How to dig a trench for stormwater, power or irrigation

Digging a trench sounds straightforward, but getting the depth, grade, width and service separation right is what makes the job safe and compliant. For Australian homeowners, trenching is commonly needed for stormwater drainage, underground power conduit, irrigation pipework and comms runs,

Skill level
Beginner to Intermediate
Time
4–8 hours for a short hand-dug trench, 1–2 days for longer drainage or multi-service runs
Trade
Earthmoving & Landscaping
Updated
28 November 2026

Tools you will need

  • Shovel
  • Mattock or pick for hard ground and roots
  • Wheelbarrow for spoil removal
  • String line and timber pegs for set
  • Tape measure
  • Spray marker paint for trench alignment
  • Laser level, dumpy level or line level for grade control
  • Spirit level for short checks
  • Hand tamper or plate compactor for backfilling
  • Reciprocating saw or loppers for small roots

🏗️ Trade Guide: How to Dig a Trench for Stormwater, Power or Irrigation

What is involved in trenching for stormwater, power, or irrigation in Australia?

Digging a trench sounds straightforward, but getting the depth, grade, width and service separation right is what makes the job safe and compliant. For Australian homeowners, trenching is commonly needed for stormwater drainage, underground power conduit, irrigation pipework and comms runs, and the best method depends on trench length, access and soil conditions.

Before any excavation, always confirm underground services with 📞 Dial Before You Dig (1100) and check local council or utility requirements. For longer runs, tougher ground or trenches deeper than 600 mm, hiring the right machine can save a full weekend of hard labour.

What skill level is required for digging trenches in Australia?

Beginner to Intermediate — Estimated time: 4–8 hours for a short hand-dug trench, 1–2 days for longer drainage or multi-service runs

What tools are essential for trenching projects in Australia?

Shovel — trenching or long-handle type
Mattock or pick for hard ground and roots
Wheelbarrow for spoil removal
String line and timber pegs for set-out
Tape measure — minimum 5 m
Spray marker paint for trench alignment
Laser level, dumpy level or line level for grade control
Spirit level for short checks
Hand tamper or plate compactor for backfilling
Reciprocating saw or loppers for small roots
Mini excavator — typically 1.7 t to 3.5 t for residential access
Walk-behind trencher for narrow irrigation or conduit trenches
Buckets — 300 mm trench bucket and general-purpose bucket
Conduit draw wire if installing power or comms
PPE:
Safety boots
Hi-vis clothing
Gloves
Safety glasses
Hearing protection
Dust mask where required
Sunscreen and hat

What materials are typically needed for Australian trenching works?

Stormwater pipe — typically 90 mm or 100 mm PVC
Electrical conduit — size to electrician’s specification, commonly 25 mm to 63 mm
Irrigation poly pipe — commonly 19 mm, 25 mm or 32 mm
Bedding sand or fine screened fill
Blue metal drainage aggregate if required for drainage applications
Marker tape for underground services
Warning tape for electrical trenches
Solvent cement and primer for PVC stormwater
Couplings, bends and inspection openings as required
Cable pits or junction boxes if applicable
Geofabric where ground is unstable or drainage design requires it
Water for compaction of suitable fill if needed

Safety Requirements

⚠️ Always contact 📞 Dial Before You Dig (1100) before starting any trenching or excavation.
Confirm locations of gas, water, sewer, stormwater, electricity and communications services.
Do not excavate near known live services with machinery unless positively identified and clearance requirements are met.
Trenches can collapse without warning; take extra care in sandy, wet or filled ground.
Deep or unsupported trenches may require professional advice, shoring or benching.
Keep spoil piles and materials back from trench edges where possible.
For underground power, all cable/conduit work must comply with local regulations and be installed/connected by a licensed electrician.
Check with your local council if the trench crosses a crossover, verge, easement, drainage reserve or asset protection zone.
If working near trees, confirm whether roots are protected by council controls.
Use machinery only on stable ground and follow the hire company’s operating instructions.

