How to install timber subfloor bearers and joists
This guide details the professional installation of timber subfloor bearers and joists, a foundational element for extensions, raised homes, and structures on sloping sites in Australia. Correct execution ensures structural integrity, compliance with AS 1684, and a level, durable base for subsequent
- Skill level
- Intermediate
- Time
- 1-3 days (depending on subfloor size and complexity)
- Trade
- Carpentry & Joinery
- Updated
- 28 November 2026
Tools you will need
- Laser Level: Self
- Tape Measure: 8m or 10m steel tape.
- Chalk Line: For marking layout.
- Impact Driver/Drill: For fastening.
- Framing Nail Gun: Pneumatic or battery
- Spirit Level: 1200mm and 600mm.
- String Line: Heavy
- Claw Hammer: For minor adjustments and nail removal.
- Shovel/Spade: For minor excavation if required.
- Concrete Mixer: Small portable mixer for stump footings.
🪚 Timber Subfloor Bearer and Joist Installation
What is involved in installing timber subfloor bearers and joists?
This guide details the professional installation of timber subfloor bearers and joists, a foundational element for extensions, raised homes, and structures on sloping sites in Australia. Correct execution ensures structural integrity, compliance with AS 1684, and a level, durable base for subsequent flooring. This process involves precise setting out, secure fixing, and adherence to Australian timber framing standards.
What skill level is required for timber subfloor installation?
Intermediate — Estimated time: 1-3 days (depending on subfloor size and complexity)
What tools are essential for timber subfloor bearer and joist installation?
Laser Level: Self-levelling, green beam recommended for visibility over distance. Tape Measure: 8m or 10m steel tape. Chalk Line: For marking layout. Circular Saw: 185mm or 235mm blade, suitable for cutting structural timber. Impact Driver/Drill: For fastening. Framing Nail Gun: Pneumatic or battery-powered, suitable for 90mm nails. Spirit Level: 1200mm and 600mm. Builder's Square/Framing Square: For checking right angles. String Line: Heavy-duty, non-stretch. Claw Hammer: For minor adjustments and nail removal. Shovel/Spade: For minor excavation if required. Post Hole Digger: If concrete stumps are being cast in situ. Concrete Mixer: Small portable mixer for stump footings.What materials are needed for a timber subfloor in Australia?
Bearers: 90x90, 100x100, 120x120, 150x150 or 190x45, 240x45, 290x45 treated pine (H3 or H4 depending on exposure) or hardwood (F17 or F27). Sizes determined by span tables in AS 1684. Joists: 90x45, 140x45, 190x45, 240x45 treated pine (H3) or hardwood (F17 or F27). Sizes determined by span tables in AS 1684. Stumps/Piers: Precast concrete stumps (e.g., 150x150mm or 200x200mm) or formwork for cast-in-situ concrete piers. Ant Caps: Galvanised steel, minimum 0.4mm thick. Bearer Straps/Connectors: Galvanised steel, appropriate for timber size (e.g., Pryda, MiTek). Joist Hangers: Galvanised steel, appropriate for joist size if required. Fasteners: 90mm galvanised nails (for framing gun or hand nailing). 100-150mm galvanised batten screws or coach screws for bearer-to-stump fixing. 35mm galvanised connector nails for straps/hangers. Damp-Proof Course (DPC): Bituminous or polyethylene, 300mm wide. Concrete: 20MPa minimum for stump footings. Packing Shims: Hardwood or plastic, various thicknesses.Safety Requirements
Personal Protective Equipment (PPE): Safety Glasses: Always worn when cutting or fastening. Hearing Protection: Earmuffs or earplugs when using power tools. Steel-Capped Boots: Essential for foot protection. Gloves: For handling timber and concrete. Site Safety: Ensure a clear work area, free from trip hazards. Secure power leads to prevent damage and tripping. Be aware of underground services (dial before you dig). Proper manual handling techniques for heavy timbers. Work safely at heights if applicable (scaffolding or stable platforms). Compliance: All structural timber work must comply with AS 1684 Residential Timber-Framed Construction and local council regulations.Step-by-Step Guide
Step 1: Site Preparation and Set Out
1️⃣ Clear and Level Site: Remove all debris, vegetation, and loose soil. Ensure the ground is reasonably level.
