How to renovate a bathroom

Learn how to renovate a bathroom to Australian standards. Expert trade guide covering demolition, AS/NZS 3500 rough-in, waterproofing, and fit-off stages.

Quick answer

Renovating an Australian bathroom involves systematic demolition, drainage and water rough-in, waterproofing coordination, tiling, and fixture fit-off. All plumbing must comply with AS/NZS 3500 and the Plumbing Code of Australia. Water supply and drainage modifications require execution and certification by a state-licensed plumbing practitioner.

Skill level
Advanced
Time
5–15 days depending on demolition extent, structural changes, waterproofing sequencing, tiling program and fixture complexity
Trade
Plumbing
Updated
28 November 2026

Tools you will need

  • Rothenberger Rocase - Hydrostatic Pressure Testing Pump
  • Milwaukee M12 Force Logic - PEX Crimp Tool
  • DeWalt DCH273N-XJ 18V XR - Brushless SDS Plus Rotary Hammer Drill
  • Bosch GLL 3-80 C - 360 Degree Multi-Line Laser Level
  • Ox Tools Pro - Sanitary Silicone Profiling Kit
  • Ridgid 2006 Faucet and Sink Installer - Basin Wrench Tool

πŸ”§ Bathroom Renovation Trade Guide for Australian Plumbing Professionals

What is involved in renovating a bathroom in Australia?

Bathroom renovations involve multiple plumbing stages including demolition, set-out, rough-in, waterproofing coordination, fit-off and commissioning. A successful project depends on correct planning, compliance with the PCA, AS/NZS 3500, fixture set-out accuracy, drainage falls, waterproofing interfaces and fixture selection to suit performance and water efficiency requirements.

Plumbing work in Australia must be performed by a licensed plumber. This guide explains the process and helps you select the right tools and materials. Licensing requirements vary by state, including NSW Fair Trading, VIC VBA, QLD QBCC and WA Building Commission, and any gas work requires a separate gas fitter licence.

What skill level is required for an Australian bathroom renovation?

Advanced β€” Estimated time: 5–15 days depending on demolition extent, structural changes, waterproofing sequencing, tiling program and fixture complexity

What essential tools are needed for plumbing a bathroom renovation?

Pipe cutters suitable for 15 mm, 20 mm and 25 mm copper and PEX
Press tool with jaws for common copper and PEX press profiles
PEX crimp tool and go/no-go gauge where crimp systems are used
PVC saw and deburring tool for DWV pipework in 40 mm, 50 mm, 65 mm, 80 mm and 100 mm
Laser level for fixture set-out, waste positioning and finished floor level checks
Rotary hammer with masonry bits and chase bits
Core drill set for slab or wall penetrations
Inspection camera for existing drainage and concealed services
Digital spirit level and fall gauge for waste and floor grading
Pressure test pump for water rough-in testing
Pipe freezing kit or isolation tools where partial live-system works are required
Basin wrench and backnut spanners for tight fit-off areas
Hole saw kit for tap bodies, shower mixers and cabinetry penetrations
Silicone applicator tools for sanitary sealing
Bucket, wet vac and containment sheeting for demolition and clean-up
PPE including gloves, eye protection, hearing protection, respirator and knee pads

Materials Required

Water pipe in approved systems such as copper tube or PEX to AS/NZS 3500 and manufacturer specifications
Typical water service sizes: 15 mm branches to fixtures, 20 mm group feeds, 25 mm where required by hydraulic design
DWV pipe and fittings to AS/NZS 1260 or relevant product standard in 40 mm basin waste, 50 mm floor waste and shower waste, 80 mm branch drain, 100 mm WC pan connection and sanitary drain
Floor waste gully or puddle flange compatible with waterproofing system
Watermarked pan connector suited to pan set-out
Isolation valves for hot and cold services
Mini stops for basin and cistern supplies where specified
Shower mixer body, basin mixer or tap set, bath outlet and accessories
WC suite, in-wall cistern or close-coupled cistern as specified
Vanity basin, bath and shower waste assemblies
Tempering valve or thermostatic mixing valve where required for personal hygiene outlets in accordance with AS/NZS 3500.4
Backflow protection as required by hazard rating and local authority requirements
Acoustic lagging or pipe insulation where required in multi-residential or NCC acoustic applications
Waterproofing-compatible puddle flanges, collars and sealants
Fire collars and fire stopping materials for penetrations where required
Silicone sanitary sealant, thread sealant and approved joint lubricant
Pipe clips, brackets and nogging supports for secure fixing
Hot water connection materials including flex connectors only where compliant and accessible
WELS-rated fixtures and fittings, typically 4-star to 6-star taps and showers, 4-star or higher toilets where specified

