Skip to main content

How to build a basic timber deck

A basic timber deck is one of the most achievable outdoor carpentry projects for an Australian homeowner, provided the set-out, footings and framing are done properly from the start. This guide covers a freestanding, low-level timber deck using common Australian materials and construction method

Skill level
Intermediate
Time
2-4 days for a typical 15-20 m² deck
Trade
Carpentry & Joinery
Updated
28 November 2026

Tools you will need

  • String line, timber pegs and profile boards for set
  • Spirit level 1800 mm or laser level
  • Framing square and speed square
  • Post hole digger or power auger
  • Shovel, wheelbarrow and mixing tub or concrete mixer
  • Circular saw 185 mm or compound mitre saw
  • Decking countersink bit for hardwood boards
  • Clamps and a deck board straightener or pry bar
  • Socket set/spanners for bolts
  • Orbital sander for edge finishing and clean

🪚 Basic timber deck trade guide for Australian homeowners and DIY builders

What is involved in building a basic timber deck in Australia?

A basic timber deck is one of the most achievable outdoor carpentry projects for an Australian homeowner, provided the set-out, footings and framing are done properly from the start. This guide covers a freestanding, low-level timber deck using common Australian materials and construction methods, with sizing and fixings aligned to good trade practice and checked against AS 1684 Residential Timber-Framed Construction, AS 1720 Timber Structures, and local council requirements.

What skill level is required for a basic timber deck project?

Intermediate — Estimated time: 2-4 days for a typical 15-20 m² deck

Which essential tools are needed for timber deck construction?

Tape measure 8 m, chalk line, pencils and marking knife
String line, timber pegs and profile boards for set-out
Spirit level 1800 mm or laser level
Framing square and speed square
Post hole digger or power auger
Shovel, wheelbarrow and mixing tub or concrete mixer
Circular saw 185 mm or compound mitre saw
Impact driver 18V and drill/driver with timber and masonry bits
Decking countersink bit for hardwood boards
Clamps and a deck board straightener or pry bar
Socket set/spanners for bolts
Orbital sander for edge finishing and clean-up

What materials are typically required for a low-level timber deck?

🪵 Quantities below suit a typical freestanding 4.8 m x 3.6 m low-level deck; adjust to your final deck size and span tables.
Decking boards: 90x19 merbau, 86x19 spotted gum, or 90x22 H3 treated pine
Joists: 140x45 H3 treated pine, typically at 450 mm centres
Bearers: double 140x45 H3 treated pine or 190x45 H3 treated pine, subject to span and post spacing
Posts/stumps: 90x90 H4 treated pine or equivalent, typically 9-12 for a deck of this size
Galvanised adjustable stirrups for each post
Concrete: 20 MPa premix, approximately 1.0-1.5 m³ depending on footing size and quantity
Joist hangers or approved structural fixing brackets
Noggings/blocking: 90x45 or 140x45 treated pine
Galvanised or stainless steel bolts: M12 galvanised bolts with washers and nuts for bearer-to-post connections
Structural screws: galvanised or Class 4 rated for outdoor use
Decking screws: 10g x 65 mm stainless steel or Class 4 for 19-22 mm decking
Joist protection tape for all joist tops
End-grain preservative for cut treated pine
Decking oil or exterior timber sealer
Weed mat/geotextile and drainage gravel for under-deck area if required
Optional fascia/border boards: 140x19 or 90x19 to suit decking species

Safety Requirements

⚠️ Wear safety glasses, hearing protection, P2 dust mask, gloves and steel-cap boots
Confirm underground services through Before You Dig Australia before any excavation
Check local council and state requirements before building; approvals may apply depending on deck height, size, boundary setbacks, and whether it is attached to the dwelling
If the finished deck is more than 1 m above ground, balustrade and stair compliance under the NCC will usually apply
Do not cover or bridge weep holes, damp-proof course, or required termite inspection zones on brick veneer homes
Use only exterior-rated fixings suitable for the timber species and exposure conditions, particularly in coastal areas
Where structural loads, retaining walls, or house attachment are involved, obtain advice from a licensed builder, engineer, or certifier

Step-by-Step Guide

Step 1: 1️⃣ Plan the deck size, height and approvals

Start by deciding the deck footprint and finished height.

For a beginner-friendly project, a freestanding low-level deck is the safest option because it avoids complex waterproofing and structural attachment to the house. A common size is 4.8 m x 3.6 m, which suits outdoor dining and seating without becoming too expensive or structurally complicated.

Check the following before you buy materials:

Local council approval requirements
Boundary setbacks
Finished floor level relative to doors
Drainage away from the house
Clearance to weep holes and termite inspection zones

💡 Keep the deck surface at a practical level below the door threshold and maintain clearance to wall cladding and brickwork. On brick veneer homes, do not block weep holes.

All timber member sizes must be confirmed against AS 1684 span tables or supplier engineering data. If in doubt, increase member sizes rather than undersizing the frame.