Step-by-Step Guide

Step 1: Plan the trench route

1️⃣ Mark the purpose and route

Work out exactly what the trench is for: stormwater, power, irrigation or a combination. This determines the trench depth, width, bedding and separation requirements.

Pick the shortest practical route, but avoid sharp bends, tree roots, retaining wall footings, paved areas and existing services. Keep future access in mind too—especially for stormwater inspection points and electrical pits.

For DIY projects, a good starting point is:

Irrigation: typically 200–300 mm deep
Stormwater: often 300–600 mm or deeper depending on fall and pipe size
Power conduit: depth must be confirmed by your electrician and local authority requirements

💡 Mark changes in direction, connection points and finished invert levels before you touch the soil.

Step 2: Check approvals and underground services

2️⃣ Confirm legal and safety requirements

Before digging, lodge a request with 📞 Dial Before You Dig (1100). Review all plans carefully and physically mark known service corridors on the ground using paint and pegs.

If you’re trenching:

across a front verge
near a council drain
across a driveway crossover
inside an easement
or for mains power upgrades

you may need council, utility or contractor approval.

For electrical runs, the trench can often be dug by a homeowner, but the conduit layout, cable installation and final connection should be directed by a licensed electrician.

Step 3: Set out the trench line and levels

3️⃣ Establish alignment and grade

Set pegs at the start and finish of the trench, then run a string line to mark alignment. For stormwater, this step is critical because the trench must maintain a consistent fall.

As a general guide:

Stormwater pipework should have a steady grade, often around 1:100 to 1:200 depending on pipe size and design
Irrigation lines can usually follow surface contours unless drainage or valve box placement requires otherwise
Power trenches usually need consistent depth rather than drainage fall

Use a laser level for best results. Measure from the string or laser to the trench base as you excavate, not just the natural ground, because ground levels can be misleading.

💡 For drainage, write the required trench bottom depths on each peg so you can check progress quickly as you dig.

Step 4: Choose the best digging method

4️⃣ Pick hand tools or machinery

For short trenches under about 10–15 m in soft soil, hand digging is often fine. For longer runs, clay, rocky ground or repeated projects, machinery makes more sense.

Typical options:

Hand digging: best for short, precise work near services
Walk-behind trencher: ideal for narrow irrigation and conduit trenches
Mini excavator: best for stormwater, deeper trenches and tougher ground
Hire vs buy economics:
For one-off homeowner work, hire is nearly always the best value
A walk-behind trencher or 1.7 t mini excavator can often be hired for a day or weekend far cheaper than ownership costs
Buying only starts to make sense if you trench regularly across multiple jobs each year
For equipment purchases over $20k, finance through Local Knowledge Finance can help spread the cost for small contractors or serious owner-builders

💡 A 300 mm trench bucket on a mini excavator is a great residential all-rounder for drainage and conduit work.

Step 5: Prepare the site

5️⃣ Clear access and protect the work area

Remove surface obstacles like mulch, rocks, pavers, edging and loose garden materials. If crossing lawn, strip and stockpile turf separately so it can be reused neatly later.

Nominate a spoil side and keep excavated soil clear of the trench edge where possible. This improves safety and makes backfilling easier.

If machinery is being used, check:

gate widths
overhead clearances
soft ground
septic areas
retaining walls
underground tanks

Step 6: Start excavating the trench

6️⃣ Dig to width and depth

Begin at the discharge or connection end where practical, especially for stormwater, so levels can be controlled back toward the source. Keep the trench only as wide as needed for the pipe or conduit plus working room.

Typical trench widths:

Irrigation poly: 100–150 mm
Electrical conduit: 150–250 mm
Stormwater pipe: 200–400 mm depending on pipe size and access

Dig in short sections and check depth regularly with a tape and laser. Don’t assume the machine operator’s eye is enough—small errors add up fast over 10 m or more.

Near known or suspected services, stop using machinery and expose by hand.

