How to set out residential footings
Learn how to set out residential footings to AS 2870. Transfer boundary offsets, establish profiles, calculate diagonals, and benchmark levels accurately.
Quick answer
Setting out residential footings requires establishing certified boundary offset pegs, erecting timber profile hurdles clear of excavation paths, and running taut string lines to delineate footing centre lines. Squaring is verified using equal diagonal cross-measurements or the 3-4-5 rule. Trench and bench levels are transferred using a calibrated laser level in accordance with AS 2870.
- Skill level
- Advanced
- Time
- 4–8 hours for a standard house set-out, or 1–2 days on sloping, constrained, or complex sites
- Trade
- Building & Construction
- Updated
- 28 November 2026
Tools you will need
- Topcon RL-H5A - Horizontal Self-Leveling Rotary Laser Level
- Lufkin 30m Pro Series - Fibreglass Long Tape Measure
- Stabila 196-2 LED - 1200mm Heavy Duty Box Beam Level
- Plumb Site 500mm - Heavy-Duty Cast Aluminium Builder's Square
- Suntuf 500m - High-Visibility Fluorescent Nylon Brickies String Line
- Estwing 1.8kg (4 lb) - Hardened Steel Drilling Club Hammer
- Spear & Jackson 1800mm - Heavy Duty Hexagonal Steel Crowbar with Chisel Point
🧱 Residential footing set-out guide for Australian site work
What is involved in setting out residential footings in Australia?
Setting out residential footings is the process of transferring the approved building design from the plans onto the site accurately so excavation, reinforcement, and concrete placement can proceed to line, level, and dimension. On Australian residential jobs, good set-out is critical because any error in building location, footing width, offsets, levels, or squareness can affect structural compliance, slab geometry, boundary setbacks, and final buildability.
This guide covers a professional workflow for setting out strip footings, pad footings, and slab edge beams on typical residential projects, with reference to AS 2870, AS 3600, AS 3700, survey control, and common council/site requirements. Structural footing dimensions and founding depths must follow the engineer’s drawings and soil classification documentation.
What skill level is required for setting out residential footings?
Advanced — Estimated time: 4–8 hours for a standard house set-out, or 1–2 days on sloping, constrained, or complex sites
What tools are essential for setting out residential footings?
Materials Required
Safety Requirements
Step-by-Step Guide
Step 1: Review the full documentation set
Start by checking the complete drawing package before a peg goes in the ground. Confirm the latest revision of the site plan, architectural floor plan, engineering footing plan, soil report, contour survey, and any surveyor’s identification survey.
Verify:
Cross-check the architectural dimensions against the engineer’s footing plan. If wall locations and footing centrelines do not reconcile, stop and clarify before proceeding.
Step 2: Establish datum and site control
Set a reliable site datum from a permanent benchmark, survey mark, kerb level, or surveyor-provided control. Mark the benchmark clearly on a protected peg or fixed point that will not be disturbed during earthworks.
Transfer levels using an automatic level or laser level and record:
If a surveyor has provided control marks, adopt these as primary references. On tighter urban sites, independent survey set-out is often the best option to ensure legal building location accuracy.
Step 3: Confirm boundaries and building location
Before setting profiles, confirm the building position relative to boundaries exactly as shown on the site plan. Measure off known survey points or title pegs where available.
Mark the building footprint roughly on the ground using paint so the crew can visually confirm:
Do not rely on fences as legal boundaries unless verified by survey information. A small location error at this stage can create major compliance and certification issues later.
Step 4: Set the primary building line
Select the most reliable reference wall line, usually the longest external wall parallel to a boundary. This becomes your primary control line for the whole footing set-out.
Drive offset pegs clear of the excavation zone and install profile boards beyond where machinery will operate. Profiles should be stable, well braced, and high enough to keep string lines clear during excavation.
Run a string line for the primary wall line and confirm the exact setback from the boundary. Then establish the perpendicular line using:
This line must be exact. Every other line will be derived from it.
Step 5: Square the building footprint
Once the first two principal lines are in place, set out the remaining external wall lines from plan dimensions. Check the rectangle or overall shape by measuring diagonals.
For standard rectangular footprints:
On larger houses, allowable tolerance should be very tight. As a trade benchmark, keep diagonal discrepancy to within 5–10 mm where possible on standard residential work. Re-check after profile adjustment because a small movement in one profile can affect the whole footprint.
For articulated facades and multiple projections, break the set-out into rectangles and check each segment individually, then confirm the global diagonals.
Step 6: Install profiles and mark wall lines
Install timber profiles at all corners and key junctions, offset far enough to remain undisturbed during excavation and footing preparation. Typically keep profiles at least 1000 mm clear of trench edges, more on deeper excavations or unstable ground.
