How to Rough-In Plumbing for a New Home Build

Rough-in plumbing for a new home build sets the entire water, sanitary drainage, venting and fixture connection layout before wall and floor linings are installed. This stage must be coordinated tightly with the builder, slab/set-out, framing, electrical and HVAC trades to ensure compliant pipe fall

Skill level
Advanced
Time
2 days to 2 weeks, depending on house size, slab type, number of wet areas, and authority inspection sequencing.
Trade
Plumbing
Updated
29 November 2026

Tools you will need

  • Pipe laser or line laser for long drainage runs
  • PVC pipe cutters and fine
  • PEX crimp tool or press
  • Hole saw kit for timber and steel framing penetrations
  • Right
  • Deburring and chamfering tools for PVC and copper
  • Tape measure, chalk line and permanent markers
  • Spirit levels and digital level
  • Pipe stands, clamps and temporary supports
  • Inspection camera or phone/tablet for as

🔧 Rough-In Plumbing for a New Home Build — Professional Trade Guide

What is rough-in plumbing for a new home build in Australia?

Rough-in plumbing for a new home build sets the entire water, sanitary drainage, venting and fixture connection layout before wall and floor linings are installed. This stage must be coordinated tightly with the builder, slab/set-out, framing, electrical and HVAC trades to ensure compliant pipe falls, penetrations, support spacing and future access.

Plumbing work in Australia must be performed by a licensed plumber. This guide explains the process and helps you select the right tools and materials. All work should comply with the Plumbing Code of Australia (PCA) and relevant AS/NZS 3500 parts, with licensing requirements administered by NSW Fair Trading, VIC VBA, QLD QBCC and WA Building Commission. Gas rough-in, if included, requires a separate gas fitter licence.

What skill level is required for rough-in plumbing in Australia?

Advanced — Estimated time: 2 days to 2 weeks, depending on house size, slab type, number of wet areas, and authority inspection sequencing.

What essential tools are needed for rough-in plumbing in Australia?

Rotary laser level with staff for setting sanitary drain invert levels and checking falls
Pipe laser or line laser for long drainage runs
PVC pipe cutters and fine-tooth saw
Copper tube cutter suitable for 15 mm, 20 mm and 25 mm
PEX crimp tool or press-fit tool compatible with the selected pipe system
Press tool with jaws for copper or multilayer systems where specified
Hole saw kit for timber and steel framing penetrations
Right-angle drill for stud and joist drilling
Reciprocating saw for framing penetrations where approved by builder/engineer
Deburring and chamfering tools for PVC and copper
Tape measure, chalk line and permanent markers
Spirit levels and digital level
Pipe stands, clamps and temporary supports
Inspection camera or phone/tablet for as-built records
Pressure test kit for water rough-in
Water test plugs, test balls and caps for DWV testing
Ladders, trestles or mobile scaffold as required
PPE: gloves, eye protection, hearing protection, high-vis, steel-cap boots

Materials Required

DWV PVC pipe to AS/NZS 1260 in typical sizes:
40 mm for basin and condensate branches where permitted
50 mm for shower, bath and floor waste branches
65 mm or 80 mm for graded fixture drains where designed
100 mm for WC pans, main sanitary drains and vent/drain stacks
150 mm where specified for larger buildings or combined drains
Pressure pipe systems for water supply to AS/NZS 3500.1 compatible manufacturer specifications:
Copper tube Type B or Type C in 15 mm, 20 mm, 25 mm
PEX or multilayer pipe in equivalent sizes, approved for concealed installation
DWV fittings: long radius bends, junctions, inspection openings, reducer junctions, pan bends, vent cowls
Water fittings: elbows, tees, unions, manifolds, isolation valves, hammer arrestors where required by design
Sleeves for slab or masonry penetrations
Pipe clips and brackets suitable for copper, PEX and PVC
Acoustic lagging for sanitary stacks and high-noise sections where specified
Pipe protection plates for stud penetrations near finished surfaces
Fire stopping products for penetrations in rated walls/floors where required
Primer and solvent cement for PVC
Flux, solder or press fittings for copper systems
Crimp rings or manufacturer-approved fittings for PEX systems
Trap set-outs, WC pan connector points and fixture outlet templates
Tempering valve allowance and hot water branchwork to bathrooms
Backflow prevention devices where required by hazard rating and authority conditions
Identification tape and labelling tags
Test caps, plugs and valves for inspection and commissioning
Water-efficient fixture provisions aligned with specified WELS ratings, commonly 4-star or higher taps and 3-star or higher showers where selected

