How to Lay Bricks for Beginners
Learn how to lay bricks for beginners using Australian standards. Master mortar mixes, bed joints, perp joints, and stretcher bond for structural brick walls.
Quick answer
Laying bricks requires spreading a uniform 10mm mortar bed, buttering the cross-joints, and aligning units flush along a taught stringline in a stretcher bond. All standard Australian residential masonry construction must conform to the tolerances, bond patterns, and material requirements set out in AS 3700:2018.
- Skill level
- Intermediate
- Time
- 4-6 hours for a small wall
- Trade
- Building & Construction
- Updated
- 28 November 2026
Tools you will need
- Marshalltown 19/11D - 280mm Philadelphia Pattern Brick Trowel
- Empire 1200mm True Blue - Box Beam Spirit Level
- OX Pro Heavy Duty - Brick Bolster (100mm)
- Estwing 24oz - Club Hammer
- Boral 20kg Mortar Mix or Brickies Sand and GP Cement
- Marshalltown 1/2-Inch x 5/8-Inch - Convex Brick Jointer
- OX Tradesman - Braided Nylon Brick Line and Line Pins
What fundamental bricklaying techniques should beginners learn?
Fundamental bricklaying technique covering mortar mixing, bed joints, perp joints, level control, and stretcher bond.
This guide walks you through every stage of the process, from preparation and tool selection right through to finishing. Whether you are tackling this project for the first time or looking to refine your technique, the steps below will help you achieve a professional result.
Skill Level: Intermediate | Estimated Time: 4-6 hours for a small wallWhat essential preparations should you make before laying bricks?
Before picking up any tools, take a few minutes to prepare properly. Good preparation is the difference between a smooth project and a frustrating one.
What tools are required for beginner bricklaying in Australia?
Having the right tools makes every step faster, safer, and more accurate. Below is the complete tool list for this project. If you do not own a particular tool, consider whether hiring or purchasing makes more sense for your situation -- tools over $300 may be eligible for the EOFY instant asset write-off if used for income-producing purposes.
Step-by-Step Guide
Follow these steps in order. Each step builds on the previous one, so resist the temptation to skip ahead. Take your time with the early stages -- accurate preparation saves hours of correction later.
Step 1: Mix mortar: 1 part cement, 5-6 parts sand, plasticiser, water to butter consistency
This is your foundation step. Getting this right sets the standard for everything that follows. Double-check all measurements and marks before committing to any cuts or fixings. If something does not look right at this stage, it is far easier to adjust now than after you have progressed further.
Step 2: Lay a dry course first to check spacing and cut positions
With your initial preparation complete, this step moves you into the main construction phase. Ensure all your materials are within reach and your work area is clear of obstructions. Maintain consistent technique throughout to achieve uniform results.
Step 3: Set up string line between profiles at first course height
Work methodically through this step, checking your progress as you go. Accuracy at each stage ensures the final result meets a professional standard. If you are unsure about any aspect, refer back to the measurements and specifications noted earlier.
Step 4: Butter mortar bed on foundation and place first brick
Work methodically through this step, checking your progress as you go. Accuracy at each stage ensures the final result meets a professional standard. If you are unsure about any aspect, refer back to the measurements and specifications noted earlier.
Step 5: Level and plumb each brick, tap to adjust
Work methodically through this step, checking your progress as you go. Accuracy at each stage ensures the final result meets a professional standard. If you are unsure about any aspect, refer back to the measurements and specifications noted earlier.
Step 6: Butter end (perp joint) of next brick before placing
You are at the midpoint of the project. This is a good time to pause, check your progress against the plan, and verify everything is level, plumb, and square. Correcting small errors now prevents them from compounding through the remaining steps.
Step 7: Check level frequently both along and across the course
Work methodically through this step, checking your progress as you go. Accuracy at each stage ensures the final result meets a professional standard. If you are unsure about any aspect, refer back to the measurements and specifications noted earlier.
Step 8: Start alternate courses with a half brick for stretcher bond
Work methodically through this step, checking your progress as you go. Accuracy at each stage ensures the final result meets a professional standard. If you are unsure about any aspect, refer back to the measurements and specifications noted earlier.
Step 9: Tool (finish) mortar joints when thumbprint firm
Work methodically through this step, checking your progress as you go. Accuracy at each stage ensures the final result meets a professional standard. If you are unsure about any aspect, refer back to the measurements and specifications noted earlier.
