Skip to main content

How to install internal doors

Installing internal doors is a core finishing carpentry task that demands accurate set-out, clean machining and careful adjustment to achieve consistent margins, smooth operation and compliant clearances. On Australian fit-outs and renovation work, the quality of the install is judged on the reveal,

Skill level
Intermediate
Time
1.5 to 3 hours per door depending on whether the jamb is existing or new, and whether lockset preparation is included
Trade
Carpentry & Joinery
Updated
28 November 2026

Tools you will need

  • Tape measure 5 m and folding rule
  • 2 m spirit level and 1.2 m level
  • Combination square and sliding bevel
  • Sharp pencil, marking knife and hinge marker
  • Cordless drill/driver 18V
  • Trim router with hinge rebate bit/jig or sharp bevel
  • Block plane and/or electric planer
  • Hammer and nail punch
  • Door lifter, wedges and packers
  • Clamps

🪚 Internal Door Installation Trade Guide

What is involved in installing internal doors in Australia?

Installing internal doors is a core finishing carpentry task that demands accurate set-out, clean machining and careful adjustment to achieve consistent margins, smooth operation and compliant clearances. On Australian fit-outs and renovation work, the quality of the install is judged on the reveal, latch engagement, swing, and final finish.

This guide covers the professional workflow for hanging standard internal swing doors, including sizing, planing allowances, hinge placement, latch preparation and final adjustment. Where relevant, tolerances and framing considerations should align with AS 1684 Residential Timber-Framed Construction and manufacturer requirements for jambs, hinges and door hardware.

What skill level is required for internal door installation?

Intermediate — Estimated time: 1.5 to 3 hours per door depending on whether the jamb is existing or new, and whether lockset preparation is included

What specific tools are required for professional internal door installation?

Tape measure 5 m and folding rule
2 m spirit level and 1.2 m level
Combination square and sliding bevel
Sharp pencil, marking knife and hinge marker
Cordless drill/driver 18V
Trim router with hinge rebate bit/jig or sharp bevel-edge chisels
Block plane and/or electric planer
Circular saw with guide or track saw for trimming door height/width if required
Hole saw set and spade bits / auger bits for latch preparation
Hammer and nail punch
Door lifter, wedges and packers
Clamps
Impact driver for fixing jamb screws where required
Random orbital sander with 120/180 grit
Dust extraction / shop vacuum

What materials are typically needed for an internal door installation?

Internal door leaf to schedule size, commonly 2040 x 820 mm, 2040 x 770 mm, 2040 x 720 mm or 2340 mm high where specified
Door jamb set to suit wall thickness, commonly 67 mm, 92 mm, 110 mm or custom
Loose stop or integrated stop jamb components if applicable
Hinges, typically 3 x 100 x 75 mm butt hinges for standard internal doors
For taller/heavier doors, 4 hinges may be required
Hinge screws, preferably quality steel screws to suit hinge manufacturer
Latch set / passage set / privacy set as specified
Door stop or magnetic stop where required
Timber packers / plastic packers
Fixing screws for jamb installation, typically 75 mm to 100 mm
Construction adhesive where specified by manufacturer
Wood filler / stopper
Touch-up paint, sealer or clear finish
Masking tape
Lubricant for latch and hinge tuning
Optional door bottom seal or acoustic seal if specified

Safety Requirements

Wear P2 dust mask or respirator, safety glasses, hearing protection and steel-cap boots
Use cut-resistant handling practices when trimming doors and machining hardware mortices
Secure the door leaf on trestles or a door bench before planing, routing or drilling
Check for concealed services before fixing jambs into adjacent framing in renovation work
Follow site SWMS, builder induction and state-specific WHS requirements
Maintain compliant manual handling practices, particularly with solid-core doors
Use extraction when machining MDF, veneer or factory-primed doors
Confirm fire-rated, acoustic or smoke doors are installed strictly to manufacturer certification requirements; do not reduce or modify beyond approved limits
If purchasing new trade tools above $300, review current EOFY instant asset write-off eligibility with your accountant if operating a small business

Step-by-Step Guide

Step 1: Check the opening, jamb condition and door schedule

Confirm the door schedule, handing, swing direction, hardware type and finished floor level before any machining starts. Measure the structural opening and finished jamb opening for width, height, plumb and twist.

On renovation work, inspect the existing jamb for damage, bow, loose legs and out-of-plumb condition. There is little value scribing a new door into a twisted or poorly fixed jamb.

For new work, verify the jamb has been installed square and plumb, with even stops and correct head level. The quality of the final margins depends on the jamb being right first.

💡 If the jamb is more than a few millimetres out of square, correct the jamb rather than trying to force the door leaf to compensate excessively.

Step 2: Establish clearances and mark the door for sizing

Set the target margins based on door type, floor finish and hardware requirements. As a general trade guide for standard internal doors:

Aim for approximately 2 mm to 3 mm clearance at each side stile
Aim for approximately 2 mm to 3 mm at the head
Allow bottom clearance to suit flooring and ventilation, commonly 5 mm to 10 mm over finished floor, or as specified

For carpet, thresholds, hydronic build-up or uneven floors, determine the bottom undercut from the highest point of the finished surface. Mark the door using a knife line or sharp pencil from measured jamb opening dimensions.