Safety Requirements

Plumbing work in Australia must be performed by a licensed plumber. This guide explains the process and helps you select the right tools and materials.
Comply with the PCA, AS/NZS 3500.1, AS/NZS 3500.2, and where applicable AS/NZS 3500.4 for heated water services.
Confirm all penetrations through structural elements with the builder, frame supplier and engineer before cutting.
Isolate any live services before commencing alteration or tie-in work.
Use correct manual handling methods for bundles of pipe, fittings and hot water units.
Maintain site housekeeping to prevent slips and trips from offcuts, solvent spills and loose pipe.
Use eye and respiratory protection when cutting, drilling or solvent welding.
Pressure testing and water testing must be controlled to prevent sudden release of caps or plugs.
Hot works such as soldering require permit compliance and fire watch where applicable.
Gas rough-in must only be carried out by a licensed gas fitter.
Waterproofing interfaces in bathrooms must be coordinated with the waterproofer; do not compromise membrane set-outs with late pipe relocations.
Maintain safe separation from electrical services and coordinate with the electrician before wall closure.

Step-by-Step Guide

Step 1: Review hydraulic design, plans and authority requirements

Start by reviewing the architectural, hydraulic, structural and slab/framing drawings together. Confirm fixture locations, wet area layouts, sewer point of connection, water meter location, hot water unit position, external hose taps, rainwater integration, and any recycled water provisions.

Check the approved drainage layout, venting strategy, invert levels, inspection openings and overflow relief gully requirements where applicable. Verify local authority and water authority conditions, including backflow containment, minimum cover, boundary trap requirements if relevant to the jurisdiction, and inspection hold points.

For bathroom renovation-style wet area planning within a new home context, lock down vanity, shower, bath and WC set-outs early. Small set-out changes later can affect floor grading, framing penetrations and waterproofing details.

Step 2: Set out all fixtures, drains and water points on site

Transfer plan dimensions onto the slab, subfloor or frame using a laser, tape and chalk line. Mark centre lines for WCs, vanities, showers, baths, kitchen sink, laundry tub, washing machine points, external taps and hot water services.

Identify vertical riser locations in walls and stacks. Mark sanitary drain routes to maintain compliant falls under AS/NZS 3500.2, ensuring practical access for testing and future maintenance. Check that framing, slab beams and bracing locations will not conflict with pipes.

For bathrooms, verify:

WC pan set-out
Shower waste centre position
Vanity waste height and centre
Bath waste location
Mixer and outlet heights
Niches and in-wall cistern positions if specified

💡 Confirm final fixture schedules and shop drawings before cutting any slab or frame. Imported fixtures and custom vanities often differ from nominal Australian rough-in dimensions.

Step 3: Install below-ground sanitary drainage

Excavate and prepare below-slab or below-ground drain trenches to the designed depths. Lay bedding where required, then install 100 mm main sanitary drains and branch drains with compliant fall and alignment.

Use long sweep junctions and bends to promote flow and serviceability. Position inspection openings so they remain accessible after completion. For WC branches, maintain direct runs where possible and avoid unnecessary changes of direction. Connect shower, bath, basin and floor wastes using correctly sized branches, commonly 50 mm for showers and baths and 40 mm or 50 mm for basins depending on fixture load and design.

At this stage, install:

Fixture risers
Floor waste gullies where required
Overflow relief gully, if required by local authority
Vent connection points
Drain caps or test points

All penetrations through slab edge beams or footings must be approved before installation.

Step 4: Install venting and stack provisions

Set out vent lines in accordance with the drainage design and AS/NZS 3500.2. Ensure trap arm lengths, discharge unit loads and branch arrangements are suitable for the selected venting method.

Run 50 mm, 65 mm, 80 mm or 100 mm vents as designed, keeping offsets to a minimum. Coordinate stack positions so they remain within service cavities and avoid clash with windows, bulkheads and roof framing.