Safety Requirements

Plumbing work in Australia must be performed by a licensed plumber. This guide explains the process and helps you select the right tools and materials.
Confirm all work complies with the Plumbing Code of Australia, AS/NZS 3500, local water authority requirements and manufacturer installation instructions.
Isolate water, power and gas before demolition or disconnection works.
Gas appliance relocation or gas line alteration requires a licensed gas fitter.
Verify wall and floor locations for electrical, gas and structural services before chasing or cutting.
Use silica dust controls during demolition, chasing and drilling.
Coordinate with the waterproofer to maintain membrane continuity around all penetrations and floor wastes.
Test rough-in pipework before closing walls and floors.
Maintain safe access, manual handling controls and site containment during demolition.
Ensure sanitary drainage venting, trap seal protection and fixture discharge unit loading comply with AS/NZS 3500.2.
Confirm heated water delivery temperatures are controlled in accordance with AS/NZS 3500.4.
In strata, apartment or commercial settings, confirm isolation, shutdown approvals and acoustic/fire-rating requirements before starting.

Step-by-Step Guide

Step 1: Site inspection, scope confirmation and compliance review

Start by confirming the renovation scope against the existing bathroom layout, architectural plans, hydraulic requirements and client selections. Identify whether the project is a like-for-like refit or includes fixture relocation, slab penetration, wall chasing, bath addition, in-wall cistern installation or drainage reconfiguration.

Inspect the existing water, sanitary drainage and venting arrangement. Establish connection points, pipe material types, water pressure, hot water capacity and whether tempering or pressure limiting upgrades are required. In older stock, check for non-compliant S-traps, undersized wastes, poor falls, inaccessible junctions or corrosion in galvanized and copper services.

Confirm relevant authority and compliance requirements early. Multi-residential and commercial projects may also require acoustic treatment, penetration fire stopping, backflow review and strata approvals.

Step 2: Measure-up, fixture set-out and hydraulic planning

Accurate set-out is critical to avoid clashes and poor fit-off. Mark centre lines for the WC, vanity, shower mixer, rose outlet, bath outlet, floor waste and any niches or in-wall cistern frames. Confirm pan set-out dimensions, vanity depth, finished wall thickness and tile build-up before rough-in.

Review fixture discharge requirements and size wastes accordingly. A typical bathroom may include 40 mm basin waste, 50 mm shower waste, 50 mm bath waste and 100 mm WC connection, but final sizing and layout must align with AS/NZS 3500.2 and fixture manufacturer data.

Plan water service runs to minimise dead legs, pressure loss and crossovers. Group hot and cold feeds neatly, allow service clearances and ensure mixer bodies are set to finished wall depth tolerances.

πŸ’‘ Select fixtures with strong WELS performance and local spare parts support. For most residential bathrooms, 4-star to 6-star WELS showers and taps offer good water efficiency without compromising customer expectations.

Step 3: Isolate services and carry out demolition

Shut down the hot and cold water supply, cap existing services and isolate power to affected areas. If gas appliances or gas pipework are nearby, ensure separation and licensed gas isolation where required.

Remove sanitary fixtures, shower screens, vanities, baths and exposed pipework carefully to preserve structural elements and any retained services. Strip wall linings and floor finishes as needed to access rough-in zones. Where existing drainage is to remain, inspect condition and verify invert levels and junction positions before proceeding.

During demolition, manage dust and slurry, and protect adjacent finished areas. Check for concealed damage such as rot, termite activity, cracked slab penetrations or failed previous waterproofing.

Step 4: Modify drainage and waste pipework

Set sanitary drainage first, as all other fixture locations depend on it. Install or alter branch drains to suit the new layout, maintaining compliant falls, fixture trap positions and venting requirements. Typical bathroom drainage alterations may include relocating a shower waste to centre, repositioning a vanity waste, resetting a floor waste and changing the WC pan connection.

