How to divert stormwater away from house foundations

Divert stormwater away from house foundations using surface grading, ag pipe, and 90mm PVC to prevent slab heave. Compliant with AS/NZS 3500.3 drainage standards.

Quick answer

Diverting stormwater away from house foundations requires grading surrounding ground away from slabs by fifty millimetres over one metre, then capturing surface and subsoil runoff using solid ninety-millimetre PVC pipes laid at a one-to-one-hundred fall. Water must safely terminate at an approved council legal point of discharge under AS/NZS 3500.3.

Skill level
Intermediate
Time
1–3 days for a typical small residential drainage diversion, depending on trench length, soil type, and access
Trade
Earthmoving & Landscaping
Updated
28 November 2026

Tools you will need

  • Kubota U17-3 - 1.7t Mini Excavator
  • Wacker Neuson VP1135A - Single Direction Plate Compactor
  • Topcon RL-H5A - Horizontal Rotating Laser Level
  • Stihl TS 420 - 350mm Cut-Off Concrete & Pipe Saw
  • Cyclone Square Mouth - Post Hole and Trenching Shovel
  • Reln 100mm x 20m - Slotted Ag Pipe with Filter Sock
  • Holman 90mm x 6m - 100D Stormwater PVC Pipe SN2

🏗️ Trade Guide: How to divert stormwater away from house foundations

Why is diverting stormwater away from house foundations important in Australia?

Diverting stormwater away from house foundations is about collecting water before it ponds against walls or slabs, then moving it safely to a legal discharge point such as a stormwater line, kerb outlet, rain garden, or approved soakage system. Done properly, this helps reduce slab movement, damp problems, erosion, and long-term structural damage.

For Australian homes, the most effective fix is usually a combination of surface grading, spoon or channel drains, and subsurface stormwater pipes installed to a consistent fall. This guide covers a practical DIY approach for common pooling issues after heavy rain, while flagging where licensed trades or council approval may be required.

What skill level is required for diverting stormwater from foundations?

Intermediate — Estimated time: 1–3 days for a typical small residential drainage diversion, depending on trench length, soil type, and access

What tools are essential for stormwater diversion projects?

🔧 Equipment Required
Shovel, trenching shovel, mattock, and rake
Wheelbarrow for spoil removal
String line, pegs, tape measure, and marking paint
Spirit level with straightedge or laser level for setting falls
Mini excavator 1.7t–2.5t for trenches over 10–15 m or hard ground
Plate compactor 60–90 kg for backfill and surface reinstatement
Brick saw or angle grinder with masonry blade if cutting paving or concrete edges
PVC pipe cutter or handsaw
Drill/driver and screwdriver set for drain grates and fittings
Garden hose for testing flow before backfilling
Optional trench pump or wet/dry vac if working in saturated ground
Geotextile scissors or utility knife
PPE:
Steel-cap boots
Hi-vis clothing
Gloves
Safety glasses
Hearing protection
P2 dust mask when cutting concrete or handling dusty soils
Sunscreen and hat for outdoor work

What materials are needed for a typical stormwater diversion system?

90 mm or 100 mm stormwater PVC pipe, quantity to suit trench run
PVC fittings: bends, couplings, tees, inspection openings as required
Surface drain:
Polymer channel drain, or
Spoon drain, or
Strip drain/grated pit depending on runoff source
Agricultural drain (ag pipe) 100 mm only if dealing with subsurface seepage behind landscaping, not as the main stormwater line beside foundations
Drainage gravel 10–20 mm if using ag pipe or creating a gravel interceptor
Geotextile filter fabric for wrapping gravel trenches
Pit(s) 300 x 300 mm or 450 x 450 mm if collecting downpipes or surface runoff
Sand or fine bedding material for pipe base where required
Backfill material:
Reusable clean excavated soil, or
Imported fill if existing soil is too wet or unsuitable
Turf underlay/topsoil and turf seed or rolls for reinstatement
Concrete or pavers if reinstating hardstand areas
Silicone or stormwater sealant where specified by fitting manufacturer
Optional:
Downpipe adaptors
Pop-up emitter if permitted and suitable
Soakwell or infiltration pit if approved by council and soil conditions allow

