How to install artificial grass on a properly prepared base

Learn how to install artificial grass on a prepared base. Excavate 100mm, compact crushed rock, screed crusher dust, and pin synthetic turf correctly.

Quick answer

To install artificial grass correctly, excavate 100 millimetres of organic soil and compact an 80 millimetre layer of Class 2 crushed rock. Screed 20 millimetres of crusher dust, lay turf with fibres facing the primary viewing angle, secure perimeter seams with 150 millimetre galvanised turf pins, and brush in kiln-dried silica sand.

Skill level
Intermediate
Time
1–3 days for 20–50 m², depending on access, excavation depth, and edge preparation
Trade
Earthmoving & Landscaping
Updated
28 November 2026

Tools you will need

  • Wacker Neuson DPU2550 - 60kg Reversible Plate Compactor
  • Stabila R-Type 2000mm - Box Beam Spirit Level
  • OX Pro Heavy Duty - 2400mm Aluminium Screed Bar
  • Tajima LC-650 - Utility Knife with Heavy Duty Hook Blades
  • Makita DUX60Z 36V - Cordless Power Broom Sweeper
  • Cyclone Square Mouth - Post Hole and Landscaping Shovel
  • Selleys Turfmaster - Polyurethane Artificial Turf Adhesive
  • True Temper 100L - Heavy Duty Poly Tray Wheelbarrow

🏗️ Installing Artificial Grass on a Properly Prepared Base

What is involved in installing artificial grass on a properly prepared base?

Artificial grass only performs as well as the base underneath it. A properly prepared base gives you a surface that drains well, stays flat, feels firm underfoot, and avoids the common DIY problems of sinking, wrinkles, edge lift, and weed growth.

For Australian conditions, the key is removing organic soil, installing a compacted road base and bedding layer, then laying and securing the turf with correct falls and drainage. This guide covers a reliable residential method suited to most backyards, side paths, courtyards, and entertaining areas.

What skill level is required to install artificial grass in Australia?

Intermediate — Estimated time: 1–3 days for 20–50 m², depending on access, excavation depth, and edge preparation

What essential tools are needed for artificial grass installation?

Tape measure, marking paint, string line and pegs
Shovel, rake and wheelbarrow
Turf cutter or mattock for existing lawn removal
Plate compactor, minimum 60–90 kg
Screed rails/pipes and screed board
Spirit level or laser level for setting falls
Utility knife with hook blades
Stiff broom or power broom
Joining tape and adhesive applicator
Hammer or mallet
Garden roller or hand tamper for final settling
Optional: mini loader or 1.7t–2.5t mini excavator for larger areas
Optional: vibrating plate with rubber mat for pavers/edge restraint zones
PPE: gloves, eye protection, hearing protection, dust mask/P2 respirator, steel-cap boots, knee pads, high-vis clothing, sunscreen

What materials are required for a durable artificial grass base?

Artificial grass, allowing an extra 5–10% for trimming and joins
Compacted road base or crushed rock, typically 75–100 mm depth
Bedding layer of crusher dust, granite dust, or synthetic turf underlay base, typically 10–20 mm
Geotextile weed mat if required for separation and weed suppression
Edge restraints: treated timber, aluminium edging, steel edging, concrete mowing strip, or existing hard edge
Galvanised turf pins/spikes, typically 150–200 mm
Joining tape and outdoor-grade synthetic turf adhesive
Infill sand if specified by turf manufacturer, typically kiln-dried silica sand
Drainage aggregate and ag pipe if site has poor drainage
Treated timber or concrete for minor retaining/edge support where needed

Safety Requirements

⚠️ Safety — 📞 Dial Before You Dig (1100) before any excavation to locate underground services such as power, gas, water, communications, and sewer.
Wear full PPE including gloves, boots, eye and hearing protection when cutting, compacting, or using powered equipment.
Use safe manual handling practices when moving base materials; road base and turf rolls are heavy.
Operate compactors and cutters in accordance with manufacturer instructions.
Take care with utility knives; always cut away from your body and change blades regularly.
If using a mini excavator, only operate within your competency and keep bystanders clear.
Check local council requirements if altering drainage, levels near boundaries, or installing works over easements.
Ensure stormwater runoff is not redirected onto neighbouring properties.

Step-by-Step Guide

Step 1: Plan the area and confirm drainage

1️⃣ Set out the job

Measure the area accurately and sketch the layout, including joins, edges, access points, pits, and nearby structures. Artificial grass should be laid so joins are minimised and pile direction is consistent across the whole area.

Check how water currently behaves in the space. The finished surface should generally fall at around 1–2% away from buildings where possible, which equals 10–20 mm per metre. On small flat courtyards, even a subtle fall is important to prevent ponding.

If the site is at the base of a slope, holds water after rain, or has heavy clay, allow for additional drainage such as a strip drain, soakage trench, or ag pipe connected to legal stormwater discharge.

