How to set out strip footings
Setting out strip footings establishes the structural footprint, alignment, and reduced levels (RL) for an entire build. This process involves establishing offset profile boards (hurdles), running high-tensile string lines to delineate wall and footing centre lines, and confirming squareness using g
- Skill level
- Intermediate to Advanced
- Time
- 4 to 8 hours (depending on site topography and complexity)
- Trade
- Building & Construction
- Updated
- 28 November 2026
Tools you will need
- Rotating Laser Level & Receiver: Dual
- Heavy
- Optical Site Square / Theodolite / Total Station:
- String Lines: Fluorescent, braided, high
- Marking Paint & Chalk: Inverted spot
🧱 Comprehensive Trade Guide: Setting Out Strip Footings to Australian Standards
What is the standard process for setting out strip footings in Australia?
Setting out strip footings establishes the structural footprint, alignment, and reduced levels (RL) for an entire build. This process involves establishing offset profile boards (hurdles), running high-tensile string lines to delineate wall and footing centre lines, and confirming squareness using geometric principles before excavation begins. All set-out operations must strictly comply with structural engineering documentation, the National Construction Code (NCC), AS 2870 (Residential Slabs and Footings), and AS 3600 (Concrete Structures).
Skill Level
Intermediate to Advanced — ⏱️ Skill Level: Intermediate/Trade | ~4 to 8 hours (depending on site topography and complexity)What tools and equipment are required to set out strip footings?
🔧 Tools Required
Rotating Laser Level & Receiver: Dual-grade self-levelling laser with staff (e.g., Leica Rugby or Topcon) Heavy-Duty Sledgehammer: 4.5 kg (10 lb) for driving star pickets and timber pegs Claw Hammer & Cordless Impact Driver: 18V brushless platform for profile construction Optical Site Square / Theodolite / Total Station: (Optional, but best practice for large boundaries) Steel Measuring Tapes: 30 m and 50 m fibreglass/nylon-coated or steel tapes (avoid elastic cloth tapes) String Lines: Fluorescent, braided, high-tensile nylon bricklayers line (non-stretch) Plumb Bob: 450 g to 600 g brass plumb bob with braided line Marking Paint & Chalk: Inverted spot-marking aerosol spray paint (Hi-Vis) and lumber crayonsWhat materials are needed to construct footing profile hurdles?
Profile Timber (Hurdles): 75 x 50 mm or 100 x 38 mm untreated/treated pine stakes and horizontal ledgers Star Pickets: 900 mm to 1500 mm high-tensile steel pickets (used for rocky or hard ground) Fixings: 75 mm wood screws, 50 mm galvanised flat-head clouts, and 65 mm bright bullet-head nails Survey/Boundary Pegs: 50 x 50 mm pointed hardwood survey pegs (300 mm to 450 mm long)Safety Requirements
⚠️ Safety
Mandatory PPE: AS-compliant steel-cap boots (AS 2210.3), Class 5 hearing protection, UV safety glasses, and high-visibility clothing. Underground Services: Dial Before You Dig (1100 / BYDA) plans must be on-site. Perform non-destructive pot-holing or service scanning prior to driving pegs or star pickets into the ground. Manual Handling: Maintain correct posture when driving pegs with a sledgehammer; switch lead arms or use a mechanical star picket driver to reduce musculoskeletal fatigue. Excavation Vicinity: Set back profile hurdles at least 1500 mm to 2000 mm outside the excavation perimeter to prevent ground collapse and preserve critical marks.Step-by-Step Guide
Step 1: Establish Primary Survey Marks & Boundaries 1️⃣
Locate the primary cadastral boundary pins or registered surveyor’s datum pegs as documented on the site plan. Cross-reference all site boundary offsets, boundary setbacks, and clear-zone clearances. Establish a clean, unobstructed baseline representing the primary wall or boundary offset. Set up a rotating laser level on a secure tripod in a central, non-disturbed location. Take a reading on the certified Site Benchmark (BM) or Temporary Benchmark (TBM) to calculate your Instrument Height (IH) and determine all relative finished ground levels and top-of-concrete (TOC) levels in accordance with AS 2870.Step 2: Erect Offset Profile Hurdles 2️⃣
Position profile boards (hurdles) at a minimum offset of 1500 mm to 2000 mm clear of the intended footing trench line to ensure machine access and prevent displacement during earthworks. Drive two vertical 75 x 50 mm timber stakes or star pickets into the ground at each corner and junction point. Secure a horizontal ledger board (100 x 38 mm) level across the stakes using an 18V impact driver and 75 mm screws. Using the laser level, adjust all horizontal profile ledgers on the site to a uniform Reduced Level (RL) or a precise fixed offset above the proposed top of footing/concrete level.Step 3: Run Gridlines, Centre Lines, and Wall Offsets 3️⃣
Pull high-tensile braided string lines across opposing profile boards to establish the external building perimeter lines. Secure string lines across the top of ledgers using 65 mm bullet-head nails or by cutting 5 mm saw kerfs into the timber. Transfer the boundary offset dimensions exactly as indicated on the engineering and architectural structural drawings. Establish secondary parallel string lines representing the external brickwork/blockwork face, cavity, internal skin, and footing trench edge lines.Step 4: Verify Squareness (3-4-5 Method & Diagonal Checking) 4️⃣