Step 2: 2️⃣ Set out the deck accurately

Mark the deck corners using pegs, string lines and profile boards.

Measure the footprint carefully and square it using the 3-4-5 method or by checking diagonals. If the diagonals match, the layout is square. This matters because even a small error at set-out will show up later as tapered decking boards and untidy fascia lines.

Mark post locations next. For a basic low-level deck, post centres are often in the range of 1800-2400 mm, depending on bearer size and span design.

Also check the site levels:

The deck frame itself should generally be built level
The ground underneath should fall away from the house for drainage
Keep enough under-deck ventilation to reduce moisture build-up

💡 Run strings to the outside face of bearers or rim boards, not just to post centres. It makes the frame easier to position and check during installation.

Step 3: 3️⃣ Dig footings and install stirrups

Excavate footing holes at each post location.

For a basic deck, typical footing sizes are around 300-450 mm diameter and 450-600 mm deep, but footing size depends on soil type, deck loads and local requirements. Always dig to firm natural ground, not loose fill.

Pour concrete and set galvanised stirrups so they are:

In line with your string
Level to each other
High enough to keep timber above ground and splashback

Allow the concrete to cure before loading the stirrups. A minimum of 24-48 hours is common for light work, longer in cool weather.

💡 Adjustable stirrups make it much easier to fine-tune post height and keep the frame level.

Step 4: 4️⃣ Install posts and bearers

Cut and stand the 90x90 H4 posts into the stirrups, then plumb and brace them.

Fix the bearers to the posts using M12 galvanised bolts or approved structural screws. For a typical low-level deck, double 140x45 H3 treated pine bearers are common, though 190x45 may be needed for longer spans.

As you work:

Keep all post tops and bearer tops to a consistent level
Check each post for plumb
Crown the timber upward where applicable
Recheck string lines before final fixing

If the deck is close to the ground, take extra care to preserve ventilation and avoid timber sitting where water can pond.

💡 Do not guess bearer sizes from appearance alone. Span tables exist for a reason, and undersized bearers are one of the most common causes of sagging decks.

Step 5: 5️⃣ Install joists, rim boards and blocking

Fix the outer rim boards first, then install the joists.

For 19-22 mm decking boards, a standard joist spacing of 450 mm centres is a good starting point for most domestic decks. Use 140x45 H3 treated pine joists unless engineering or span tables require larger members.

Secure joists with joist hangers or structural screws. Then install:

A rim board around the perimeter
Blocking/noggings at mid-span or as needed to keep joists straight
Additional framing where board joins, fascia, steps or posts will occur

If the deck has any height above ground or possible lateral movement, include diagonal bracing to suit the design.

Apply joist protection tape to the top of each joist before laying boards. This helps reduce moisture sitting around screw penetrations and extends frame life.

💡 Hardwood decking is durable, but the frame underneath usually fails first if water sits on unprotected joists. Joist tape is inexpensive insurance.

Step 6: 6️⃣ Dry-lay the decking and check board spacing

Before fixing all the boards, place a few boards loosely across the frame to check how the layout will finish.

This helps you avoid ending up with a tiny rip on the last board. Adjust your starting point or use a border board if needed.

Typical installation rules:

Leave 4-6 mm gaps between boards, or follow the board supplier’s specification
Maintain a 10-15 mm gap where decking meets walls or fixed structures
Plan all butt joins over a double joist
Stagger butt joins for a cleaner appearance if the layout allows

If using merbau or spotted gum, pre-drill near board ends to reduce splitting.

💡 Do not rely on “eye spacing”. Use a spacer, gauge block or proprietary deck spacer so your gaps stay consistent across the whole job.

Step 7: 7️⃣ Fix the decking boards properly

Start from your straightest reference edge and fix each board with two screws at every joist.

For 90x19 or similar decking, the screws should generally sit about 12-15 mm in from each board edge. Use 10g x 65 mm stainless steel or Class 4 decking screws suited to exterior timber.

As you lay boards:

Pull bowed boards straight using clamps or a deck board straightener
Check alignment every 4-5 boards
Keep butt joins neat and supported
Maintain even board overhangs before trimming ends

Once all boards are fixed, snap a chalk line and trim the outer edge for a clean straight finish.

💡 Hardwood decking often moves slightly after installation. Neat, consistent screw lines and uniform spacing make the finished deck look professional even after seasonal movement.

Step 8: 8️⃣ Fit fascia boards, steps or edge trims

Once the deck boards are down, install fascia or border boards to conceal the frame and create a finished edge.

Use matching decking species or treated pine fascia depending on your budget and finish level. Fix fascia boards so they remain clear of the ground and have room to drain and dry.

If the deck needs steps:

Keep risers consistent, usually around 170-190 mm
Aim for tread depths of around 240-250 mm or more
Ensure solid support under stair stringers
Check stair and balustrade requirements under the NCC if the deck height triggers compliance

Sand or plane sharp arrises on exposed edges to reduce splintering.

