How to install a timber fence post and panel

Learn how to install timber fence posts and panels to Australian standards. Get footing depths, H4 timber specs, and post-setting techniques that last.

Quick answer

To install a timber fence post and panel, set H4 treated pine posts into 600mm deep concrete footings spaced 2.4 metres apart. Plumb each post with a spirit level, attach H3 treated horizontal rails, and fix palings 50mm clear of the soil using hot-dipped galvanised fasteners under AS 1684.

Skill level
Intermediate
Time
6–10 hours for a short run of 3–5 panels, or 1–2 days depending on soil, access, and concrete curing time
Trade
Carpentry & Joinery
Updated
28 November 2026

Tools you will need

  • Stabila 196-2 LED - 1200mm Heavy-Duty Spirit Level
  • Post Hole Digger - Cyclone Heavy Duty Post Hole Pincer
  • Milwaukee M18 FUEL - 1/4 Inch Hex Impact Driver
  • Makita DHS680Z 18V Brushless - 165mm Circular Saw
  • Spear & Jackson - 1800mm x 25mm Hexagonal Digging Bar
  • Bahco 300mm - Combination Square
  • Bostitch F28WW-E - Pneumatic Framing Nailer

🪚 How to Install a Timber Fence Post and Panel

What is involved in installing a timber fence post and panel?

Installing a timber fence post and panel properly is all about accurate set-out, solid footings, and keeping every post plumb and in line. For Australian conditions, the job needs to account for wind loads, soil type, termite risk, drainage, and boundary requirements so the fence stays straight and serviceable for years.

This guide covers a standard timber boundary fence installation suitable for repairs or new work, using common Australian materials and methods. For structural guidance, set-out, fixing requirements, and good practice, refer to AS 1684 Residential Timber-Framed Construction and check local council rules for height, boundary placement, and any state-specific fencing regulations.

What skill level is required to install a timber fence post and panel?

Intermediate — Estimated time: 6–10 hours for a short run of 3–5 panels, or 1–2 days depending on soil, access, and concrete curing time

What tools are required for timber fence post and panel installation?

Tape measure — minimum 8 m
String line and line level for straight set-out
Post hole digger or 2-person auger for faster excavation
Shovel and digging bar for rocky ground
Spirit level — 1200 mm preferred
Circular saw or mitre saw with timber blade
Impact driver and drill/driver combo
Clamps for holding rails and panels in position
Quick-set square or framing square
Wheelbarrow and mixing tray if mixing concrete manually
Concrete mixer if installing multiple posts
Nail gun or hammer depending on fixing method
Stringline pins or timber pegs
Pencil/marker and chalk line

What materials are needed for a standard timber fence post and panel installation?

🪵 Materials

Fence posts — typically 100x100 mm H4 treated pine or 125x75 mm H4 treated pine, quantity to suit fence length
Fence panels — pre-made treated pine panels or site-built palings panels, typically 1800 mm wide
Fence rails — typically 70x35 mm or 90x45 mm H3 treated pine, usually 2 or 3 rails per bay
Palings if building panels on site — common sizes 100x16 mm or 150x16 mm treated pine
Concrete mix — approximately 2–4 bags per post depending on hole size
20 mm drainage gravel — 1/4 to 1/2 bag per hole where required
Galvanised batten screws or Type 17 timber screws — 50 mm, 75 mm, or 100 mm to suit members
Hot-dip galvanised nails if nailing off palings or rails
Temporary bracing timber — 70x35 mm offcuts
Timber preservative for cut ends
Exterior-grade string line
Post caps optional, for weather protection
Exterior fence stain, oil, or paint optional for finishing
Termite management products if required in termite-prone areas
Packers/shims for panel alignment

Safety Requirements

⚠️ Safety

Wear PPE: safety glasses, hearing protection, gloves, steel-cap boots, and dust mask when cutting treated timber.
Use correct manual handling technique when lifting 100x100 mm posts, concrete bags, and full panels.
Locate all underground services before digging using Before You Dig Australia.
Confirm boundary location before installation; disputes can arise if the fence is built off-line.
Check state and local council rules for maximum fence heights, pool-adjacent fencing requirements, and front boundary restrictions.
Treated pine offcuts and sawdust should be handled carefully and disposed of appropriately.
If using power tools outdoors, use an RCD-protected circuit or site-safe extension leads.

Step-by-Step Guide

Step 1: Plan the fence line and confirm boundary

1️⃣ Confirm layout and legal position

Measure the total fence run and identify where each post will sit. Most timber fence panels are set out in regular bays, commonly around 1800 mm centre-to-centre or to suit the manufactured panel width.

Confirm the boundary with title plans, existing survey marks, or a licensed surveyor if there is any doubt. Do not rely solely on an old fence line, especially after storm damage.

