How to Rough-In Plumbing for a New Home Build
Rough-in plumbing for a new home build sets the entire water, sanitary drainage, venting and fixture connection layout before wall and floor linings are installed. This stage must be coordinated tightly with the builder, slab/set-out, framing, electrical and HVAC trades to ensure compliant pipe fall
- Skill level
- Advanced
- Time
- 2 days to 2 weeks, depending on house size, slab type, number of wet areas, and authority inspection sequencing.
- Trade
- Plumbing
- Updated
- 29 November 2026
Tools you will need
- Pipe laser or line laser for long drainage runs
- PVC pipe cutters and fine
- PEX crimp tool or press
- Hole saw kit for timber and steel framing penetrations
- Right
- Deburring and chamfering tools for PVC and copper
- Tape measure, chalk line and permanent markers
- Spirit levels and digital level
- Pipe stands, clamps and temporary supports
- Inspection camera or phone/tablet for as
🔧 Rough-In Plumbing for a New Home Build — Professional Trade Guide
What is rough-in plumbing for a new home build in Australia?
Rough-in plumbing for a new home build sets the entire water, sanitary drainage, venting and fixture connection layout before wall and floor linings are installed. This stage must be coordinated tightly with the builder, slab/set-out, framing, electrical and HVAC trades to ensure compliant pipe falls, penetrations, support spacing and future access.
Plumbing work in Australia must be performed by a licensed plumber. This guide explains the process and helps you select the right tools and materials. All work should comply with the Plumbing Code of Australia (PCA) and relevant AS/NZS 3500 parts, with licensing requirements administered by NSW Fair Trading, VIC VBA, QLD QBCC and WA Building Commission. Gas rough-in, if included, requires a separate gas fitter licence.
What skill level is required for rough-in plumbing in Australia?
Advanced — Estimated time: 2 days to 2 weeks, depending on house size, slab type, number of wet areas, and authority inspection sequencing.
What essential tools are needed for rough-in plumbing in Australia?
Materials Required
Safety Requirements
Step-by-Step Guide
Step 1: Review hydraulic design, plans and authority requirements
Start by reviewing the architectural, hydraulic, structural and slab/framing drawings together. Confirm fixture locations, wet area layouts, sewer point of connection, water meter location, hot water unit position, external hose taps, rainwater integration, and any recycled water provisions.
Check the approved drainage layout, venting strategy, invert levels, inspection openings and overflow relief gully requirements where applicable. Verify local authority and water authority conditions, including backflow containment, minimum cover, boundary trap requirements if relevant to the jurisdiction, and inspection hold points.
For bathroom renovation-style wet area planning within a new home context, lock down vanity, shower, bath and WC set-outs early. Small set-out changes later can affect floor grading, framing penetrations and waterproofing details.
Step 2: Set out all fixtures, drains and water points on site
Transfer plan dimensions onto the slab, subfloor or frame using a laser, tape and chalk line. Mark centre lines for WCs, vanities, showers, baths, kitchen sink, laundry tub, washing machine points, external taps and hot water services.
Identify vertical riser locations in walls and stacks. Mark sanitary drain routes to maintain compliant falls under AS/NZS 3500.2, ensuring practical access for testing and future maintenance. Check that framing, slab beams and bracing locations will not conflict with pipes.
For bathrooms, verify:
💡 Confirm final fixture schedules and shop drawings before cutting any slab or frame. Imported fixtures and custom vanities often differ from nominal Australian rough-in dimensions.
Step 3: Install below-ground sanitary drainage
Excavate and prepare below-slab or below-ground drain trenches to the designed depths. Lay bedding where required, then install 100 mm main sanitary drains and branch drains with compliant fall and alignment.
Use long sweep junctions and bends to promote flow and serviceability. Position inspection openings so they remain accessible after completion. For WC branches, maintain direct runs where possible and avoid unnecessary changes of direction. Connect shower, bath, basin and floor wastes using correctly sized branches, commonly 50 mm for showers and baths and 40 mm or 50 mm for basins depending on fixture load and design.
At this stage, install:
All penetrations through slab edge beams or footings must be approved before installation.
Step 4: Install venting and stack provisions
Set out vent lines in accordance with the drainage design and AS/NZS 3500.2. Ensure trap arm lengths, discharge unit loads and branch arrangements are suitable for the selected venting method.
Run 50 mm, 65 mm, 80 mm or 100 mm vents as designed, keeping offsets to a minimum. Coordinate stack positions so they remain within service cavities and avoid clash with windows, bulkheads and roof framing.
For multi-bathroom layouts, consider acoustic treatment around stacks near bedrooms or living areas. Lag stacks where specified to reduce noise transmission.
💡 A well-positioned vent stack saves time later in roof rough-in and reduces the need for awkward offsets that can create framing conflicts.
Step 5: Install cold water and hot water rough-in
Run the incoming cold water main from the meter point using the specified system, commonly copper, PEX or multilayer. Typical residential branch sizes are 20 mm or 25 mm mains reducing to 15 mm branches, subject to fixture loading and design calculations under AS/NZS 3500.1.
Install hot and cold branches to:
Provide isolation valves at appropriate locations for serviceability. Route hot water lines efficiently to reduce heat loss and dead legs. Allow for tempering valve distribution to bathrooms and personal hygiene fixtures, generally limiting delivery temperature in line with AS/NZS 3500.4 requirements.