Step 9: 9️⃣ Seal, inspect and maintain the deck

Clean the completed deck thoroughly and remove metal filings, sawdust and tannin residue.

Treat all cut ends of treated pine with an appropriate preservative. For the decking surface, apply a quality exterior oil or sealer in line with the manufacturer’s instructions. Some hardwood products are best left to weather briefly before oiling, while others can be coated sooner, so always confirm the product recommendation.

Carry out a final inspection:

Check all screws and bolts are tight
Make sure the deck feels solid underfoot
Confirm there are no proud fixings or split boards
Verify water drains away from the house and under the deck remains ventilated

Ongoing maintenance is straightforward:

Wash the deck every 6-12 months
Recoat as needed based on sun and weather exposure
Inspect fixings, movement and any signs of rot annually

💡 A basic annual inspection adds years to the life of a deck, especially in coastal or high-rainfall areas.

Common Mistakes to Avoid

1.Using undersized bearers, joists or footings without checking span tables and site conditions.
2.Building the deck too close to the house and covering weep holes, drainage paths or termite inspection zones.
3.Setting joists wider than recommended for the decking thickness, which leads to bounce and premature board movement.
4.Using the wrong screws or brackets for outdoor timber, especially with merbau or in coastal areas where corrosion is more aggressive.
5.Failing to square the deck at set-out, which results in tapered board widths, crooked fascia lines and poor visual finish.

Pro Tips

💡 For a first deck, choose a freestanding design rather than attaching a ledger to the house. It is simpler, safer and avoids many waterproofing issues.
💡 Use H4 treated pine for posts and H3 treated pine for above-ground framing. Match all fixings to the exposure environment.
💡 Install joist protection tape and treat every cut end. These two small steps make a noticeable difference to service life.
💡 If you are using merbau, wash the boards before final finishing to reduce tannin bleed onto paving or concrete.
💡 If you are purchasing trade-grade tools over $300 for eligible business use, check the current ATO EOFY instant asset write-off rules with your accountant before buying.

Recommended Tools

Makita 18V Impact Driver Kit — reliable for decking screws and structural screws without excessive wrist fatigue
DeWalt 185 mm Circular Saw — ideal for clean cutting of 90x45, 140x45 and decking boards on site
Bosch Green Beam Laser Level — speeds up post height setting, bearer levelling and overall set-out accuracy
Sutton Tools Decking Countersink Bit — very useful when pre-drilling hardwood decking such as merbau and spotted gum
Bessey Deck Board Straightener — helps pull bowed boards into line for consistent spacing and a cleaner finish

Frequently asked questions

What is involved in build a basic timber deck?
A basic timber deck is one of the most achievable outdoor carpentry projects for an Australian homeowner, provided the set-out, footings and framing are done properly from the start. This guide covers a freestanding, low-level timber deck using common Australian materials and construction method
What skill level do I need for build a basic timber deck?
Intermediate — Estimated time: 2-4 days for a typical 15-20 m² deck
What are common mistakes when build a basic timber deck?
1. Using undersized bearers, joists or footings without checking span tables and site conditions. 2. Building the deck too close to the house and covering weep holes, drainage paths or termite inspection zones. 3. Setting joists wider than recommended for the decking thickness, which leads to bounce and premature board movement. 4. Using the wrong screws or brackets for outdoor
What tools do I need for build a basic timber deck?
This guide includes a comprehensive tools list. Key carpentry & joinery tools are detailed in the Tools Required section.
What is the Australian standard for timber deck construction?
The primary Australian standards governing timber deck construction are AS 1684 Residential Timber-Framed Construction and AS 1720 Timber Structures. These standards provide guidelines for timber selection, span tables, and fixing methods, ensuring structural integrity and safety. Always consult the latest editions and local council requirements.
How long does it take to build a basic timber deck?
A basic, freestanding low-level timber deck, typically 15-20 m² in size, generally takes an intermediate-skilled tradie or DIY builder between 2 to 4 days to complete. This timeframe can vary based on site conditions, weather, and the efficiency of the construction process.
What are common mistakes to avoid when building a deck?
Common mistakes include using undersized bearers or joists without consulting span tables, obstructing weep holes or termite inspection zones, and incorrect joist spacing for the chosen decking thickness. Using inappropriate fasteners for outdoor conditions is also a frequent error, leading to premature failure. Always refer to AS 1684 for correct sizing and fixing.
What type of timber treatment is recommended for deck posts in Australia?
For deck posts in ground contact in Australia, H4 treated pine (Hazard Level 4) or equivalent is recommended. This treatment protects against severe decay and insect attack, ensuring the longevity and structural stability of the deck's foundation. For above-ground components, H3 treated timber is typically sufficient.

Written by Chippy, the Carpentry & Joinery specialist at VIC.Tools.