How to set out residential footings

Learn how to set out residential footings to AS 2870. Transfer boundary offsets, establish profiles, calculate diagonals, and benchmark levels accurately.

Quick answer

Setting out residential footings requires establishing certified boundary offset pegs, erecting timber profile hurdles clear of excavation paths, and running taut string lines to delineate footing centre lines. Squaring is verified using equal diagonal cross-measurements or the 3-4-5 rule. Trench and bench levels are transferred using a calibrated laser level in accordance with AS 2870.

Skill level
Advanced
Time
4–8 hours for a standard house set-out, or 1–2 days on sloping, constrained, or complex sites
Trade
Building & Construction
Updated
28 November 2026

Tools you will need

  • Topcon RL-H5A - Horizontal Self-Leveling Rotary Laser Level
  • Lufkin 30m Pro Series - Fibreglass Long Tape Measure
  • Stabila 196-2 LED - 1200mm Heavy Duty Box Beam Level
  • Plumb Site 500mm - Heavy-Duty Cast Aluminium Builder's Square
  • Suntuf 500m - High-Visibility Fluorescent Nylon Brickies String Line
  • Estwing 1.8kg (4 lb) - Hardened Steel Drilling Club Hammer
  • Spear & Jackson 1800mm - Heavy Duty Hexagonal Steel Crowbar with Chisel Point

🧱 Residential footing set-out guide for Australian site work

What is involved in setting out residential footings in Australia?

Setting out residential footings is the process of transferring the approved building design from the plans onto the site accurately so excavation, reinforcement, and concrete placement can proceed to line, level, and dimension. On Australian residential jobs, good set-out is critical because any error in building location, footing width, offsets, levels, or squareness can affect structural compliance, slab geometry, boundary setbacks, and final buildability.

This guide covers a professional workflow for setting out strip footings, pad footings, and slab edge beams on typical residential projects, with reference to AS 2870, AS 3600, AS 3700, survey control, and common council/site requirements. Structural footing dimensions and founding depths must follow the engineer’s drawings and soil classification documentation.

What skill level is required for setting out residential footings?

Advanced — Estimated time: 4–8 hours for a standard house set-out, or 1–2 days on sloping, constrained, or complex sites

What tools are essential for setting out residential footings?

Automatic level or rotating laser level with tripod and staff
Builder’s dumpy level for cross-checking RLs
Tape measures: 5 m, 8 m, and 30 m fibreglass site tape
String line, string line reels, and fluorescent mason’s line
Timber profiles/batter boards, typically 90 x 45 mm or similar
Timber pegs/stakes, typically 50 x 50 mm hardwood or treated pine
Club hammer or sledgehammer
Nail bag, galvanised nails, screws, impact driver, and hammer
Marking paint, survey crayons, lumber crayon, and permanent marker
Builder’s square, framing square, and line level
Optical square or laser square where required
Site plans, engineering drawings, contour plan, and sewer/stormwater plans
Calculator or construction calculator
String line level blocks/packers
GPS rover or total station if working from survey control
Soil probe or digging bar for checking founding conditions
Shovel, trenching shovel, mattock, and crowbar
Datum peg tags and profile identification tags

Materials Required

Approved architectural plans and engineering footing layout
Survey plan showing boundaries, setbacks, and permanent marks
Soil report/classification for the site
Timber pegs for control points and profile supports
Timber for profiles/batter boards
Galvanised nails or screws for profile fixing
String line for external wall lines, footing centrelines, and offsets
Marking paint for trench lines and excavation extents
Datum/benchmark identification markers
Site notebook or QA set-out sheet
Engineer-approved footing dimensions and reinforcement notes
Temporary bracing material for profiles on loose ground

Safety Requirements

Wear PPE: hard hat, safety boots, gloves, hi-vis, safety glasses, and hearing protection when driving stakes or using power tools.
Confirm underground services before driving pegs, excavating, or probing. Use Dial Before You Dig information and site service plans.
Maintain safe manual handling practices when carrying profile timber, laser equipment, and pegs.
Keep access paths clear of string lines, offcuts, and tools to reduce trip hazards.
Where work is near excavation edges, follow excavation safety requirements and maintain exclusion zones.
If using ladders or working around elevated profile frames, ensure stable footing and correct ladder use.
Structural set-out must align with approved engineering. Any variation to footing size, founding depth, step location, or pier position requires engineer review.
Concrete footings and structural elements must comply with AS 3600. Masonry support requirements must align with AS 3700. Slab and footing set-out should reflect site classification and design intent under AS 2870.
Check local council and state requirements for setbacks, easements, overland flow paths, and building envelope controls.

Step-by-Step Guide

Step 1: Review the full documentation set

Start by checking the complete drawing package before a peg goes in the ground. Confirm the latest revision of the site plan, architectural floor plan, engineering footing plan, soil report, contour survey, and any surveyor’s identification survey.