Safety Requirements

⚠️ Safety
📞 Dial Before You Dig (1100) before any excavation, even for shallow trenches. Underground gas, power, NBN, sewer, and water services may run near the house.
Do not undermine footings, slab edges, or piers. Keep excavation clear of structural supports unless a qualified engineer or builder advises otherwise.
Check local council and water authority requirements before connecting to stormwater mains, kerb outlets, easements, or legal points of discharge.
In many Australian jurisdictions, stormwater connection work may need to be done or certified by a licensed plumber/drainer under AS/NZS 3500.3 and local plumbing regulations.
Use safe trenching practices. Avoid leaving open trenches unattended. Shore or batter unstable excavations where needed, especially in wet or sandy soils.
Keep spoil heaps back from trench edges to reduce collapse risk.
Do not discharge stormwater onto neighbouring property.
If cutting concrete or pavers, control dust and wear eye, hearing, and respiratory protection.
If water ingress is entering internal walls, subfloor spaces, or causing foundation movement, get a licensed drainage contractor, builder, or structural engineer involved promptly.

Step-by-Step Guide

Step 1: Identify where the water is coming from

1️⃣ Assess the water source before digging anything.

Watch the area during rain if possible, or use a hose to simulate runoff. You want to know whether the problem is:

Roof water overflowing from gutters or downpipes
Surface runoff from paving, paths, or driveways falling toward the house
Garden beds built too high against brickwork or slab edges
Subsurface seepage moving through soil toward the footing
Blocked or undersized existing stormwater lines

Mark the low points where water ponds and note the highest points where runoff starts. Also check whether the water is sitting against:

Brick veneer weep holes
The slab edge
Timber subfloor vents
Retaining walls close to the dwelling

If the issue is simply one downpipe overflowing, the fix may be as simple as clearing gutters and adding a new stormwater line. If the whole yard falls toward the house, you will usually need a combination of regrading and drainage.

Step 2: Confirm your legal discharge point

2️⃣ Work out where the water can legally and practically go.

Good drainage only works if the collected water has somewhere to discharge. Common options in Australia are:

Existing stormwater pipe connected to council system
Kerb outlet, where permitted
On-site soakwell or infiltration pit, where permitted and suitable for the soil
Rain garden or detention area approved for overflow control
A lower section of your own block that drains away safely

Do not run stormwater onto the neighbour’s land or let it pond at the boundary.

Check with council about:

Kerb connections
Stormwater discharge approvals
Soakwells/infiltration systems
Works near easements
Heritage or strata restrictions

💡 If you are unsure whether your existing line is stormwater or sewer, stop and have it identified by a licensed plumber. Never connect stormwater into sewer.

Step 3: Choose the right drainage method

3️⃣ Match the solution to the actual problem.

For most homeowners, the best drainage strategy falls into one or more of these categories:

A. Regrade the ground away from the house

This is the first and cheapest fix. Finished ground should generally fall away from the house by at least 50 mm over the first 1 m, and ideally 100 mm over 2–3 m where site conditions allow.

B. Install a surface drain

Use a channel drain, spoon drain, or grated pit where hard surfaces or concentrated runoff send water toward the wall. This is ideal at:

Patio edges
Garage thresholds
Pathways beside the house
Bottom of sloping paving
C. Install a stormwater pipe to carry collected water away

A solid PVC stormwater line 90 mm or 100 mm is the standard solution for moving water from pits or drains to the discharge point. Aim for a minimum fall of around 1:100 where possible, with 1:200 sometimes workable on short runs if levels are tight and workmanship is accurate.

D. Install an interceptor or ag drain for seepage

Use an ag drain only where groundwater or subsurface seepage is the problem, such as behind a retaining edge or along a cut slope. It is not the best primary drain for roof or surface runoff beside a house.

E. Lower garden beds or remove built-up soil

If mulch, soil, or paving is bridging weep holes or sitting too high against the slab, lowering those levels may solve the issue without extensive drainage.

Step 4: Set out levels and trench line

4️⃣ Get the fall right before you start excavation.

Use a laser level or string line to mark:

Drain inlet height
Pipe trench route
Pit locations
Final outlet height

For solid stormwater pipe, keep a steady fall of about:

1:100 preferred for reliability
Absolute minimums depend on pipe size and local regulations, so follow AS/NZS 3500.3 and local plumbing requirements

For example:

A 10 m run at 1:100 needs 100 mm of fall from start to finish

Mark trench width to suit the pipe and working room. A trench around 200–300 mm wide is common for a 90–100 mm stormwater pipe in a residential yard.

💡 Beginners often dig first and try to fix levels later. That usually leads to flat spots that hold water. Set the levels before the excavator or shovel goes in.

Step 5: Excavate carefully and protect the foundations

5️⃣ Dig the trench without disturbing the footing zone.

Before excavation, confirm again that you have completed 📞 Dial Before You Dig (1100) checks.