💡 Mark your finished height before you start digging. Remember to allow for the turf thickness, typically 30–40 mm, plus the bedding layer and compacted base.

Step 2: Excavate to the correct depth

2️⃣ Remove grass, roots and soft soil

Strip off existing turf, weeds, roots, mulch, and all organic material. Organic matter left under synthetic grass will decompose and create voids, soft spots, and unevenness later.

Typical excavation depth for a standard domestic installation is:

100–130 mm total for pedestrian areas on stable ground
125–150 mm if the soil is soft, reactive, or drainage is poor

This usually allows for:

75–100 mm compacted road base
10–20 mm screeded bedding layer
30–40 mm artificial grass thickness

Trim the subgrade so it is neat and already roughly following the intended fall. Remove all loose material before placing base.

For areas over 30 m², or where access allows, hiring a 1.7t–2.5t mini excavator and small dumper or loader is often more economical than hand excavation. Buying generally only makes sense if you are regularly doing landscape works; for equipment over $20k, finance through Local Knowledge Finance can be worth considering.

Step 3: Install edging and drainage provisions

3️⃣ Lock in the perimeter first

Artificial turf needs firm edge restraint so it stays tight and secure. Install edging before final base prep where possible. Suitable options include:

Aluminium turf edging
Steel garden edging
Treated timber fixed securely
Existing concrete path or paved edge
Concrete mowing strip

Set edging to finished height, allowing for the turf thickness so the grass sits just proud or flush, depending on the look you want.

If drainage is questionable, now is the time to install it. A simple solution is an ag pipe laid at the low side of the area in free-draining aggregate, wrapped in geotextile where required. Maintain a minimum drainage fall of around 1% or 10 mm per metre where practical.

⚠️ Avoid trapping water between the synthetic turf area and surrounding hardscape. Water must have a path out.

Step 4: Prepare and compact the subgrade

4️⃣ Create a firm foundation

Once excavation is complete, compact the natural subgrade using a plate compactor. This step is often skipped by DIYers, but it is critical.

If the subgrade is very soft, wet, or pumping underfoot, remove more material and stabilise with additional compacted crushed rock. Do not build on mud or saturated soil.

Lay geotextile separation fabric if the site is clayey, prone to contamination from soil pumping into the base, or if weed suppression is needed. Overlap joins by at least 150–300 mm.

💡 A stable subgrade means the base layer can do its job. If the ground still moves after compaction, fix that first rather than hoping the top layers will hide it.

Step 5: Install the compacted road base

5️⃣ Build the structural layer

Spread road base or crushed rock in layers, not all at once. Compact in lifts of about 50 mm loose thickness until you achieve a total compacted depth of 75–100 mm for most residential foot traffic areas.

Use a plate compactor and make multiple passes in alternating directions. Moisture content matters: slightly damp base compacts better than bone-dry dusty material.

Check levels regularly with a laser level, string line, or straightedge. Maintain your target fall of 10–20 mm per metre.

The finished compacted base should be:

Hard and stable underfoot
Even, with no low spots
Consistent in fall
Slightly below final level to allow for the screed layer and turf

For areas used only by pedestrians, 75 mm compacted base is usually adequate on good ground. For higher-use zones, pet areas, or softer sites, go closer to 100 mm.

Step 6: Screed the bedding layer

6️⃣ Get the surface smooth and true

Install a fine screed layer of crusher dust, granite dust, or a turf-specific bedding material over the compacted base at about 10–20 mm. This is the layer that lets you achieve a smooth final finish.

Use screed rails and a straightedge to strike off the material evenly. Do not leave humps, footprints, or loose patches. Lightly compact or settle the surface as required, but do not overwork it into waves.

This layer should be smooth enough that any imperfections are minor. Artificial grass will not hide major base defects; if anything, it can make them more obvious in certain light.

💡 Stand back and inspect from multiple angles, especially in late afternoon light. Surface ripples show up best then.

Step 7: Roll out and position the artificial grass

7️⃣ Allow the turf to relax

Roll out the artificial grass over the prepared base and position it with the pile all running in the same direction. Leave a small margin around edges for trimming.

Let the turf relax in the sun for at least 1–2 hours where possible. This helps reduce ripples and makes trimming and joining easier in warm Australian conditions.

If using multiple pieces, make sure the pile direction matches. Dry-fit all sections before any cutting or joining.

Avoid dragging the backing across rough surfaces or sharp edges that could damage it.

Step 8: Trim, join and secure the turf

8️⃣ Make the installation neat and tight

Trim edges from the underside using a sharp utility knife. Take small cuts and follow stitch lines where possible for cleaner edges.

For joins:

Fold back both edges
Trim carefully so the gap is tight without overlapping
Lay joining tape centred under the seam
Apply outdoor-grade turf adhesive as per manufacturer instructions
Bring both sides together neatly with the fibres upright, not trapped in glue

Weight the join lightly while curing if recommended.

