How to level ground for a trampoline or kids' play area
Level ground for a trampoline or kids' play area safely in Australia. Learn about DGB20 base material, compaction methods, and AS 4685.0:2017 safety principles for a stable, well-drained surface.
- Skill level
- Beginner to Intermediate
- Time
- 4–8 hours for a small trampoline pad, 1–2 days for a larger play area or sites with more than 100 mm of fall.
- Trade
- Earthmoving & Landscaping
- Updated
- 28 November 2026
Tools you will need
- Spectra Precision LL100N - Laser Level Kit
- Stanley FatMax 8m - Tape Measure
- Cyclone 636100 - Square Mouth Shovel
- Bailey 10L - Wheelbarrow
- Wacker Neuson BS50-2 - Plate Compactor (approx. 60kg)
- Trojan - Hand Tamper
- Screed Bar 2.4m - Aluminium Straight Edge
- Makita DHR242Z - Rotary Hammer Drill (for pegging)
- Bunnings Timber Pegs - 450mm x 45mm
🏗️ Trade Guide: How to level ground for a trampoline or kids' play area
Why is proper ground levelling crucial for trampolines and play areas?
Levelling ground for a trampoline or kids’ play area is a straightforward earthworks job when you plan the site properly, control drainage, and compact the base in layers. The goal is to create a firm, flat, and well-drained surface so the equipment sits safely, doesn’t rock, and won’t turn into a muddy low spot after summer storms.
What skill level and time commitment are required for levelling ground?
Beginner to Intermediate — Estimated time: 4–8 hours for a small trampoline pad, 1–2 days for a larger play area or sites with more than 100 mm of fall.What essential tools are needed for levelling ground for play equipment?
What are the recommended base materials for a trampoline or play area?
Safety Requirements
unless you know the construction and clearance requirements.
Step-by-Step Guide
Step 1: 1️⃣ Choose the right location
Pick a spot with enough clearance around the trampoline or play equipment for safe access and fall zones. As a minimum, choose a site clear of tree roots, clotheslines, fences, retaining walls, and overhead branches.
A good backyard site should:
For trampolines, allow the manufacturer’s footprint plus at least 1 m of clear access around the outside while you work. For play areas, allow for the equipment footprint plus softfall or circulation zones.
💡 Starting on the flattest part of the yard saves time, reduces spoil, and often avoids needing imported fill.
Step 2: 2️⃣ Set out the area and check levels
Mark the perimeter with pegs and string line. For a round trampoline, mark a square or circle slightly larger than the frame. For a play area, set out the full pad plus edging if used.
Use a laser level or string line to measure the existing fall across the site. Record the high side and low side. This tells you how much material you need to cut or fill.
As a guide:
For most play surfaces, aim for the finished surface to be level across the equipment area, with the surrounding ground falling away at about 1:100 to 1:80 to shed water.
Step 3: 3️⃣ Decide on cut, fill, or a combination
The best result usually comes from a cut-and-fill balance rather than simply building up the low side. Cut the high side down and use suitable compactable fill on the low side.
General rule:
For stable DIY jobs:
💡 Topsoil is not a structural base. It is for plants, not for trampolines or swing sets.
Step 4: 4️⃣ Strip turf and remove soft topsoil
Remove grass and topsoil across the entire area plus at least 150–300 mm extra around the perimeter. Strip to firm subgrade.
Typical stripping depth:
You can do this by hand with a spade and mattock for small sites. For larger areas, a 1.7 t mini excavator with a clean-up bucket makes the job much faster and cleaner.
Dispose of spoil, reuse it elsewhere in the garden, or stockpile it for edge reinstatement.
Step 5: 5️⃣ Shape the subgrade
Once the soft layer is removed, trim the subgrade to the target level. Cut the high side and lightly fill the low side with compactable material as needed.
Check levels continuously with the laser. The subgrade should be:
Typical build-ups:
If the native soil is soft or clayey, lay geotextile fabric before placing base material. This helps stop the base punching into the soil and improves long-term stability.
Step 6: 6️⃣ Fix drainage before you compact
If the site is wet, shaded, or low in the yard, solve drainage now rather than after the first storm. A level pad can still drain well if the surrounding ground falls away and the base is free-draining.
Options include:
Do not trap water by creating a flat “dish” with raised edges. The finished area should not become the lowest point in the backyard.
Council approval may be required if you are connecting drainage into legal points of discharge or materially altering stormwater flow.
Step 7: 7️⃣ Place base material in layers
Spread road base or other compactable granular fill in thin layers rather than one thick dump. This is the step that determines whether the surface stays level.
Recommended layer thickness:
Lightly wet dry material before compaction. It should be damp, not saturated. Compact each layer with a plate compactor in overlapping passes until it feels firm underfoot and no longer ruts easily.
For deeper fill on the low side:
💡 Hire vs buy: for a one-off backyard job, a plate compactor is almost always better to hire. Buying only starts to make sense if you regularly do paving, shed pads, or landscaping work. A mini excavator is also generally a hire item for homeowners, while ownership suits contractors or acreage users with ongoing projects.
Step 8: 8️⃣ Screed and fine-level the surface
Once the main base is compacted, apply a 20–30 mm layer of crusher dust or bedding material if you need a finer finish. Screed it using a straight edge to remove bumps and hollows.