Check local requirements for:

Maximum fence height
Shared boundary fencing obligations
Visibility near driveways
Pool barrier implications if relevant

💡 Pro tip: If you are replacing only one section, measure multiple existing bays first. Older fences are often out of square, so matching the actual opening is better than assuming standard panel width.

Step 2: Set out the post positions

2️⃣ Run a straight line and mark centres

Drive a peg at each end of the proposed fence line and run a tight string line. This will become your reference for keeping posts aligned.

Mark each post centre along the line. For pre-made panels, use the exact manufacturer panel width plus any bracket allowance. For site-built fencing, spacing can be adjusted slightly, but keep bays consistent for appearance and strength.

Double-check:

Total run length
End conditions at house walls, gates, or returns
Whether the fence steps or rakes on sloping ground

💡 Pro tip: On sloping sites, decide early whether the fence will be stepped or raked. A stepped fence is easier for DIY work and more common with standard panels.

Step 3: Dig the post holes

3️⃣ Excavate to proper depth and diameter

Dig each hole typically to 600 mm deep minimum for a standard 1800 mm high residential fence, though deeper holes may be required in soft ground, high wind areas, or for taller fences. A common hole diameter is 250–300 mm for 100x100 mm posts.

As a practical guide:

Standard suburban fence: 250–300 mm diameter x 600 mm deep
Softer soil or exposed sites: increase depth to 700–900 mm if needed
Taller or heavier fence: increase footing size accordingly

Keep the hole base relatively flat and remove loose spoil. In poorly drained ground, place a small amount of 20 mm gravel at the bottom to assist drainage, but do not use gravel as a substitute for correct footing depth.

⚠️ Always locate underground services before digging.

Step 4: Cut and prepare the posts

4️⃣ Size posts correctly and seal cut ends

Cut posts to length allowing for:

Above-ground fence height
Post embedment depth
Extra length if you intend to trim tops after installation

For example, for a 1800 mm high fence with 600 mm in-ground depth, a post length of around 2400 mm is typical before trimming.

Apply timber end sealer/preservative to all cut ends, especially on treated pine, to improve durability. Use H4 treated pine for in-ground posts, not H3, as H4 is rated for ground contact.

💡 Pro tip: Leave posts slightly overlength and trim the tops to a finished line after the concrete has set. This gives a neater final result.

Step 5: Concrete the first post in place

5️⃣ Set the first post plumb

Position the first post in the hole and align it to the string line. Keep the face of the post just touching the line or offset consistently, rather than pushing the line out of position.

Check plumb in both directions with a 1200 mm spirit level. Brace the post temporarily with 70x35 mm timber screwed to stakes.

Place concrete around the post and compact it well. Finish the top of the concrete slightly proud and sloped away from the post so water sheds clear rather than pooling at the timber.

Allow quick-set concrete to firm up enough that the post will not move before proceeding.

Step 6: Install the remaining posts

6️⃣ Work bay-by-bay and maintain alignment

Repeat the process for each post along the fence line, checking:

Post spacing
Plumb
Height consistency
Straightness to the string line

Measure from post to post carefully so each panel or rail span fits properly. It is good practice to install all posts first for a long run, but for DIY beginners, installing posts one or two bays at a time can reduce cumulative error.

If ground falls significantly, determine your finished top line before fixing panels. On stepped fences, each bay drops in a controlled increment. On raked fences, posts remain vertical while rails and palings follow the slope.

💡 Pro tip: Sight along the line from one end after every second or third post. Minor alignment issues are easier to fix while the concrete is still green.

Step 7: Fit the rails or panel support framing

7️⃣ Fix the structural members securely

If using pre-made fence panels, install the required support rails or fixing cleats between posts to suit the panel type. If building the fence from individual rails and palings, fix 2 or 3 rails between posts depending on fence height.

Typical rail sizes:

70x35 mm H3 treated pine for lighter fencing
90x45 mm H3 treated pine for stronger spans or exposed sites

For a standard 1800 mm high paling fence, a common arrangement is:

Bottom rail approximately 150–250 mm above ground
Mid rail centred
Top rail approximately 150–200 mm below top of fence

Use galvanised screws or hot-dip galvanised nails suitable for external treated timber. Predrill near ends if splitting is likely.

Reference good framing and fixing practice under AS 1684 principles, particularly for connection durability and member alignment.

Step 8: Install the fence panel or palings

8️⃣ Fix panels level and evenly spaced

Lift the panel into place and pack it off the ground slightly to reduce moisture contact. A typical clearance is 50–75 mm above finished ground level unless site conditions require otherwise.

Clamp the panel to the posts, then check:

Level across the bay
Even reveal to adjacent panels
Bottom clearance consistency

Fix off with galvanised screws or approved brackets as per the panel manufacturer’s instructions.