Secure the perimeter using galvanised turf pins or spikes at roughly 200–300 mm centres, depending on edge type and wind exposure. Drive them flush and hide them within the fibres.

Where fixed to timber edging, screws with washers or manufacturer-approved fixing methods may be used instead of pins.

⚠️ Do not stretch the turf excessively to “pull out” wrinkles. Position it naturally and work methodically from one side.

Step 9: Apply infill and groom the surface

9️⃣ Finish for performance and appearance

If your chosen turf requires infill, spread kiln-dried silica sand evenly at the manufacturer’s recommended rate. This helps support the fibres, improve ballast, and keep the turf sitting properly.

Brush the turf upright with a stiff broom or power broom so the sand settles down into the pile. Apply in light passes rather than dumping it in one spot.

Groom the surface until:

Fibres are standing up evenly
Infill is distributed consistently
Seams are visually blended
No loose debris remains

Not all products require infill, so always follow the turf supplier’s specification.

Step 10: Final checks and ongoing maintenance

🔟 Inspect the job properly

Walk the entire area and check for:

Soft spots
Visible seams
Loose edges
Ponding points
Low corners
Exposed pins
Uneven pile direction

Lightly hose the surface to test drainage. Water should move freely without pooling for long periods.

Maintenance is straightforward but still necessary. Brush high-traffic areas occasionally, remove leaves and debris, rinse pet areas, and top up infill if needed over time.

💡 Artificial grass is low-maintenance, not no-maintenance. A quick tidy every few weeks keeps it looking far better long term.

Common Mistakes to Avoid

1.Excavating too shallow and trying to save on base materials, which leads to movement and low spots.
2.Laying turf directly over soil, old grass, or poorly compacted fill.
3.Ignoring drainage and leaving the finished area dead flat with no fall.
4.Skipping edge restraints, causing the turf to creep, curl, or lift.
5.Making poor joins with mismatched pile direction or visible seam gaps.
6.Failing to compact road base in layers, resulting in settlement after the first few months.
7.Using the wrong infill or too much adhesive, which can affect appearance and drainage.

Pro Tips

Use a laser level for anything over 20 m². It makes drainage and finished levels much more accurate than eyeballing.
In hot weather, lay and trim turf once it has warmed and relaxed; it handles better and sits flatter.
For narrow side access jobs, hiring a compact 1.7t mini excavator and plate compactor is usually cheaper than buying, unless you do repeated projects. If stepping up to ownership of machinery over $20k, look at Local Knowledge Finance.
Choose a turf product with a realistic pile height for the intended use. Around 30–35 mm often works well for family backyards because it balances appearance and practicality.
On reactive clay sites, spend extra time on drainage and subgrade stability. That investment matters more than buying a premium turf if the base is poor.

Recommended Tools

Wacker Neuson VP plate compactor — reliable compaction for base and subgrade
Stihl TS or quality utility knife system with hook blades — cleaner trimming and edge finishing
Laser level kit — essential for setting correct falls of 10–20 mm per metre
1.7t–2.5t mini excavator hire — ideal for faster excavation on larger areas
Power broom — helps lift fibres and evenly distribute infill for a professional finish

Frequently asked questions

What base is required for installing artificial grass?
A stable synthetic turf installation requires a compacted 75 to 100 millimetre sub-base of Class 2 crushed rock or road base, topped with a 15 to 25 millimetre bedding layer of crusher dust. This dual-layer system provides structural stability underfoot, prevents settling, and guarantees permeable drainage in heavy Australian downpours.
How deep should you excavate before laying artificial grass?
Excavate the site to a total depth of 100 to 120 millimetres below the finished surface height. This allows for a 75 to 80 millimetre compacted road base layer, a 20 millimetre screeded crusher dust layer, and the artificial grass backing. Ensure excavation includes a 1:100 fall away from building foundations.
Do you need weed mat under artificial turf?
Lay commercial-grade woven geotextile weed mat directly over the excavated subgrade before adding road base, or place it directly beneath the turf. Placing geotextile fabric at the subgrade level prevents native soil migration into your crushed rock while suppressing weed growth and maintaining sub-surface water permeability in clay soils.
How do you secure the edges and joins of artificial grass?
Secure artificial grass joins using outdoor synthetic turf joining tape and wet-pour polyurethane adhesive, pressing seams firmly with a heavy roller. Fasten edges every 200 to 300 millimetres using 150 millimetre galvanised U-pins, or screw the turf directly into treated pine perimeter timber edging buried flush with surrounding soil.
Why do you need silica sand infill on artificial grass?
Spread washed, dried Australian silica sand infill across the turf at 10 to 15 kilograms per square metre using a drop spreader. Sand infill weighs the turf down against wind lift, keeps the synthetic yarn fibres standing vertically, protects the backing from UV degradation, and absorbs surface foot-traffic heat.