If reducing the door significantly, split the reduction across both stiles where practical to keep the lock stile and hinge stile visually balanced, unless one edge is already factory-finished to remain intact.

💡 Always check manufacturer trimming limits on hollow-core, semi-solid and specialty doors before cutting. Exceeding the allowable trim can expose voids or void warranties.

Step 3: Trim the door leaf to size

Place the door on stable trestles and clamp securely. Trim height and width using a track saw or circular saw with guide, keeping cuts clean and square. Use masking tape on veneered faces if needed to reduce breakout.

Plane the edges with a block plane or electric planer to final fit. Slightly ease the arrises so the door does not bind and the paint system finishes neatly.

Where the floor is out of level, scribe the bottom edge to suit the floor line, then cut and plane to the scribed line. Re-seal all freshly cut edges, especially on primed, MDF-faced or veneered doors.

💡 On painted doors, leave enough material for final site tuning after the first test fit. Taking too much off early is a common avoidable error.

Step 4: Set out hinge positions

Mark hinge positions on the door and jamb consistently across the project. Standard practice for a typical internal door is:

Top hinge: approximately 150 mm to 180 mm down from the top of the door
Bottom hinge: approximately 200 mm to 230 mm up from the bottom
Third hinge: centred between top and bottom hinges, or slightly above centre on heavier doors

Transfer the set-out to both the door edge and the jamb. Confirm the hinge gains line through cleanly with existing jamb marks if replacing a door into an existing frame.

Use the same reference points throughout the job so hinge lines remain consistent across adjacent doors. That consistency is noticeable on finished fit-out work.

💡 For solid-core, oversized or high-use commercial-style leaves, step up to 4 hinges and confirm hinge grade suits the weight.

Step 5: Mortice the hinges into the door and jamb

Mark the hinge thickness precisely using a marking knife or gauge. Machine the gains using a trim router with hinge jig for speed and repeatability, then square the corners with a sharp chisel if required.

If working by hand, knife the perimeter first, chisel across the grain in shallow passes, then pare the base flat. The hinge leaf should finish flush with the timber surface, not proud and not sunk.

Dry-fit each hinge and check screw holes align centrally. On hardwood jambs or dense species, pre-drill all screw holes to avoid snapping screws or jacking the hinge out of position.

💡 A hinge leaf buried too deep will pull the margin tight on that side and create latch-side reveal issues. Flush means flush.

Step 6: Hang the door leaf

Fix the hinges to the door first, then stand the leaf in the opening using wedges or a door lifter. Support the door at the correct bottom clearance and align the top margin visually before fixing off to the jamb.

Start with the top hinge using one screw in each leaf to allow minor adjustment, then secure the bottom hinge, then the middle hinge. Open and close the door to assess swing, side clearance and whether the leaf drops or binds.

Once the fit is correct, install the remaining screws. Replace at least one short screw in the top hinge jamb leaf with a longer fixing into solid framing where practical for a more durable install.

💡 The top hinge does most of the work over time. A long screw into framing markedly improves long-term performance.

Step 7: Check margins, swing and make final adjustments

Inspect the reveal around the perimeter. The gap should present consistently when the door is closed, without hinge bind, latch-side pinch or head rub.

If the door binds:

Check whether the jamb is out of plumb
Check hinge gains are too deep or too shallow
Check the leaf needs minor planing on the hinge or lock stile
Check the bottom edge against floor high spots

Make small controlled adjustments only. Plane in fine passes and re-hang as required. Re-seal any trimmed areas immediately after fitting.

On painted work, final stop and fill should be left clean for the painter, with no torn veneer or over-cut hardware gains.

Step 8: Set out and install the latch or lockset

Confirm the backset and spindle height from the hardware specification. A common internal latch centre height is around 900 mm to 1000 mm above finished floor, but match the project standard or existing doors.

Mark the latch centre on the lock stile, bore the face hole with the correct hole saw, then bore the edge for the latch body. Mortice the latch faceplate so it sits flush to the edge.

Fit the latch, handles and privacy snib if required. Close the door against the stop and transfer the latch tongue position onto the jamb for the striker plate. Mortice the striker neatly and test latch engagement.

The latch should engage positively without needing to slam the door or lift the handle. Adjust striker position and depth as required.

💡 On retrofit work, align handle heights with adjacent doors unless directed otherwise by the schedule. Inconsistent hardware heights stand out immediately.

Step 9: Fit stops, seals and final hardware

If using loose door stops, close the door against the latch and fix the stops to achieve an even compression without forcing the leaf out of plane. Keep the stop line visually consistent and avoid over-tight contact that causes rebound.