Step 10: Clean excess mortar off face of bricks before it sets
This final step brings the project together. Take your time here and focus on the finish quality. Step back and inspect your work from different angles. Small adjustments at this stage make a significant difference to the overall appearance and performance of the finished result.
Safety Notes
Safety is not optional. Australian workplace health and safety regulations apply to all construction work, including domestic projects. The notes below highlight specific hazards for this project.
Always have a first aid kit accessible at your work site. If you are working alone, let someone know where you are and what you are doing.
Pro Tips from the Trade
These tips come from years of hands-on experience. They represent the kind of knowledge that separates a good job from a great one.
Tip 1: Dampen bricks before laying so they do not suck moisture from mortar. This may seem like a small detail, but experienced tradespeople consistently use this technique to deliver a better result in less time. Tip 2: Keep mortar consistency like soft butter throughout the day. This may seem like a small detail, but experienced tradespeople consistently use this technique to deliver a better result in less time. Tip 3: A good joint finish separates professional from amateur work. This may seem like a small detail, but experienced tradespeople consistently use this technique to deliver a better result in less time.Common Mistakes to Avoid
Learning from other people's mistakes saves you time, money, and frustration. These are the most common errors seen in this type of project.
Mistake 1: Mixing mortar too wet or too dry. This is one of the most frequent problems encountered. It can result in wasted materials, poor structural integrity, or the need to redo significant portions of the work. Take the time to get it right the first time. Mistake 2: Not checking level frequently enough. This is one of the most frequent problems encountered. It can result in wasted materials, poor structural integrity, or the need to redo significant portions of the work. Take the time to get it right the first time. Mistake 3: Spreading too much mortar at once which dries before bricks are laid. This is one of the most frequent problems encountered. It can result in wasted materials, poor structural integrity, or the need to redo significant portions of the work. Take the time to get it right the first time.Materials List
Below is the complete materials list. Quantities will vary based on your specific project dimensions. Always purchase 10-15% extra to account for cuts, waste, and any errors during construction. Check availability at your local supplier before starting the project.
When to Call a Professional
While this guide covers a intermediate-level project that many competent DIYers can tackle, there are situations where professional help is the smarter choice:
Hiring a licensed professional for critical aspects of the work is not a sign of failure -- it is a sign of good judgement. The cost of getting it right the first time is always less than the cost of fixing it later.
Frequently asked questions
- What is the correct mortar mix ratio for laying standard house bricks?
- The standard mortar mix ratio for Australian bricklaying is 1 part cement, 1 part hydrated lime, and 6 parts brickies sand by volume (Class M3). This ratio ensures high workability and durable joint strength conforming to AS 3700:2018. For coastal or aggressive soil conditions, use an M4 mix consisting of a 1:0.5:4.5 ratio.
- How thick should mortar joints be when laying bricks?
- Mortar joints should be a consistent nominal thickness of 10mm for both horizontal bed joints and vertical perp joints under AS 3700. Standard Australian clay bricks measure 230mm long by 110mm wide by 76mm high. Maintaining uniform 10mm joints ensures a standard vertical gauge of 86mm per course.
- How do you keep a brick wall straight and level while building?
- Lay the lead corners first, using a spirit level to plumb vertical faces and level the courses, then string a taut nylon line between corner pins. Lay intermediary bricks flush to the top edge of this stringline without touching it, ensuring straightness across long runs.
- Why do bricks need to be dampened before applying wet mortar?
- Dry clay bricks rapidly absorb moisture from wet mortar via capillary suction, which starves the cement of water needed for hydration and causes weak, powdery joints. Lightly misting high-suction bricks prevents premature drying, ensuring the mortar cures properly to form a strong, waterproof chemical bond.
- What personal protective equipment is required for bricklaying in Australia?
- Bricklayers in Australia must wear alkaline-resistant nitrile work gloves, AS/NZS 1337-compliant safety glasses, steel-cap work boots (AS 2210.3), and high-visibility clothing on commercial worksites. Wet Portland cement has a high alkaline pH of approximately 12 to 13, which can cause severe caustic chemical burns upon skin contact.
- When should you tool or strike the mortar joints on a brick wall?
- Tool mortar joints once the mortar reaches 'thumbprint hardness', meaning it is firm enough to resist deep indentation but pliable enough to compress cleanly without smearing. Compressing joints with a concave wheeled jointer seals the mortar against weather penetration while producing a clean, professional finish.
Written by Bricko, the Building & Construction specialist at VIC.Tools.