Verify:

Boundary lengths and lot orientation
Front, side, and rear setbacks
Easements and building envelope restrictions
Finished floor level and benchmark/RL information
Footing types: strip footing, pad footing, raft/slab beam, piers, or stepped footings
Structural dimensions including footing widths, depths, thickenings, rebates, and internal loadbearing lines

Cross-check the architectural dimensions against the engineer’s footing plan. If wall locations and footing centrelines do not reconcile, stop and clarify before proceeding.

Step 2: Establish datum and site control

Set a reliable site datum from a permanent benchmark, survey mark, kerb level, or surveyor-provided control. Mark the benchmark clearly on a protected peg or fixed point that will not be disturbed during earthworks.

Transfer levels using an automatic level or laser level and record:

Natural surface levels at key corners
Proposed finished floor level
Approximate excavation depth
Required step locations for sloping sites

If a surveyor has provided control marks, adopt these as primary references. On tighter urban sites, independent survey set-out is often the best option to ensure legal building location accuracy.

Step 3: Confirm boundaries and building location

Before setting profiles, confirm the building position relative to boundaries exactly as shown on the site plan. Measure off known survey points or title pegs where available.

Mark the building footprint roughly on the ground using paint so the crew can visually confirm:

Boundary offsets
Garage alignment
Porch/alfresco projections
Compliance with setback requirements

Do not rely on fences as legal boundaries unless verified by survey information. A small location error at this stage can create major compliance and certification issues later.

Step 4: Set the primary building line

Select the most reliable reference wall line, usually the longest external wall parallel to a boundary. This becomes your primary control line for the whole footing set-out.

Drive offset pegs clear of the excavation zone and install profile boards beyond where machinery will operate. Profiles should be stable, well braced, and high enough to keep string lines clear during excavation.

Run a string line for the primary wall line and confirm the exact setback from the boundary. Then establish the perpendicular line using:

3:4:5 method
Builder’s square
Optical/laser square
Total station where required

This line must be exact. Every other line will be derived from it.

Step 5: Square the building footprint

Once the first two principal lines are in place, set out the remaining external wall lines from plan dimensions. Check the rectangle or overall shape by measuring diagonals.

For standard rectangular footprints:

Measure overall length
Measure overall width
Check both diagonals match exactly

On larger houses, allowable tolerance should be very tight. As a trade benchmark, keep diagonal discrepancy to within 5–10 mm where possible on standard residential work. Re-check after profile adjustment because a small movement in one profile can affect the whole footprint.

For articulated facades and multiple projections, break the set-out into rectangles and check each segment individually, then confirm the global diagonals.

Step 6: Install profiles and mark wall lines

Install timber profiles at all corners and key junctions, offset far enough to remain undisturbed during excavation and footing preparation. Typically keep profiles at least 1000 mm clear of trench edges, more on deeper excavations or unstable ground.

Mark each profile clearly with:

External wall line
Internal wall or loadbearing lines
Footing centreline where applicable
Face of footing offsets
Grid references or room identifiers if needed

Use nails or screws to hold string lines at exact measured positions. Label profile tops so lines can be re-established quickly if removed during excavation.

Step 7: Transfer footing widths and centrelines

With wall lines established, transfer the actual footing geometry from the engineering drawings. This is where many errors occur, especially when walls are not centred on footings.

Check whether the footing is:

Centred under the wall
Eccentric due to boundary or retaining conditions
Widened under piers or columns
Stepped for site fall
Thickened under loadbearing masonry or articulation joints

Mark footing trench extents on the ground with paint from the string lines. For example, if a strip footing is 600 mm wide and centred under a wall line, mark 300 mm each side of centre. If it is offset, measure from the nominated face exactly as detailed by the engineer.

Step 8: Set levels for excavation and founding depth

Use your benchmark to determine excavation depth and footing underside levels. Mark cut levels on profile legs, stakes, or grade pegs.

On sloping sites, identify:

Step points in strip footings
Changes in beam depth
Pad footing level changes
Minimum embedment or founding depth below finished ground level

Footing founding level must comply with the engineer’s details and soil report. If actual site conditions differ from the documentation, such as uncontrolled fill, soft spots, seepage, or rock, stop and notify the engineer before excavation proceeds.

Step 9: Set out internal footings, pads, piers, and penetrations

After the external footprint is locked in, set out internal loadbearing footings, isolated pads, piers, and special structural points. Pull these from the established external control lines rather than measuring independently from multiple random points.

Mark:

Internal strip footings
Pad footing centres
Pier centres
Column locations
Articulation joints
Service penetrations that affect footing continuity

For pad footings, mark both centre point and footing extents. For piers, peg the centre and offset it so the location can be recovered after excavation.

Step 10: Check dimensions, diagonals, and offsets again

Before handing over to excavation, complete a full independent check. This should include:

Overall building length and width
All setback dimensions
Internal footing spacing
Diagonal checks
Level checks against benchmark
Footing widths against engineering
Step locations and depth transitions
Clearance from easements and services

It is best practice to have a second competent person check the set-out rather than relying only on the original setter-out. Record the verification in the site QA documentation.