2️⃣ Establish Datum and Boundary Lines: Use a laser level to establish a consistent datum point. Mark out the perimeter of the subfloor using string lines, ensuring they are square and level. Double-check diagonals for squareness.
3️⃣ Mark Stump Locations: Refer to your engineering plans or AS 1684 span tables for bearer and joist spacing. Mark the exact locations for all stumps/piers on the ground.
💡 Pro Tip: Use spray paint to clearly mark stump centres for excavation.
Step 2: Install Stumps/Piers
1️⃣ Excavate Footings: Dig holes for stumps/piers to the required depth and diameter as per engineering specifications or AS 2870 (Residential Slabs and Footings). Ensure adequate bearing capacity.
2️⃣ Pour Footings (if cast-in-situ): Place a layer of compacted aggregate, then pour concrete to the required level. Set stump anchors or cast-in bolts if specified.
3️⃣ Install Precast Stumps: Place DPC on the footing. Position precast concrete stumps, ensuring they are plumb and at the correct height. Use a laser level and string lines to accurately set the top of each stump. Pack with non-shrink grout or concrete if minor adjustments are needed.
4️⃣ Install Ant Caps: Place ant caps on top of each stump, ensuring they are flat and extend beyond the stump on all sides. This creates a visible barrier against termites.
Step 3: Install Bearers
1️⃣ Cut Bearers to Length: Measure and cut bearers to the required lengths, allowing for any overlaps or scarf joints as per AS 1684.
2️⃣ Position Bearers: Lay the bearers on top of the ant caps, aligning them precisely with your set-out lines. Ensure the top edge of each bearer is level across its length and with adjacent bearers using the laser level. Use packing shims under bearers on stumps if minor height adjustments are needed.
3️⃣ Fix Bearers to Stumps: Securely fix bearers to stumps using appropriate galvanised fasteners.
Timber Stumps: Nail or screw directly through the bearer into the stump. Concrete Stumps: Use galvanised bearer straps or coach screws into pre-drilled holes with appropriate anchors. Ensure all fixings comply with AS 1684.4️⃣ Join Bearers: Where bearers require joining, ensure joints occur over a stump. Use a scarf joint or butt joint with a galvanised strap or splice plate, as specified.
Step 4: Install Joists
1️⃣ Mark Joist Layout: Mark the joist centres (typically 450mm or 600mm) on the top edge of the bearers. Start from one end and work across, ensuring consistent spacing.
2️⃣ Cut Joists to Length: Measure and cut joists to span between bearers. Ensure ends are square.
3️⃣ Position Joists: Place joists on edge, aligning them with the marked centres on the bearers. Ensure the crown (natural curve) of the timber is facing upwards.
4️⃣ Fix Joists to Bearers:
Face Nailing: Nail through the top of the joist into the bearer using 90mm galvanised nails (minimum 2 nails per connection). Skew Nailing: Nail through the side of the joist at an angle into the bearer (minimum 2 nails per connection). Joist Hangers: If joists are flush with the top of the bearer or if specified, use galvanised joist hangers fixed with appropriate connector nails.5️⃣ Install Blocking/Nogging: Install blocking or nogging between joists at mid-span or as specified by AS 1684 to prevent joist roll and provide lateral stability. These should be cut to fit snugly and skew-nailed in place.
💡
Pro Tip: Use a joist spacing jig to speed up marking and ensure accuracy.Step 5: Final Checks and Bracing
1️⃣ Check Level and Square: Re-check the entire subfloor for levelness and squareness using your laser level and builder's square. Make any necessary adjustments.