Mark each profile clearly with:
Use nails or screws to hold string lines at exact measured positions. Label profile tops so lines can be re-established quickly if removed during excavation.
Step 7: Transfer footing widths and centrelines
With wall lines established, transfer the actual footing geometry from the engineering drawings. This is where many errors occur, especially when walls are not centred on footings.
Check whether the footing is:
Mark footing trench extents on the ground with paint from the string lines. For example, if a strip footing is 600 mm wide and centred under a wall line, mark 300 mm each side of centre. If it is offset, measure from the nominated face exactly as detailed by the engineer.
Step 8: Set levels for excavation and founding depth
Use your benchmark to determine excavation depth and footing underside levels. Mark cut levels on profile legs, stakes, or grade pegs.
On sloping sites, identify:
Footing founding level must comply with the engineer’s details and soil report. If actual site conditions differ from the documentation, such as uncontrolled fill, soft spots, seepage, or rock, stop and notify the engineer before excavation proceeds.
Step 9: Set out internal footings, pads, piers, and penetrations
After the external footprint is locked in, set out internal loadbearing footings, isolated pads, piers, and special structural points. Pull these from the established external control lines rather than measuring independently from multiple random points.
Mark:
For pad footings, mark both centre point and footing extents. For piers, peg the centre and offset it so the location can be recovered after excavation.
Step 10: Check dimensions, diagonals, and offsets again
Before handing over to excavation, complete a full independent check. This should include:
It is best practice to have a second competent person check the set-out rather than relying only on the original setter-out. Record the verification in the site QA documentation.
Step 11: Mark excavation lines and protect control
Once verified, mark trench lines clearly with paint or lime and identify no-go zones for machine operators. Explain which strings represent wall lines and which represent footing edges so there is no confusion during excavation.
Protect all control marks:
On busy sites, profile loss is common. Good offset control saves rework and delays.
Step 12: Re-establish and verify after excavation
After excavation, re-run the string lines and check that trench positions, widths, and founding levels match the set-out. Confirm:
This is the final opportunity to catch errors before reinforcement and concrete placement. If trench dimensions or soil conditions differ from design assumptions, obtain engineering direction before pouring.
Common Mistakes to Avoid
Pro Tips
💡 Where independent survey set-out is required or the site is constrained, hiring a surveyor or a total station for a day is often more economical than absorbing one boundary or level error.
💡 For larger jobs or repeated project-home work, laser square and rotary laser hire can be more cost-effective than purchase if use is occasional. If your crew is setting out weekly, ownership usually pays back quickly through time savings and fewer call-backs.
Recommended Tools
Frequently asked questions
- How do you set out residential footings accurately?
- To set out residential footings, establish verified boundary control points, erect timber profile hurdles outside the excavation zone, and pull string lines to locate footing centre lines and slab edges. Check squareness using the 3-4-5 rule and diagonal cross-measurements, then benchmark excavation depths with a calibrated optical or laser level against an approved Australian Height Datum (AHD).
- What is the Australian standard for residential footings?
- The primary Australian standard for residential footings is AS 2870: Residential Slabs and Footings. It governs structural design and construction based on site classification and reactive clay movement. Reinforced concrete components must also adhere to AS 3600 for concrete structures, while unreinforced masonry footings align with the design guidelines set out in AS 3700.
- How far back should profile boards be placed from the trench?
- Profile boards should be erected at least 1.0 to 1.5 metres outside the planned trench line. This setback prevents the timber hurdles and string lines from being disturbed or collapsed by 1.5 to 5-tonne mini-excavators swinging tracks, vibrating surrounding ground, or dumping spoil during initial footing excavation.
- How do you check a building set-out for square?
- Check set-out squareness using the mathematical 3-4-5 triangle method on all corners and by measuring equal diagonal distances between opposing corners of rectangular layouts. If both diagonal measurements match exactly to within 2 to 3 millimetres, the intersecting string lines form true 90-degree right angles without angular run-out.
- What are the most common footing set-out mistakes on site?
- The most common footing set-out mistakes include pulling measurements from existing boundary fences rather than certified cadastral survey pegs, forgetting to account for brickwork cavity offsets, failing to recheck diagonals after adjusting string lines, and placing profile hurdles too close to the machine excavation zone.
- How long does a residential footing set-out take?
- A standard rectangular residential set-out on a flat site typically takes 4 to 8 hours for a two-person trade crew. Complex layouts with articulation joints, multiple level steps, steep topography, or tight zero-lot boundaries can take 1 to 2 full days to establish baseline controls and profiles.