Use approved DWV materials and fittings with long-radius changes of direction where practical. Ensure floor waste and shower waste locations suit screed falls and tile layout. A poorly positioned floor waste can create waterproofing and grading issues later in the build.

If working in slab-on-ground construction, verify cut depths, reinforcement impact and engineer requirements before trenching or coring. In timber floors, confirm joist penetrations meet structural rules and install support and acoustic isolation where required.

πŸ’‘ In renovations, camera-inspect downstream drainage before tie-in. It is far cheaper to identify partial blockages or poor historical workmanship before the room is rebuilt.

Step 5: Rough-in hot and cold water services

Run hot and cold water pipework to all fixtures including the vanity, shower, bath, cistern and accessories requiring water connection. Secure all pipework with proper clipping, allow for thermal movement where relevant and maintain separation from electrical services.

Set mixer bodies and outlets precisely to finished wall datum. Incorrect rough-in depth is one of the most common causes of difficult fit-off and poor trim presentation. For shower and bath mixers, use manufacturer rough-in tolerances and check tile plus adhesive thickness before final fixing.

Install accessible isolation where possible. Use compliant connection methods for the selected piping system and avoid burying non-approved or inaccessible joints.

Pressure test the rough-in before wall closure. Record results if required by the project QA process or certifier.

Step 6: Coordinate framing, sheeting and penetration details

Before wall sheeting, verify all noggings, cistern frames, wall-hung fixture supports and mixer backing plates are securely installed. Confirm outlet positions, bracket heights and face projections match the selected sanitaryware and tapware.

All pipe and waste penetrations through floors and walls must be neat, supported and compatible with the waterproofing system. Install puddle flanges, sleeves or collars as required. This stage is where coordination between plumber, builder and waterproofer has the biggest effect on final quality.

In apartment and classed buildings, address acoustic lagging, fire collars and fire stopping at penetrations before close-up.

Step 7: Waterproofing coordination and floor waste preparation

The waterproofer relies on correct plumbing preparation. Ensure the floor waste body, puddle flange, shower waste and penetrations are fixed firmly, clean and ready for membrane application. Waste outlet heights must suit screed and tile build-up so that grates finish flush and drainage remains effective.

Do not leave excessive gaps around penetrations. Any movement or poor support at the waste flange can compromise the membrane and create leaks. Confirm shower floor grades direct water effectively to the waste without ponding.

⚠️ Waterproofing itself is generally a separate licensed/specialist trade in many projects, but plumbing penetrations must be coordinated so the membrane system remains compliant and warrantable.

Step 8: Fit-off sanitary fixtures and tapware

Once waterproofing, tiling and joinery are complete, return for final fit-off. Install the WC pan and cistern, vanity basin, mixer tapware, shower trim, bath outlet, wastes, traps and accessories. Check all finished surfaces for damage risk and use proper protection during installation.

Set the WC with the correct pan connector and verify full seal integrity. Connect basin and bath wastes with accessible trap arrangements where required. Install mini stops and flexible connectors only if compliant, accessible and suitable for the application.

Apply sanitary-grade silicone to fixture interfaces as specified, without obstructing maintenance access or drainage provisions. Ensure all trim plates sit square and flush, and all fixtures are level.

Step 9: Connect hot water, tempering and commissioning items

Confirm the bathroom is supplied by a compliant hot water system and that delivery temperatures to personal hygiene fixtures meet AS/NZS 3500.4 requirements. Where required, install or verify a tempering valve or thermostatic mixing valve and test the outlet temperature.

If the renovation increases demand by adding a bath, double shower or additional fixtures, assess whether the existing hot water unit remains suitable. In many upgrades, undersized storage or poor pressure balance becomes apparent only after fit-off unless checked early.

Check shower performance, basin flow, cistern fill, bath fill rate and simultaneous demand effects. Verify there is no excessive pressure, hammer or temperature fluctuation.

Step 10: Test, inspect and hand over

Commission the full bathroom thoroughly. Test every fixture for leaks under static and dynamic conditions. Flood-test shower and floor drainage performance visually where appropriate, confirm trap seals hold, and ensure there is no gurgling or evidence of venting deficiency.

Inspect all visible joints, silicone lines, pan stability, waste grate levels, trap alignment and access to serviceable items. Confirm WELS ratings and model details for client documentation. Where certification is required, provide compliance documentation in line with state requirements.