2️⃣ Check Fastenings: Ensure all nails, screws, and connectors are properly installed and secure.
3️⃣ Install Bracing: If required by AS 1684 or engineering plans, install diagonal bracing or other specified bracing elements to provide lateral stability to the subfloor.
Common Mistakes to Avoid
Pro Tips
Pre-Drill Hardwood: When working with hardwoods, pre-drilling pilot holes for screws and nails will prevent splitting and make fastening easier. Laser Level for Efficiency: Invest in a good quality self-levelling laser. It's invaluable for setting stump heights and ensuring a perfectly level subfloor, saving significant time and rework. Order Timber Strategically: Plan your timber lengths to minimise waste. Order longer lengths and cut down, or order specific lengths to suit your spans. Weather Protection: If the subfloor will be exposed for an extended period before flooring, consider covering it with a tarp to protect the timber from excessive wetting and drying cycles. EOFYS Instant Asset Write-Off: Remember to claim eligible tools over $300 under the EOFY instant asset write-off scheme.Recommended Tools
DeWalt DCN692 Framing Nailer: Excellent battery-powered option for cordless convenience and powerful nailing. Bosch GLL 3-80 CG Green Beam Laser Level: Provides highly visible 360-degree lines for precise set-out and levelling. Makita HS7611 Circular Saw: Reliable and robust 185mm circular saw, ideal for structural timber cuts. Pryda Timber Connectors: A trusted brand for a wide range of galvanised steel connectors, ensuring compliance and strength.Frequently asked questions
- What is involved in install timber subfloor bearers and joists?
- This guide details the professional installation of timber subfloor bearers and joists, a foundational element for extensions, raised homes, and structures on sloping sites in Australia. Correct execution ensures structural integrity, compliance with AS 1684, and a level, durable base for subsequent
- What skill level do I need for install timber subfloor bearers and joists?
- Intermediate — Estimated time: 1-3 days (depending on subfloor size and complexity)
- What are common mistakes when install timber subfloor bearers and joists?
- 1. Incorrect Set Out: Failure to achieve a perfectly square and level subfloor from the outset will lead to ongoing issues with flooring and wall framing. 2. Non-Compliant Spans: Using incorrect bearer or joist sizes/spacings for the intended load, leading to structural failure or excessive deflection. Always refer to AS 1684. 3. Inadequate Termite Protection: Skipping ant caps or D
- What tools do I need for install timber subfloor bearers and joists?
- This guide includes a comprehensive tools list. Key carpentry & joinery tools are detailed in the Tools Required section.
- What is involved in installing timber subfloor bearers and joists?
- Installing timber subfloor bearers and joists involves precise setting out, secure fixing, and adherence to Australian timber framing standards, specifically AS 1684. This foundational process ensures structural integrity and provides a level, durable base for subsequent flooring in extensions or raised homes across Australia.
- What skill level is required for timber subfloor installation?
- An intermediate skill level is required for timber subfloor installation. This task typically takes 1-3 days, depending on the subfloor's size and complexity. Tradies should possess a solid understanding of structural carpentry, accurate measurement, and compliance with Australian building codes to ensure a safe and durable outcome.
- What are common mistakes when installing timber subfloor bearers and joists?
- Common mistakes include incorrect set-out leading to unlevel floors, using non-compliant spans for bearers or joists, and inadequate termite protection. According to AS 1684, all structural timber elements must meet specified span tables, and AS 3660.1 mandates appropriate termite management systems for Australian conditions.
- What is the Australian standard for timber subfloor construction?
- The Australian standard for timber subfloor construction is AS 1684, 'Residential timber-framed construction'. This standard requires specific timber sizing, spacing, and fixing methods based on design loads and environmental conditions. For tradies in Queensland, additional requirements for cyclonic regions may apply, as detailed in AS 1684.2:2021.