Excavate the trench along your marked line, keeping enough clearance from the house footing. Do not dig under the slab edge or strip footing. If the trench must run close to the house, keep it shallow and controlled, and stop if you expose footing material or create undermining.

Typical trench depth for a small residential stormwater line may be:

200–450 mm for a shallow yard run
Deeper where needed to maintain fall to the outlet

If you hit:

Rock: consider a hydraulic breaker attachment or rerouting
Wet collapsing soil: widen, batter back, or stop and reassess
Existing pipes/cables: expose by hand and protect them
Hire vs buy economics:

For a one-off DIY job, hiring a 1.7t–2.5t mini excavator for a day is usually far cheaper than buying. Buying only makes sense if you have repeated projects or a small business workload. If you are considering machinery over $20,000, equipment finance through Ding Financial can help spread the cost.

Step 6: Install pits, channel drains, or spoon drains where water collects

6️⃣ Capture the water before it reaches the wall.

Install a surface collection point at the low spot causing the problem. Common setups include:

Channel drain beside paving or slab

Place the top of the grate slightly below the finished surface so water enters easily, typically by 3–5 mm. Concrete or bed it securely so it does not rock or settle.

Grated pit under downpipe or at low corner

Use a 300 x 300 mm pit for small areas, or larger if multiple inflows are collected. Fit a leaf basket if collecting roof water.

Spoon drain in lawn or garden edge

Useful where you need to intercept shallow sheet flow without a full grated trench drain.

Keep drains clear of weep holes and maintain ventilation gaps in brick veneer construction.

Step 7: Lay the stormwater pipe to the correct fall

7️⃣ Use solid pipe for carrying water away.

Lay 90 mm or 100 mm PVC stormwater pipe on a firm base, checking each section with your laser or level. Avoid backfalls, bellies, or too many tight bends.

Best practice:

Use long, smooth runs
Minimise sharp changes in direction
Install inspection openings where future cleaning may be needed
Bed the pipe evenly so it is fully supported
Keep joints clean and properly fitted

If using an ag drain for seepage interception:

Lay it with the slots oriented as per manufacturer guidance
Surround with clean 10–20 mm drainage gravel
Wrap the gravel envelope with geotextile to reduce sediment clogging
Connect the ag drain to a proper discharge point, not just a dead-end trench

💡 Solid PVC pipe is better than corrugated flex pipe for most residential stormwater diversion jobs because it holds grade better and is less likely to sag or clog.

Step 8: Regrade surrounding ground so water sheds away from the house

8️⃣ Drainage pipe alone is not enough if the surface still falls back to the wall.

Once the pipe is in, shape the surrounding soil so rainfall naturally runs away from the house. As a practical target:

Achieve at least 50 mm fall over 1 m away from the foundation
Maintain a clear gap below weep holes
Keep mulch and garden beds from building up against the wall

For paved areas:

Reset or relay pavers to a fall away from the dwelling
Concrete paths should fall away at roughly 1:80 to 1:100, depending on the surface and use

This surface grading step is often what makes the whole system effective. Even a perfect pipe run will struggle if the yard still funnels water to the slab edge.

Step 9: Test the system before backfilling

9️⃣ Run water through everything while it is still exposed.

Use a garden hose to test:

Each pit and drain inlet
The pipe fall
The outlet performance
Any joins or adaptors

Watch for:

Water sitting in the drain
Slow movement through the pipe
Leaks at fittings
Overflow at pits
Water escaping near the house instead of at the outlet

If you find ponding, fix it now. Lift and reset the pipe or adjust the bedding. This is far easier before backfill and reinstatement.

Step 10: Backfill, compact, and reinstate properly

🔟 Finish the job so the drain keeps working long term.

Backfill in layers and compact gently, especially around pits and pipe sides. Do not dump large rocks or demolition rubble onto the pipe.

Reinstate:

Lawn with topsoil and turf/seed
Garden beds with controlled mulch depth
Paving with proper bedding and edge restraint
Concrete surfaces if drains were installed through a path or slab edge

Use the plate compactor on suitable areas to reduce future settlement. Around fragile pipe, use controlled hand compaction first.

Hire vs buy economics:

A plate compactor is almost always a hire item for homeowners unless you do regular paving or landscaping work. For trade or repeated use, ownership can stack up, but for occasional jobs, hire is more cost-effective.

Step 11: Maintain the drainage so the problem does not return

1️⃣1️⃣ A good drainage system still needs periodic checks.