Where a manifold system is used, label each circuit clearly and protect concealed tubing from abrasion and UV exposure during construction.
Step 6: Rough-in bathroom, kitchen and laundry fixture points
Bring all water and waste points to precise rough-in positions for the final fixtures. In bathrooms, set mixer bodies, shower breeches, wall basin outlets and in-wall cistern frames exactly to manufacturer dimensions.
Typical rough-in considerations include:
For kitchens and laundries, align sink wastes and water points with cabinet shop drawings. Provide allowances for water filters, ice-maker points and appliance clearances where documented.
💡 Always rough to the actual selected fixture, not a generic template. Custom joinery and imported tapware can vary significantly.
Step 7: Protect, support and identify pipework
Clip and support all pipework to manufacturer requirements and relevant standards. Prevent sagging, stress on fittings and movement during pressure testing or wall closure.
Fit nail plates where pipes pass close to wall faces. Sleeve pipes through masonry and slab penetrations. Separate water services from heated surfaces, electrical conduits and sharp framing edges. Label hot, cold, recycled water and future connection points where applicable.
In acoustic-sensitive areas, isolate pipe brackets and avoid hard contact that can transmit water hammer or discharge noise.
Step 8: Coordinate with other trades before close-up
Walk the job with the builder, frame contractor, electrician, HVAC installer and waterproofer before the walls are closed. Confirm access around:
Check that no plumbing points obstruct cabinetry, noggings, ductwork or tile set-outs. Confirm shower wastes and floor wastes align with screed and waterproofing falls. Resolve clashes now, not after sheeting.
This stage is also where you should photograph all pipe runs, junctions and concealed valves for as-built documentation and future maintenance reference.
Step 9: Pressure test water services and test sanitary drainage
Cap all water points and pressure test the cold and hot water rough-in in accordance with system manufacturer requirements and AS/NZS 3500.1. Monitor for pressure drop and inspect every joint, manifold and valve.
For drainage, conduct water or air testing as permitted and required by the authority or certifier under AS/NZS 3500.2. Ensure all caps, plugs and inspection points are secure before filling or pressurising the system.
Record test results and rectify any leaks immediately. Do not leave untested rough-in concealed.
Step 10: Final inspection, compliance and handover to lock-up stage
Carry out a final rough-in inspection against plans, fixture schedule and code requirements. Confirm all points are plumb, level, secure, identified and protected. Verify that future fit-off access is practical and all mandatory valves and test points remain accessible.
Complete required compliance documentation for the jurisdiction and arrange inspection if required by the certifier or authority. Typical licensing oversight is through NSW Fair Trading, VIC VBA, QLD QBCC and WA Building Commission.
Only release the area for wall and floor closure once testing, inspection and coordination are complete.
Common Mistakes to Avoid
Pro Tips
Recommended Tools
🔒 Licensing
Plumbing work in Australia must be performed by a licensed plumber. This guide explains the process and helps you select the right tools and materials. Gas work requires a separate gas fitter licence.
Frequently asked questions
- What is involved in rough-in plumbing for a new home build?
- Rough-in plumbing for a new home build sets the entire water, sanitary drainage, venting and fixture connection layout before wall and floor linings are installed. This stage must be coordinated tightly with the builder, slab/set-out, framing, electrical and HVAC trades to ensure compliant pipe fall
- What skill level do I need for rough-in plumbing for a new home build?
- Advanced — Estimated time: 2 days to 2 weeks, depending on house size, slab type, number of wet areas, and authority inspection sequencing.
- What are common mistakes when rough-in plumbing for a new home build?
- 1. Setting fixture points from nominal plans instead of manufacturer shop drawings, leading to misaligned mixers, wastes and cabinetry. 2. Insufficient fall on sanitary drains or creating backfalls after late structural or framing changes. 3. Overcrowding service penetrations in studs and noggings without protection plates or structural approval. 4. Failing to allow for finished wall and floor thi
- What tools do I need for rough-in plumbing for a new home build?
- This guide includes a comprehensive tools list. Key plumbing tools are detailed in the Tools Required section.
- What is the Australian standard for rough-in plumbing?
- The primary Australian standard for rough-in plumbing is AS/NZS 3500, which comprises multiple parts covering water services, sanitary plumbing and drainage, and heated water services. This standard, along with the Plumbing Code of Australia (PCA), dictates requirements for pipe sizing, materials, installation methods, and testing. Always refer to the latest edition and state-specific amendments.
- How long does rough-in plumbing typically take for a new home build?
- Rough-in plumbing for a new home build typically takes between 2 days and 2 weeks. This timeframe varies significantly based on the house size, complexity of wet areas (bathrooms, kitchens, laundries), the type of slab (e.g., concrete vs. raised floor), and the sequence of required authority inspections. Larger, multi-level homes with numerous fixtures will naturally require more time.
- What are common mistakes to avoid during plumbing rough-in?
- Common mistakes include setting fixture points from generic plans instead of precise manufacturer shop drawings, leading to misalignment. Another frequent error is insufficient fall or creating backfalls in sanitary drains due to late structural changes. Overcrowding service penetrations in framing without proper protection plates or engineering approval is also a significant issue, compromising structural integrity and compliance.
Written by Pipey, the Plumbing specialist at VIC.Tools.