Check level in multiple directions:
Target tolerance for a trampoline or small play frame:
This step is important because a slightly uneven base often shows up once the frame is assembled.
Step 9: 9️⃣ Compact the finished surface and test stability
Compact the final surface again and walk the entire area. There should be no rocking, soft spots, or visible pumping underfoot.
Test by placing a long straight edge or the actual equipment legs/frame layout on the pad. Check whether all legs or support points will sit evenly without packing random pavers underneath.
If the area is for a larger play set, test for:
Correct any defects now. Small imperfections are much easier to fix before installation.
Step 10: 🔟 Install edging, surfacing, and tidy the surrounds
For a dedicated play area, install edging to hold mulch, sand, or turf neatly in place. Reinstate surrounding lawn with topsoil and turf where you cut into the yard.
Suitable finishes include:
If the play equipment has a fall height that needs impact attenuation, choose surfacing that meets the intended performance requirements under AS 4422.
Step 11: 1️⃣1️⃣ Final safety check before use
Before the kids jump in:
If the ground settles after the first few weeks, top up and recompact early before the tilt becomes worse.
Common Mistakes to Avoid
It settles, stays soft, and becomes muddy. Always use compactable base material under the equipment area.
Dumping 100–150 mm all at once and compacting only the top leads to future settlement.
A level pad without drainage planning often turns into a puddle after rain.
Not allowing extra room around the trampoline or play set makes installation and maintenance harder.
Backyard service strikes are more common than people think. Always use 📞 Dial Before You Dig (1100) before excavating.
Pro Tips
Recommended Tools
Frequently asked questions
- What is the best base material for levelling ground under a trampoline or play area in Australia?
- The best base material for levelling ground under a trampoline or play area in Australia is a well-compacting aggregate like DGB20 (Dense Graded Base, 20mm minus) or crushed rock. These materials offer excellent stability, drainage, and compaction properties, preventing settlement and ensuring a firm, safe surface for play equipment that complies with local council recommendations for hardstand bases.
- How deep should the compacted base be for a trampoline or kids' play area?
- For a stable and durable base for a trampoline or kids' play area, aim for a compacted depth of at least 100-150mm using suitable aggregate. This depth provides adequate structural support and prevents future settlement, especially when compacted in 50-75mm layers with a Wacker Neuson BS50-2 plate compactor, ensuring long-term stability for equipment like a Vuly Ultra trampoline.
- What Australian safety standards apply to levelling ground for children's play equipment?
- While there isn't a specific Australian Standard solely for ground levelling for domestic play equipment, AS 4685.0:2017 (Playgrounds and playground equipment – General safety requirements and test methods) outlines general safety principles. Ensuring a level, stable, and well-drained surface free from trip hazards is crucial for meeting these broader safety objectives and preventing injuries, particularly around equipment like a Springfree trampoline.
- How do I ensure proper drainage when levelling ground for a play area?
- To ensure proper drainage when levelling ground for a play area, establish a slight fall of 1-2% (e.g., 10-20mm per metre) away from the centre or primary structure, directing water to a suitable run-off area or ag-pipe system. This prevents water pooling, which can lead to muddy conditions, equipment instability, and mosquito breeding, protecting your investment in a Plum Play swing set.
- What is the recommended compaction method for a stable trampoline base?
- The recommended compaction method for a stable trampoline base involves compacting the chosen aggregate (e.g., DGB20) in layers of no more than 75mm using a plate compactor, such as a Wacker Neuson BS50-2 or similar 60kg model. Each layer should be moistened slightly before compaction to achieve optimal density and prevent future settlement, ensuring the base can support dynamic loads from jumping.
- Can I use a hand tamper instead of a plate compactor for small areas?
- Yes, a Trojan hand tamper can be used for very small areas or tight corners (e.g., less than 1 square metre) where a plate compactor cannot reach, but it requires significantly more effort and may not achieve the same consistent compaction density. For areas larger than 1 square metre, a hired plate compactor is strongly recommended for superior and more consistent results, crucial for a long-lasting base.
- What Australian standard applies to the fall zone around domestic play equipment?
- While there isn't a specific Australian Standard solely for domestic fall zones, AS 4685.0:2017 (Playgrounds and playground equipment – General safety requirements and test methods) provides general safety principles. This standard recommends a clear, impact-absorbing fall zone around equipment, free from obstructions, to minimise injury risk. For specific dimensions, always consult the play equipment manufacturer's instructions, such as those provided by Vuly or Springfree.
- How do you calculate the amount of road base needed for a level pad?
- To calculate the amount of road base, multiply the length by the width of the area by the desired compacted depth, then add 10-15% for compaction. For example, a 4m x 4m pad at 0.15m compacted depth requires (4m x 4m x 0.15m) 1.15 = approximately 2.76 cubic metres of DGB20. This calculation ensures sufficient material after compaction with a Wacker Neuson BS50-2 plate compactor.
- What is the recommended moisture content for compacting road base in Australia?
- The recommended moisture content for compacting road base, such as DGB20, is typically between 6-10% of its dry weight, known as 'optimum moisture content'. According to general civil engineering practices in Australia, this allows for maximum compaction density. Applying water with a garden hose and allowing it to soak in for 30-60 minutes before using a plate compactor like the Wacker Neuson BS50-2 is a common method to achieve this.
Written by Digger, the Earthmoving & Landscaping specialist at VIC.Tools.