After the next heavy rain, inspect:

Whether water still ponds near the wall
Whether pits are catching sediment or leaves
Whether the outlet is free-flowing
Whether soil has settled and created a new low spot

Ongoing maintenance:

Clean gutters and downpipes
Remove leaves from grates and pits
Flush inspection openings if flow slows
Top up low spots with compacted fill
Keep garden edging and mulch from redirecting water back toward the house

Common Mistakes to Avoid

1.Installing a drain with insufficient fall

Flat pipes or low spots trap water and sediment, leading to recurring blockages.

2.Using ag pipe as the main stormwater line

Ag pipe is for seepage interception, not for carrying concentrated roof or surface water long distances beside a house.

3.Draining to nowhere

A drain must connect to a legal and functional discharge point. A trench full of gravel alone is not a reliable solution in heavy rain.

4.Leaving ground levels too high against the house

Soil, mulch, paving, or gravel built up over weep holes or slab edges can worsen damp and drainage issues.

5.Excavating too close to foundations without planning

Undermining the footing or slab edge can create structural risk and turn a drainage repair into a major building problem.

Pro Tips

💡 Start with the cheapest fix first: Clean gutters, extend downpipes, and regrade surface levels before installing more complex drainage.
💡 Use a laser level if possible: It is the quickest way for DIYers to avoid drainage falls that look right but do not actually work.
💡 Capture water early: A channel drain at the top of the problem area is usually more effective than trying to dry out the bottom after water has already reached the wall.
💡 Keep inspection access: Add an inspection opening or accessible pit on longer runs so future blockages can be cleared without digging up the yard.
💡 Do not ignore repeated ponding near slabs: Ongoing wetting and drying around reactive clay sites can contribute to movement. If cracks are appearing, get building advice as well as drainage advice.

Recommended Tools

1.7t mini excavator with 300 mm trench bucket — ideal for narrow residential stormwater trenches with good access
Rotary laser level kit — essential for setting accurate pipe falls and surface grades
90 kg plate compactor — suitable for compacting trench backfill and reinstated paving base
300 x 300 mm polymer stormwater pit with galvanised grate — good for collecting surface water near paths and downpipes
100 mm PVC stormwater pipe and fittings pack — durable, smooth-bore option for reliable residential drainage runs

If you are pricing up regular-use machinery such as a mini excavator, track loader, or commercial compaction gear over $20,000, finance through Ding Financial is worth considering instead of tying up cash in a one-off purchase.

Frequently asked questions

What is the Australian standard for residential stormwater drainage?
AS/NZS 3500.3:2021 Plumbing and Drainage — Stormwater Drainage regulates all residential surface and subsoil water disposal. It specifies pipe sizing, bedding materials, and minimum gradient falls. It mandates that surface water must discharge to an approved legal point of discharge, such as council kerb infrastructure or an on-site detention system.
What is the minimum fall required for stormwater pipes in Australia?
The minimum fall for 90mm and 100mm residential stormwater pipes is 1:100, which equals a 10mm drop per metre of pipe run. This gradient ensures self-cleansing velocity to prevent silt accumulation. Surface ground levels around concrete slabs must fall at least 50mm over the first metre under the National Construction Code.
Can you use slotted ag pipe for roof stormwater runoff?
No, slotted ag-pipe must never connect directly to downpipes or receive concentrated roof runoff. Ag-pipe is designed solely for subsurface groundwater seepage. Discharging concentrated roof water into slotted pipe saturates the soil directly beside footings, which promotes reactive clay foundation movement and concrete slab heave under AS 2870.
What is the difference between surface drainage and subsoil drainage?
Surface drainage collects overland sheet flow using swales, spoon drains, and grated channel pits before it ponds against footings. Subsoil drainage uses slotted pipe encased in aggregate and geotextile fabric to lower the underground water table. Diverting water from foundations typically requires both systems working in conjunction to protect structural footings.
Do I need council approval to alter stormwater drainage on my property?
Council approval is generally not required for internal repairs, but connecting into council street kerbs or main infrastructure requires a road opening permit. Any alteration to designated drainage easements, overland flow paths, or works that discharge excess water onto neighbouring allotments breaches local council bylaws and civil water law across all states.
How far should downpipes discharge away from house footings?
Downpipes must discharge to a sealed solid PVC line and terminate at an approved legal point at least several metres from footings. According to CSIRO guidelines and AS 2870, saturated ground within 1.5 to 3 metres of concrete footings triggers differential soil movement, causing masonry cracking and structural failure.

Written by Digger, the Earthmoving & Landscaping specialist at VIC.Tools.