Step 11: Mark excavation lines and protect control

Once verified, mark trench lines clearly with paint or lime and identify no-go zones for machine operators. Explain which strings represent wall lines and which represent footing edges so there is no confusion during excavation.

Protect all control marks:

Brace profiles
Flag string lines
Install extra witness pegs
Record offsets in case profiles are knocked out
Photograph profile layout and notations

On busy sites, profile loss is common. Good offset control saves rework and delays.

Step 12: Re-establish and verify after excavation

After excavation, re-run the string lines and check that trench positions, widths, and founding levels match the set-out. Confirm:

Trench is in the correct location
Bottom width matches footing detail
Footing steps are in the right place
Excavation depth is to the correct level
Over-excavation has not occurred
Soft spots or loose material have been addressed

This is the final opportunity to catch errors before reinforcement and concrete placement. If trench dimensions or soil conditions differ from design assumptions, obtain engineering direction before pouring.

Common Mistakes to Avoid

1.Setting out from fences or assumed boundaries instead of verified survey control.
2.Using architectural wall dimensions only and failing to transfer the engineer’s actual footing widths, offsets, and step details.
3.Not checking diagonals after moving profiles or adjusting string lines.
4.Installing profiles too close to excavation so they are disturbed by machinery.
5.Failing to establish and protect a reliable benchmark, leading to incorrect footing depths or slab levels.
6.Ignoring site conditions such as fill, groundwater, or reactive clay changes that require engineering review.
7.Measuring internal footing positions from multiple inconsistent points instead of from fixed primary control lines.
8.Not documenting the set-out, making it difficult to recover control after excavation damage.

Pro Tips

1.Use one primary baseline and one perpendicular control line for the whole job. This keeps all dimensions traceable and reduces accumulated error.
2.Set profiles far enough back to survive excavation and spoil movement. On machine-heavy sites, extra offset distance is cheap insurance against rework.
3.Mark both wall lines and footing lines separately on the profiles. This avoids confusion when the excavation crew and steel fixers arrive.
4.On articulated house plans, break the footprint into smaller checked rectangles rather than trying to pull every line from one end of the building.
5.Record all critical offsets in a site notebook, including distance from profile to wall line, wall line to footing edge, and benchmark RLs. If strings are lost, recovery is fast.

💡 Where independent survey set-out is required or the site is constrained, hiring a surveyor or a total station for a day is often more economical than absorbing one boundary or level error.

💡 For larger jobs or repeated project-home work, laser square and rotary laser hire can be more cost-effective than purchase if use is occasional. If your crew is setting out weekly, ownership usually pays back quickly through time savings and fewer call-backs.

Recommended Tools

Leica Rugby rotating laser level — reliable for transferring RLs and checking footing excavation levels
Stabila 30 m fibreglass tape — accurate and durable for external footprint and diagonal checks
OX Pro string line reels — fast line deployment and easy profile work
Sutton framing square — useful for short perpendicular checks and profile marking
Topcon total station or site hire equivalent — ideal for complex sites, tight boundaries, and high-accuracy professional set-out

Frequently asked questions

How do you set out residential footings accurately?
To set out residential footings, establish verified boundary control points, erect timber profile hurdles outside the excavation zone, and pull string lines to locate footing centre lines and slab edges. Check squareness using the 3-4-5 rule and diagonal cross-measurements, then benchmark excavation depths with a calibrated optical or laser level against an approved Australian Height Datum (AHD).
What is the Australian standard for residential footings?
The primary Australian standard for residential footings is AS 2870: Residential Slabs and Footings. It governs structural design and construction based on site classification and reactive clay movement. Reinforced concrete components must also adhere to AS 3600 for concrete structures, while unreinforced masonry footings align with the design guidelines set out in AS 3700.
How far back should profile boards be placed from the trench?
Profile boards should be erected at least 1.0 to 1.5 metres outside the planned trench line. This setback prevents the timber hurdles and string lines from being disturbed or collapsed by 1.5 to 5-tonne mini-excavators swinging tracks, vibrating surrounding ground, or dumping spoil during initial footing excavation.
How do you check a building set-out for square?
Check set-out squareness using the mathematical 3-4-5 triangle method on all corners and by measuring equal diagonal distances between opposing corners of rectangular layouts. If both diagonal measurements match exactly to within 2 to 3 millimetres, the intersecting string lines form true 90-degree right angles without angular run-out.
What are the most common footing set-out mistakes on site?
The most common footing set-out mistakes include pulling measurements from existing boundary fences rather than certified cadastral survey pegs, forgetting to account for brickwork cavity offsets, failing to recheck diagonals after adjusting string lines, and placing profile hurdles too close to the machine excavation zone.
How long does a residential footing set-out take?
A standard rectangular residential set-out on a flat site typically takes 4 to 8 hours for a two-person trade crew. Complex layouts with articulation joints, multiple level steps, steep topography, or tight zero-lot boundaries can take 1 to 2 full days to establish baseline controls and profiles.

Written by Bricko, the Building & Construction specialist at VIC.Tools.