For multi-bathroom layouts, consider acoustic treatment around stacks near bedrooms or living areas. Lag stacks where specified to reduce noise transmission.

💡 A well-positioned vent stack saves time later in roof rough-in and reduces the need for awkward offsets that can create framing conflicts.

Step 5: Install cold water and hot water rough-in

Run the incoming cold water main from the meter point using the specified system, commonly copper, PEX or multilayer. Typical residential branch sizes are 20 mm or 25 mm mains reducing to 15 mm branches, subject to fixture loading and design calculations under AS/NZS 3500.1.

Install hot and cold branches to:

Basins
Showers
Baths
Kitchen sink
Dishwasher point
Laundry tub
Washing machine taps
External hose taps
Fridge points if required

Provide isolation valves at appropriate locations for serviceability. Route hot water lines efficiently to reduce heat loss and dead legs. Allow for tempering valve distribution to bathrooms and personal hygiene fixtures, generally limiting delivery temperature in line with AS/NZS 3500.4 requirements.

Where a manifold system is used, label each circuit clearly and protect concealed tubing from abrasion and UV exposure during construction.

Step 6: Rough-in bathroom, kitchen and laundry fixture points

Bring all water and waste points to precise rough-in positions for the final fixtures. In bathrooms, set mixer bodies, shower breeches, wall basin outlets and in-wall cistern frames exactly to manufacturer dimensions.

Typical rough-in considerations include:

Basin wastes centred to cabinet layouts
Shower mixer depth set for final tile thickness
Shower arm and head heights aligned with specification
WC water point positioned clear of cistern framing
Bath hob or freestanding bath filler rough-in coordinated with floor finish
Floor wastes set to finished floor heights

For kitchens and laundries, align sink wastes and water points with cabinet shop drawings. Provide allowances for water filters, ice-maker points and appliance clearances where documented.

💡 Always rough to the actual selected fixture, not a generic template. Custom joinery and imported tapware can vary significantly.

Step 7: Protect, support and identify pipework

Clip and support all pipework to manufacturer requirements and relevant standards. Prevent sagging, stress on fittings and movement during pressure testing or wall closure.

Fit nail plates where pipes pass close to wall faces. Sleeve pipes through masonry and slab penetrations. Separate water services from heated surfaces, electrical conduits and sharp framing edges. Label hot, cold, recycled water and future connection points where applicable.

In acoustic-sensitive areas, isolate pipe brackets and avoid hard contact that can transmit water hammer or discharge noise.

Step 8: Coordinate with other trades before close-up

Walk the job with the builder, frame contractor, electrician, HVAC installer and waterproofer before the walls are closed. Confirm access around:

Vanity cabinets
Wall-hung pans
Shower niches
Exhaust ducting
Switchboard walls
Bulkheads
Structural bracing

Check that no plumbing points obstruct cabinetry, noggings, ductwork or tile set-outs. Confirm shower wastes and floor wastes align with screed and waterproofing falls. Resolve clashes now, not after sheeting.

This stage is also where you should photograph all pipe runs, junctions and concealed valves for as-built documentation and future maintenance reference.

Step 9: Pressure test water services and test sanitary drainage

Cap all water points and pressure test the cold and hot water rough-in in accordance with system manufacturer requirements and AS/NZS 3500.1. Monitor for pressure drop and inspect every joint, manifold and valve.

For drainage, conduct water or air testing as permitted and required by the authority or certifier under AS/NZS 3500.2. Ensure all caps, plugs and inspection points are secure before filling or pressurising the system.

Record test results and rectify any leaks immediately. Do not leave untested rough-in concealed.

Step 10: Final inspection, compliance and handover to lock-up stage

Carry out a final rough-in inspection against plans, fixture schedule and code requirements. Confirm all points are plumb, level, secure, identified and protected. Verify that future fit-off access is practical and all mandatory valves and test points remain accessible.

Complete required compliance documentation for the jurisdiction and arrange inspection if required by the certifier or authority. Typical licensing oversight is through NSW Fair Trading, VIC VBA, QLD QBCC and WA Building Commission.

Only release the area for wall and floor closure once testing, inspection and coordination are complete.