Clean the work area, remove debris, explain isolation points and maintenance requirements to the client or builder, and note any limitations relating to pre-existing infrastructure retained outside the renovation zone.

Common Mistakes to Avoid

1.Roughing in mixer bodies and outlets without allowing for final wall build-up, resulting in poor trim fit or non-compliant installation depth.
2.Using incorrect waste sizes or inadequate falls, especially on shower and bath wastes, causing slow discharge and trap issues.
3.Failing to coordinate penetrations and waste flange preparation with the waterproofing contractor, leading to membrane failure and leaks.
4.Reusing deteriorated existing drainage or water pipework without condition assessment, particularly in older homes with corrosion or poor historical alterations.
5.Overlooking tempering requirements, pressure limiting, acoustic treatment or fire stopping in multi-residential and higher-specification projects.

Pro Tips

πŸ’‘ Carry out a full fixture set-out on walls and floors before any rough-in. This avoids clashes with vanities, shaving cabinets, niches and frameless screens.
πŸ’‘ Use laser levels to set all trim heights consistently, especially in bathrooms with feature tile lines or wall-hung vanities.
πŸ’‘ Preselect WC suite and cistern models early. Pan set-out and in-wall frame dimensions can affect the entire room layout.
πŸ’‘ In renovation work, always verify existing downstream drainage capacity and condition before connecting new sanitary fixtures.
πŸ’‘ Recommend high-WELS fixtures with proven service support. A 4-star or better toilet and 4-star to 6-star tapware/showerware can improve water efficiency and appeal to clients without sacrificing usability.

Recommended Tools

Milwaukee M12/M18 Press Tool β€” reliable for copper and approved press systems in tight bathroom rough-in spaces
REMS or Rothenberger Pipe Cutter Set β€” clean, accurate cuts on copper and multilayer pipe
Stabila Laser Level β€” essential for accurate fixture set-out, waste positioning and trim alignment
Ridgid SeeSnake or compact inspection camera β€” useful for checking existing drainage before tie-in
Knipex Cobra pliers and basin wrench set β€” ideal for fit-off in confined vanity and cistern spaces

Frequently asked questions

What Australian standards apply to bathroom renovations?
Bathroom renovations must comply with AS/NZS 3500 for plumbing and drainage, AS 3740 for waterproofing wet areas, and the National Construction Code Volume Three. Water supply pipes must meet AS/NZS 3500.1, sanitary drainage requires AS/NZS 3500.2, and all installed fixtures must carry WaterMark certification and appropriate WELS ratings.
What is the correct order of trades for a bathroom renovation?
A standard bathroom renovation follows a strict sequence: strip-out and demolition, structural alterations, plumbing and electrical rough-in, wall sheeting, waterproofing, wall and floor tiling, grouting, and final trade fit-off. Plumbers must pressure test pipework prior to sheeting and coordinate puddle flange heights with the waterproofer before membrane application.
What are the minimum fall requirements for bathroom drainage in Australia?
Sanitary drainage pipes under AS/NZS 3500.2 require a minimum grade of 1.65% (1 in 60) for DN65 pipes and 2.50% (1 in 40) for DN40 to DN50 pipes. Shower floors require a continuous fall towards the waste outlet between 1:60 and 1:80 to ensure complete drainage without ponding.
Can a homeowner do their own bathroom plumbing in Australia?
No, homeowners cannot legally carry out regulated plumbing or drainage work in Australia. State regulators including NSW Fair Trading, the Victorian Building Authority, and QBCC mandate that all drinking water supply, sanitary drainage, and gasfitting work be completed by a licensed plumber who issues a Compliance Certificate upon completion.
How do you avoid common bathroom rough-in mistakes?
Avoid common rough-in mistakes by calculating finished wall thicknesses before setting mixer depths, including tile and adhesive allowances. Ensure shower mixer bodies sit flush within manufacturer tolerances, install nogging support to prevent pipe movement, and fit test plugs to hydrostatic pressure test all lines before wall linings are installed.
How long does a full bathroom plumbing renovation take?
Plumbing work on a typical bathroom renovation takes between 5 to 15 working days spread across multiple trade phases. The initial rough-in typically takes one to two days, with the final fit-off requiring one day after tiling, while intermediate inspection, drying, and waterproofing stages dictate the overall schedule.

Written by Pipey, the Plumbing specialist at VIC.Tools.