If building from loose palings:

Fix palings to rails starting at one end
Use a spacer for consistent gaps
Keep top lines true with a string or chalk line
Nail or screw each paling securely to every rail

💡 Pro tip: For privacy fences, maintain consistent paling gaps across the whole run. Even a 3–5 mm variation becomes obvious over several bays.

Step 9: Trim, cap, and finish the fence

9️⃣ Complete the final presentation and weather protection

Once the fence is fixed and the posts are secure, trim post tops to a neat uniform height if required. Install post caps if specified.

Check all fixings are seated properly and that no sharp edges or protruding fasteners remain. Sand or plane any rough edges likely to be handled.

Apply your chosen finish:

Exterior timber oil for a natural look
Fence stain for colour and UV protection
Exterior paint for a solid finish

Follow manufacturer drying times and only coat timber when moisture levels and weather conditions are suitable.

Step 10: Final inspection and clean-up

🔟 Check performance and tidy the site

Walk the fence line and inspect:

All posts plumb
Panels secure
Rails tight
Ground clearance consistent
No loose concrete or spoil left around the base

Backfill and compact any disturbed ground around footings once the concrete has sufficiently cured. Remove braces only when the posts are fully stable.

Dispose of treated timber waste, concrete bags, and fastener packaging correctly.

Common Mistakes to Avoid

1.Using the wrong treatment class — in-ground posts must be H4 treated pine, not H3.
2.Setting posts too shallow — shallow footings lead to leaning and movement, especially after rain or wind.
3.Ignoring the string line — even small alignment errors become obvious over a long fence run.
4.Fixing panels hard onto the ground — this traps moisture and shortens the life of the timber.
5.Not checking boundary location first — this can create expensive disputes and rework.
6.Poor concrete finish at the post base — flat or dished concrete holds water against the post.
7.Using non-galvanised fixings — these will corrode quickly in outdoor conditions, particularly near the coast.

Pro Tips

💡 Use quick-set concrete for single-post repair jobs, but for larger runs, mixing standard concrete in bulk is often more economical.
💡 In coastal areas, upgrade to hot-dip galvanised or even stainless steel fixings for better durability.
💡 If the site is exposed to strong winds, consider heavier posts such as 125x75 mm or 100x100 mm and reduce bay width if needed.
💡 Mark one face of every post as your control face so all measurements are taken from the same side.
💡 If purchasing a new auger, saw, or driver kit for the job, tools over $300 may be relevant to the EOFY instant asset write-off if used for eligible small business purposes—worth checking with your accountant if the tools are for trade or business use.

Recommended Tools

🔧 Recommended Tools

Makita 18V Brushless Impact Driver — reliable for fastening rails and panels into treated pine
Ox Pro 1200 mm Spirit Level — useful for accurate post plumbing
Sutton Tools Auger or post hole digging setup — helps in firm ground and reduces digging time
DeWalt or Makita Circular Saw with framing blade — clean cutting for posts and rails
Irwin Quick-Grip clamps — ideal for holding panels and rails in position during fixing

Frequently asked questions

How deep should a fence post hole be in Australia?
A standard Australian timber fence post requires a hole depth equal to one-third of its total length, typically at least 600mm deep for a 1.8-metre fence. In reactive clay, loose sand, or high-wind zones classified under AS/NZS 1170.2, increase post footing depth to 700mm to 900mm to prevent movement.
Can you use H3 treated pine for fence posts in ground?
No, H3 treated pine must not be used in-ground because it is rated only for above-ground external applications subject to periodic wetting. In-ground timber fence posts require H4 or H5 treated pine under AS 1604, providing essential resistance against fungal rot, ground moisture, and subterranean termite attack.
How much concrete do you need per timber fence post?
Each standard fence post footing typically requires two 20kg bags of rapid-set or standard concrete mix for a 600mm deep, 200mm diameter hole. For corner, gate, or end posts subjected to higher mechanical loads, use three to four bags within a 250mm to 300mm wide footing.
What is the Australian standard for building a timber boundary fence?
Timber boundary fence construction is governed by AS 1684 for structural timber framing, AS 1604 for preservative treatment, and AS/NZS 1170.2 for structural wind actions. Additionally, residential boundary fences must comply with state-specific dividing fences legislation and local municipal council planning schemes regarding maximum heights.
How far apart should timber fence posts be spaced?
Timber fence posts in Australia should be spaced between 2.1 metres and 2.4 metres apart on centre, matching standard rail lengths. Spacing posts beyond 2.4 metres risks rail sag, structural twisting, and panel failure under moderate wind loads or when using heavy hardwood or treated pine palings.
How do you keep timber fence panels off the ground?
Install an H4 treated pine plinth board or leave a minimum 50mm clearance between the bottom of the fence panel palings and the soil. Suspending timber palings above ground level prevents direct contact with damp soil, reducing ground moisture absorption, fungal decay, and premature termite infestation.

Written by Chippy, the Carpentry & Joinery specialist at VIC.Tools.