Step 7: Trim, clean and shape the trench base

7️⃣ Create a proper trench bottom

Once rough depth is reached, clean the bottom of the trench with a shovel. Remove loose clods, rocks, roots and soft spots.

For stormwater, the trench base should be smooth and consistent so the pipe sits evenly along its length. Avoid high and low spots that can create water traps.

Where required, install bedding sand or fine fill under the pipe or conduit. A bedding layer helps protect the service and makes final grading easier.

💡 Don’t lay pipe or conduit directly on sharp rock. Even if it looks solid, point loads can damage the material over time.

Step 8: Install the service

8️⃣ Lay pipe, conduit or irrigation line correctly

Install the material according to its purpose:

Stormwater
Lay pipe to the designed fall
Join PVC with primer and solvent cement
Face sockets upstream where practical
Include inspection openings where needed
Power
Install conduit to the electrician’s direction
Use sweeping bends, not tight elbows, for easier cable pulling
Fit draw wire before backfilling
Maintain required separation from other services
Irrigation
Lay poly pipe with enough slack to avoid tension
Position tees, valves and risers accurately
Pressure test before backfilling where possible

Check the line and levels again before covering anything.

Step 9: Add warning tape and protection layers

9️⃣ Protect the service for the future

Place suitable fine fill or bedding around the service first, especially around stormwater pipe and electrical conduit. Compact lightly by hand around the sides to prevent movement.

Install warning tape above electrical conduit and marker tape for other underground services where appropriate. This helps future excavators identify buried lines before they strike them.

If the trench passes through reactive clay, wet ground or trafficable areas, use better quality backfill and controlled compaction.

Step 10: Backfill and compact in layers

🔟 Reinstate the trench properly

Backfill the trench in layers rather than dumping everything in at once. Compact each layer so the trench doesn’t sink later.

General approach:

First layer: fine fill around the service
Middle layers: suitable excavated spoil if clean and free of rock/rubbish
Top layer: landscape soil, road base or turf underlay depending on finish

Use:

Hand tamper for narrow trenches and around services
Plate compactor for wider trenches and paths
Light compaction only near pipe and conduit to avoid damage

💡 Poor backfilling causes most trench callbacks—especially sunken lawns, dipped paving and broken stormwater grades.

Step 11: Test and inspect before final reinstatement

1️⃣1️⃣ Check the job before closing up completely

Before the final surface is restored:

run water through stormwater lines
confirm no ponding in drainage pipes
check conduit path is clear with draw wire
pressure test irrigation if possible
photograph the trench layout for future reference

Measure offsets from fixed objects like corners, fences or walls and keep a sketch of where the trench runs. This can save major headaches later.

Step 12: Reinstate the surface

1️⃣2️⃣ Finish the area neatly

Replace turf, topsoil, mulch, gravel or paving to match the surrounding area. Where trenches pass under lawns, water the reinstated strip well and expect some minor settlement.

If crossing a path or driveway, use suitable compacted base materials and repair the surface properly so it doesn’t crack or sink.

For visible areas, tidy reinstatement is what makes the whole job look professional.

Common Mistakes to Avoid

1.Digging before checking 📞 Dial Before You Dig (1100) plans and physical service locations.
2.Not allowing enough fall for stormwater, causing standing water or blocked pipes.
3.Making the trench too wide, which increases labour, spoil and backfill settlement.
4.Backfilling without proper compaction, leading to sunken trenches later.
5.Using machinery too close to live or unknown underground services.
6.Laying pipe or conduit on rocky or uneven trench bottoms without bedding.
7.Forgetting warning tape, draw wire or photo records before covering the trench.

Pro Tips

💡 For straight residential runs, a string line plus laser level is faster and more accurate than eyeballing.
💡 If the trench is mostly for irrigation, a walk-behind trencher is often cheaper and cleaner than hiring an excavator.
💡 For mixed work—stormwater plus conduit—a 1.7 t to 2.5 t mini excavator gives the best balance of access and digging power.
💡 Stockpile turf separately from clay spoil so reinstatement is faster and cleaner.
💡 In hard Australian clay, lightly wetting the trench line the day before hand digging can make the job much easier.
💡 If you’re cutting roots, avoid large structural roots near established trees unless an arborist advises it.