Common Mistakes to Avoid

1.Setting fixture points from nominal plans instead of manufacturer shop drawings, leading to misaligned mixers, wastes and cabinetry.
2.Insufficient fall on sanitary drains or creating backfalls after late structural or framing changes.
3.Overcrowding service penetrations in studs and noggings without protection plates or structural approval.
4.Failing to allow for finished wall and floor thicknesses, especially in showers, in-wall cisterns and bath fillers.
5.Installing hot water branches with excessive dead legs, causing long wait times and poor water efficiency.
6.Omitting accessible inspection openings or isolating valves needed for maintenance.
7.Closing walls before pressure and drainage tests are completed and documented.

Pro Tips

1.💡 Set out bathrooms from finished tile lines and final fixture centres, not just frame dimensions.
2.💡 Run the hot water system as centrally as practical to reduce pipe lengths, heat loss and callback complaints.
3.💡 Use long-radius drainage fittings wherever space allows for better hydraulic performance and easier clearing.
4.💡 Photograph every wall before sheeting, including tape measure references from corners to concealed services.
5.💡 Where premium homes specify water efficiency, match rough-in sizing and pressure management to the selected WELS fixtures so performance remains acceptable at compliant flow rates.
6.💡 Pre-label all manifold lines and valve groups clearly to speed fit-off and future servicing.
7.💡 Coordinate shower waste position early with tile module and floor waste requirements to improve finish quality and waterproofing outcomes.

Recommended Tools

Stabila LAX/rotary laser level — reliable set-out and fall checking across slab and frame stages
Milwaukee or RIDGID press tool kit — efficient and repeatable joining for compliant press-fit systems
REMS or Rothenberger PEX crimp/expansion tool — system-specific rough-in speed and consistency
RIDGID micro drain camera — useful for inspection, fault finding and documenting drainage runs
Knipex pipe cutter and deburring set — clean cuts and better joint preparation across copper and plastic systems

🔒 Licensing

Plumbing work in Australia must be performed by a licensed plumber. This guide explains the process and helps you select the right tools and materials. Gas work requires a separate gas fitter licence.

Frequently asked questions

What is involved in rough-in plumbing for a new home build?
Rough-in plumbing for a new home build sets the entire water, sanitary drainage, venting and fixture connection layout before wall and floor linings are installed. This stage must be coordinated tightly with the builder, slab/set-out, framing, electrical and HVAC trades to ensure compliant pipe fall
What skill level do I need for rough-in plumbing for a new home build?
Advanced — Estimated time: 2 days to 2 weeks, depending on house size, slab type, number of wet areas, and authority inspection sequencing.
What are common mistakes when rough-in plumbing for a new home build?
1. Setting fixture points from nominal plans instead of manufacturer shop drawings, leading to misaligned mixers, wastes and cabinetry. 2. Insufficient fall on sanitary drains or creating backfalls after late structural or framing changes. 3. Overcrowding service penetrations in studs and noggings without protection plates or structural approval. 4. Failing to allow for finished wall and floor thi
What tools do I need for rough-in plumbing for a new home build?
This guide includes a comprehensive tools list. Key plumbing tools are detailed in the Tools Required section.
What is the Australian standard for rough-in plumbing?
The primary Australian standard for rough-in plumbing is AS/NZS 3500, which comprises multiple parts covering water services, sanitary plumbing and drainage, and heated water services. This standard, along with the Plumbing Code of Australia (PCA), dictates requirements for pipe sizing, materials, installation methods, and testing. Always refer to the latest edition and state-specific amendments.
How long does rough-in plumbing typically take for a new home build?
Rough-in plumbing for a new home build typically takes between 2 days and 2 weeks. This timeframe varies significantly based on the house size, complexity of wet areas (bathrooms, kitchens, laundries), the type of slab (e.g., concrete vs. raised floor), and the sequence of required authority inspections. Larger, multi-level homes with numerous fixtures will naturally require more time.
What are common mistakes to avoid during plumbing rough-in?
Common mistakes include setting fixture points from generic plans instead of precise manufacturer shop drawings, leading to misalignment. Another frequent error is insufficient fall or creating backfalls in sanitary drains due to late structural changes. Overcrowding service penetrations in framing without proper protection plates or engineering approval is also a significant issue, compromising structural integrity and compliance.