Check initial right angles at intersections using the Pythagorean theorem: measure 3000 mm along one string line, 4000 mm along the perpendicular string line, and adjust until the hypotenuse measures exactly 5000 mm (or scale up to 6000 mm : 8000 mm : 10000 mm for larger profiles). Perform full-building diagonal cross-checks across the entire rectangular grid. Diagonal measurements corner-to-corner ($A-C$ and $B-D$) must match precisely ($±\mathbf{2\text{ mm}}$ tolerance). If diagonals differ, adjust the string lines parallel along the profile boards until exact equality is reached while maintaining boundary setback limits.Step 5: Plumb Down and Mark Ground Excavation Trenches 5️⃣
Drop a heavy brass plumb bob (450 g – 600 g) from the string line intersections down to natural ground level to eliminate parallax error caused by wind or line sag. Drive temporary timber indicator pegs directly below the string intersections. Measure out from the wall centre lines or brick face lines to establish the trench width (e.g., for a 400 mm wide strip footing supporting a 230 mm brick cavity wall, mark 200 mm each side of the centre line). Using high-visibility inverted aerosol ground marker paint, spray continuous, clear trench guidelines on the ground for the excavator operator. Clearly mark critical Reduced Levels (RLs), trench depths, and step locations on adjacent profiles and indicator pegs.Common Mistakes to Avoid
Pro Tips
💡 Saw-Kerf Marking: Instead of driving nails into the top edge of profile timber (which can catch lines or bend), cut a neat 3 mm to 5 mm saw kerf at your exact line point using a handsaw. The string drops cleanly into the slot and retains position under tension. 💡 Colour-Code Profile Nails: Use distinct paint colours or tags on hurdle nails to separate different elements (e.g., Red = Trench Edge, White = Brick/Block Face, Blue = Cavity/Internal Frame). 💡 Equipment Hire vs Purchase: For precision foundations, hire a calibrated dual-grade laser with digital receiver or a total station for $120–$200/day if you do not perform set-outs weekly; it eliminates the calibration liability and capital cost of high-end survey equipment ($3,000+). 💡 Tension Springs for Long Runs: On spans over 25 m, incorporate a small screen-door tension spring on one end of the string line to maintain uniform tension regardless of temperature shifts throughout the day.Recommended Tools
Leica Rugby 610 / Topcon RL-H5A Rotating Laser: High-accuracy horizontal self-levelling laser for establishing profile heights and checking sub-base excavation depths. Empire 450g Solid Brass Plumb Bob: Essential for transferring suspended string line intersections to ground markers accurately without wind deflection. Lufkin Executive 30m / 50m Heavy-Duty Steel Tape: High-accuracy, zero-elasticity steel tape measure for precise diagonal cross-checks and boundary confirmation. Spear & Jackson Heavy-Duty Post Hole/Picket Driver: Minimises manual fatigue and prevents mushrooming timber pegs/star pickets when establishing sturdy hurdle stations.Frequently asked questions
- What is involved in set out strip footings?
- Setting out strip footings establishes the structural footprint, alignment, and reduced levels (RL) for an entire build. This process involves establishing offset profile boards (hurdles), running high-tensile string lines to delineate wall and footing centre lines, and confirming squareness using g
- What skill level do I need for set out strip footings?
- Intermediate to Advanced — ⏱️ Skill Level: Intermediate/Trade | ~4 to 8 hours (depending on site topography and complexity)
- What are common mistakes when set out strip footings?
- 1. Setting Profiles Too Close to Trenches: Installing hurdles within 1000 mm of the dig zone leads to profile failure caused by excavator track displacement or trench slumping. Maintain a 1500 mm – 2000 mm buffer. 2. Using Inelastic or Low-Grade Line: Using standard twisted twine causes line sag and stretch, leading to horizontal set-out errors exceeding 20 mm over long spans.
- What tools do I need for set out strip footings?
- This guide includes a comprehensive tools list. Key building & construction tools are detailed in the Tools Required section.
- What is the Australian standard for setting out strip footings?
- The primary Australian standard for setting out strip footings is AS 2870-2011 (Residential Slabs and Footings), alongside AS 3600-2018 for structural concrete. These standards specify set-out tolerances, minimum trench depths, and bearing requirements relative to site classification. Structural engineering drawings take precedence to comply with National Construction Code performance requirements.
- How far should profile hurdles be placed from the footing trench?
- Profile hurdles must be set back between 1,500 mm and 2,000 mm from the proposed trench excavation edge. According to SafeWork Australia excavation guidelines, this minimum clearance prevents profile displacement from plant machinery tracking, soil surcharge loading, and edge blowouts during heavy excavator operations.
- How do you square a strip footing set-out accurately?
- Square a strip footing set-out by applying the 3-4-5 Pythagorean theorem or by measuring opposing corner-to-corner diagonal string lines. For a true 90-degree corner, the diagonal measurements between intersecting grid lines must be exactly equal, verified using a calibrated steel or fibreglass tape measure.
- What line should be used for setting out building profiles?
- High-tensile braided nylon bricklayers line (fluorescent) must be used rather than standard twisted string or cotton cord. Braided line resists sagging, moisture stretch, and wind deflection across spans exceeding 20 metres, ensuring critical alignment tolerances within 2 mm are maintained.
Written by Bricko, the Building & Construction specialist at VIC.Tools.