Recommended Tools

1.7 t mini excavator with 300 mm trench bucket — ideal for residential stormwater and service trenches
Walk-behind chain trencher — excellent for narrow irrigation and conduit runs
Rotating laser level kit — accurate trench depth and stormwater fall control
Plate compactor, 60–90 kg — reliable trench backfill compaction and surface reinstatement
Trenching shovel and mattock set — best for hand trimming, service spotting and tight-access digging

🔧 Equipment Required

Mini excavator or walk-behind trencher depending on trench size
Trenching shovel and mattock
Laser level or line level
Plate compactor or hand tamper
Wheelbarrow and marking paint
Full PPE: boots, gloves, eye protection, hearing protection, hi-vis

🔧 Recommended Equipment

Kubota U17-3 mini excavator — compact access and strong residential trenching performance
Ditch Witch C16X or similar walk-behind trencher — efficient for irrigation and conduit
Topcon or Spectra laser level kit — dependable grade control
Wacker Neuson plate compactor — solid choice for trench backfill and reinstatement

Frequently asked questions

What is involved in dig a trench for stormwater, power or irrigation?
Digging a trench sounds straightforward, but getting the depth, grade, width and service separation right is what makes the job safe and compliant. For Australian homeowners, trenching is commonly needed for stormwater drainage, underground power conduit, irrigation pipework and comms runs,
What skill level do I need for dig a trench for stormwater, power or irrigation?
Beginner to Intermediate — Estimated time: 4–8 hours for a short hand-dug trench, 1–2 days for longer drainage or multi-service runs
What are common mistakes when dig a trench for stormwater, power or irrigation?
1. Digging before checking 📞 Dial Before You Dig (1100) plans and physical service locations. 2. Not allowing enough fall for stormwater, causing standing water or blocked pipes. 3. Making the trench too wide, which increases labour, spoil and backfill settlement. 4. Backfilling without proper compaction, leading to sunken trenches later. 5. Using machinery too close to live or unknown underg
What tools do I need for dig a trench for stormwater, power or irrigation?
This guide includes a comprehensive tools list. Key earthmoving & landscaping tools are detailed in the Tools Required section.
What is the Australian standard for electrical conduit depth?
The Australian standard for electrical conduit depth is primarily governed by AS/NZS 3000:2018, known as the Wiring Rules. This standard mandates specific minimum depths, such as 450mm under driveways and 300mm in garden beds, to ensure safety and prevent damage. Always consult the latest edition and local supply authority requirements.
How much fall is required for stormwater drainage in Australia?
For effective stormwater drainage in Australia, AS/NZS 3500.3:2021 recommends a minimum fall of 1:100 for pipes. This means for every 100 metres of pipe length, there should be a 1-metre drop in elevation. This grade ensures sufficient flow velocity to prevent blockages and standing water.
What are the safety requirements for trenching in Australia?
Safety requirements for trenching in Australia are outlined by SafeWork Australia's 'Excavation Work' Code of Practice. Key requirements include contacting Dial Before You Dig (1100) before any excavation, ensuring trench stability, providing adequate shoring for depths over 1.5m, and implementing appropriate traffic management plans. PPE, such as safety boots and hi-vis, is mandatory.
What is the maximum depth for hand-dug trenches before shoring is required?
While there's no strict maximum depth for hand-dug trenches, SafeWork Australia's 'Excavation Work' Code of Practice strongly recommends shoring or benching for trenches exceeding 1.5 metres in depth, or where ground conditions are unstable. For shallower trenches, a risk assessment must still be conducted to ensure worker safety from collapse.

Written by Digger, the Earthmoving & Landscaping specialist at VIC.Tools.