Install any acoustic seals, drop seals or bottom brushes in accordance with manufacturer details. For bathroom and WC doors, confirm privacy hardware operates freely and emergency release function is accessible where required.

Fit the final door stop to wall or floor position so the handle does not impact adjacent surfaces. Check that floor stops do not create trip hazards in circulation zones.

Step 10: Finish, inspect and hand over

Fill any minor fixing blemishes, sand lightly and touch up primed or clear-finished edges. Lubricate hinges and latch lightly if needed.

Complete a final QA check:

Even margins
Smooth swing without self-opening or self-closing caused by poor plumb
Positive latch action
No floor strike
Clean hardware alignment
No visible breakout, tear-out or damaged arrises

For multi-door jobs, stand back and inspect the line of heads, handles and margins across the elevation. Consistency is the benchmark of professional joinery and finishing carpentry.

What are the common mistakes to avoid when installing internal doors? to Avoid

1.Cutting the door to final size before confirming the jamb is plumb, level and fixed correctly.
2.Allowing insufficient bottom clearance for finished floor coverings, especially carpet or uneven renovation floors.
3.Setting hinge gains too deep or too shallow, which throws off the reveal and causes bind.
4.Using poor-quality screws or failing to pre-drill in hardwood, leading to broken screws and loose hinges.
5.Ignoring manufacturer trim limits on hollow-core, fire-rated or specialty doors.
6.Misaligning latch and striker, resulting in hard closing or handle lift to latch properly.
7.Failing to seal cut edges, especially on MDF or factory-primed doors, which can lead to moisture uptake and swelling.

Pro Tips

1.Use a dedicated hinge routing jig for volume fit-out work. It improves repeatability, speed and finish quality across multiple doors.
2.Keep a consistent hinge set-out template in the ute or workshop so every door on the project matches.
3.On replacement doors in old homes, check the jamb for winding before touching the leaf. Many “bad doors” are actually frame issues.
4.Slightly ease the latch-side arris after final planing to improve closing feel and reduce paint drag.
5.Install one long screw through the top hinge into framing for better long-term support, particularly on solid-core leaves.
6.For painted jobs, prime or seal all fresh cuts the same day to avoid moisture movement and raised fibres.

Recommended Tools

Makita 18V Brushless Drill/Driver Kit — reliable for hinge fixing, latch drilling and general install work
Festool TS 55 Track Saw — accurate trimming of door height and width with clean edges
Mafell or Gainsborough-style Hinge Routing Jig — fast, repeatable hinge mortices across multiple doors
Stanley No. 60 1/2 Block Plane — ideal for controlled edge trimming and easing arrises
Whitco / Sutton Hole Saw Kit — suited to clean lockset and latch boring in common internal door materials

Frequently asked questions

What is involved in install internal doors?
Installing internal doors is a core finishing carpentry task that demands accurate set-out, clean machining and careful adjustment to achieve consistent margins, smooth operation and compliant clearances. On Australian fit-outs and renovation work, the quality of the install is judged on the reveal,
What skill level do I need for install internal doors?
Intermediate — Estimated time: 1.5 to 3 hours per door depending on whether the jamb is existing or new, and whether lockset preparation is included
What are common mistakes when install internal doors?
1. Cutting the door to final size before confirming the jamb is plumb, level and fixed correctly. 2. Allowing insufficient bottom clearance for finished floor coverings, especially carpet or uneven renovation floors. 3. Setting hinge gains too deep or too shallow, which throws off the reveal and causes bind. 4. Using poor-quality screws or failing to pre-drill in hardwood, leading to broken screws
What tools do I need for install internal doors?
This guide includes a comprehensive tools list. Key carpentry & joinery tools are detailed in the Tools Required section.
What is the Australian standard for timber-framed construction relevant to door installation?
The primary Australian standard is AS 1684 Residential Timber-Framed Construction. This standard outlines requirements for framing, including jamb installation and tolerances, ensuring structural integrity and proper door function. Compliance with AS 1684.2:2021 is crucial for residential projects across Australia.
How much clearance is required under an internal door in Australia?
According to the National Construction Code (NCC) and good trade practice, a typical clearance of 10-15mm is allowed under an internal door for airflow and floor covering expansion. This clearance should be measured from the finished floor level to the bottom of the door leaf, ensuring adequate ventilation and preventing drag.
What are the standard internal door sizes in Australia?
Common standard internal door leaf sizes in Australia are 2040 x 820 mm, 2040 x 770 mm, and 2040 x 720 mm. For higher ceilings, 2340 mm high doors are also specified. These dimensions are critical for ordering and ensuring correct fit within standard Australian residential framing.
Why is pre-drilling important for hinge screws in Australian hardwoods?
Pre-drilling is essential when fixing hinge screws into Australian hardwoods like Jarrah or Spotted Gum to prevent screw breakage and timber splitting. According to best practice, the pilot hole diameter should be slightly less than the screw's core diameter, ensuring a strong, secure, and clean fastening.

Written by Chippy, the Carpentry & Joinery specialist at VIC.Tools.