posts first, then run a string line between them to guide the intermediate posts.
Common Mistakes to Avoid
Pro Tips
Pre-Drill Pilot Holes for Braces: If screwing braces to timber posts, pre-drilling pilot holes prevents splitting. Use a Post Level: A specialised post level wraps around the post, allowing you to check plumb on two sides simultaneously, speeding up the process. Consider a Concrete Collar: For timber posts, ensure the concrete extends slightly above ground level and slopes away from the post. This "collar" prevents water from pooling directly at the timber-concrete interface, reducing rot. Clean Tools Immediately: Concrete is much harder to remove once it has cured. Clean all tools thoroughly with water immediately after use.Recommended Tools
Frequently asked questions
- How deep should a fence post hole be in Australia?
- A standard Australian fence post hole must be dug to a minimum depth of one-third of the total post length, or at least 600mm deep for standard 1.8-metre boundary fences. In reactive clay or high-wind zones classified under AS 1170.2, hole depths should increase to 700mm to 900mm.
- Can you use rapid set concrete for structural fence posts?
- Rapid-set concrete is suitable for standard intermediate fence posts, but should not be used for heavy load-bearing applications like gate posts or structural retaining posts. High-stress posts require standard 20MPa to 25MPa concrete mix blended with potable water, which achieves proper compressive strength compliant with AS 3600.
- Do you put gravel at the bottom of a fence post hole?
- Place approximately 50mm to 100mm of aggregate or drainage gravel at the bottom of the post hole before setting timber posts. This creates a drainage bed that allows water to escape away from the timber end grain, significantly reducing the risk of premature fungal rot and subterranean termite attack.
- How long should concrete cure before attaching fence rails or palings?
- Wait at least 24 to 48 hours before attaching fence rails and lightweight Colorbond sheets, or a minimum of three to seven days for heavy timber palings. While rapid-set concrete hardens within two hours, full design curing strength requires 28 days under typical Australian conditions.
- How do you keep fence posts plumb while concrete sets?
- Secure the post using two timber bracing arms fixed at 90-degree angles to each other, staked into the ground using timber pegs. Check both faces with a 1200mm spirit level before and immediately after pouring concrete, ensuring the post does not drift out of plumb during compaction.
- Should concrete be domed at the top of a fence post hole?
- Slope or dome the concrete collar slightly above ground level away from the post face using a margin trowel. This prevents surface rainwater from pooling against the timber or steel base, channelling runoff directly into the surrounding soil and preventing premature corrosion or rot at the ground line.